SH 31 SH 31/BS 31D Split to FM 1393
0163-01-072 · let Oct 9, 2025 · Navarro, Dallas · Seal Coat
$14,985,368Low bid: CLARK CONSTRUCTION OF TEXAS, INC.-23.2% vs estimate $19,507,649
$1,320,914Left on the table8.8% gap to the second bid
2BiddersSpread 9% low to high
536Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CLARK CONSTRUCTION OF TEXAS, INC. | $14,985,368 | -23.2% | $1,320,914 | 3+$1,958,760 | 0 | |
| 2 | NORTHEASTERN PAVERS, LLC | $16,306,282 | +8.8% | -16.4% | 4+$2,951,986 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
CLARK CONSTRUCTION OF TEXAS, INC. vs NORTHEASTERN PAVERS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 316-7087 ASPH (AC-15P, AC-20-5TR OR AC-20XP) | 5,726.04 TON | $595.25 | $690.00 | $595.25 | $542,542 |
| 344-7009 SP MIXES SP-C PG64-22 | 5,055 TON | $203.00 | $275.00 | $131.13 | $363,960 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $25,000.00 | $61,250.00 | $11,585.04 | $290,000 |
| 500-7001 MOBILIZATION | 1 LS | $2,286,000.00 | $2,000,000.00 | $523,850.32 | -$286,000 |
| 354-7051 PLANE ASPH CONC PAV(2") | 45,955 SY | $3.80 | $9.50 | $1.86 | $261,944 |
| 316-7236 AGGR (TY-PL, GR-3 LTWT)(SAC-B) | 15,789 CY | $186.36 | $195.00 | $168.60 | $136,417 |
| 316-7238 AGGR (TY-PL, GR-4)(SAC-B) | 12,719 CY | $175.29 | $185.00 | $163.01 | $123,501 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 1,699,163 LF | $0.5000 | $0.4400 | $0.4757 | -$101,950 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 1,215,375 LF | $0.5000 | $0.4600 | $0.4986 | -$48,615 |
| 666-7279 RE PROF PM (W)6"(SLD) RAISD PROF ONLY | 718,936 LF | $0.2800 | $0.2500 | $0.2873 | -$21,568 |
| 666-7184 RE PM TY II (W) 24" (SLD) | 9,093 LF | $4.00 | $6.25 | $3.83 | $20,459 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 20,154 EA | $0.0100 | $1.00 | $0.5715 | $19,952 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 1,576,520 LF | $0.1600 | $0.1500 | $0.1701 | -$15,765 |
| 344-7077 TACK COAT | 5,055 GAL | $1.00 | $4.00 | $3.25 | $15,165 |
| 677-7002 ELIM EXT PM & MRKS (6") | 58,272 LF | $0.7500 | $0.5000 | $0.2755 | -$14,568 |
| 672-7004 REFL PAV MRKR TY II-A-A | 14,831 EA | $5.00 | $4.05 | $3.97 | -$14,089 |
| 666-7280 RE PROF PM (Y)6"(SLD) RAISD PROF ONLY | 441,213 LF | $0.2800 | $0.2500 | $0.2862 | -$13,236 |
| 302-7007 LOAD, HAUL & DELIVERY OF AGGREGATE | 50 MI | $125.00 | $350.00 | $137.50 | $11,250 |
| 677-7030 ELIM EXT PM & MRKS (RUMBLE STRIP) | 558,544 LF | $0.1600 | $0.1800 | $0.1262 | $11,171 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 2,268 LF | $6.00 | $10.50 | $7.19 | $10,206 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,290,776 of the $1,320,914 gap.
CLARK CONSTRUCTION OF TEXAS, INC.: unbalanced items
Placed 1NORTHEASTERN PAVERS, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,000,000.00 | $523,850.32 | 3.82x | $1,476,150 |
| 344-7009 SP MIXES SP-C PG64-22 | 5,055 TON | $275.00 | $131.13 | 2.10x | $727,283 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $61,250.00 | $11,585.04 | 5.29x | $397,320 |
| 354-7051 PLANE ASPH CONC PAV(2") | 45,955 SY | $9.50 | $1.86 | 5.12x | $351,234 |