FY26 - Brenham AO RPM - 09
6489-88-001 · let Oct 14, 2025 · Washington, Bryan · Routine Maintenance Project
$114,100Low bid: TRP INFRASTRUCTURE SERVICES, LLC-6.1% vs estimate $121,500
$40,900Left on the table35.8% gap to the second bid
4BiddersSpread 45% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TRP INFRASTRUCTURE SERVICES, LLC | $114,100 | -6.1% | $40,900 | 0 | 1-$7,184 | |
| 2 | D. I. J. CONSTRUCTION, INC. | $155,000 | +35.8% | 27.6% | $2,600 | 1+$58,816 | 0 |
| 3 | PAVEMENT MARKINGS INC. | $157,600 | +38.1% | 29.7% | $7,400 | 1+$4,197 | 0 |
| 4 | THE CONFIDENCE GROUP, INC | $165,000 | +44.6% | 35.8% | 1+$13,197 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
TRP INFRASTRUCTURE SERVICES, LLC vs D. I. J. CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 40 DAY | $50.00 | $1,700.00 | $229.60 | $66,000 |
| 672-7004 REFL PAV MRKR TY II-A-A | 20,000 EA | $3.95 | $3.00 | $3.97 | -$19,000 |
| 672-7006 REFL PAV MRKR TY II-C-R | 6,000 EA | $3.95 | $3.00 | $4.19 | -$5,700 |
| 672-7002 REFL PAV MRKR TY I-C | 2,000 EA | $3.95 | $3.00 | $4.04 | -$1,900 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $500.00 | $1,000.00 | $600.85 | $1,500 |
Positive: the low bidder was cheaper on that item. These 5 items account for $40,900 of the $40,900 gap.
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 40 DAY | $50.00 | $229.60 | 0.22x | -$7,184 |
D. I. J. CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 40 DAY | $1,700.00 | $229.60 | 7.40x | $58,816 |
PAVEMENT MARKINGS INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $2,000.00 | $600.85 | 3.33x | $4,197 |
THE CONFIDENCE GROUP, INC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $5,000.00 | $600.85 | 8.32x | $13,197 |