Culvert Replacement 07 10.25
6487-69-001 · let Oct 15, 2025 · Collin, Dallas · Routine Maintenance Project - Sealed
$461,459Low bid: AAD CONTRACTING INC.+2.2% vs estimate $451,670
$51,319Left on the table11.1% gap to the second bid
4BiddersSpread 26% low to high
32Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AAD CONTRACTING INC. | $461,459 | 2.2% | $51,319 | 5+$58,209 | 2-$478,423 | |
| 2 | HIGHWAY 19 CONSTRUCTION LLC | $512,778 | +11.1% | 13.5% | $66,167 | 7+$106,536 | 3-$506,435 |
| 3 | ED BELL CONSTRUCTION COMPANY | $578,945 | +25.5% | 28.2% | $3,702 | 9+$131,453 | 2-$530,355 |
| 4 | GARRET SHIELDS INFRASTRUCTURE | $582,647 | +26.3% | 29.0% | 4+$57,663 | 1-$473,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
AAD CONTRACTING INC. vs HIGHWAY 19 CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 400-7006 CUT & RESTORING PAV | 176 SY | $150.00 | $350.00 | $171.81 | $35,200 |
| 466-7056 HEADWALL (CH - FW - 45) (DIA= 48 IN) | 2 EA | $25,000.00 | $12,000.00 | $25,000.00 | -$26,000 |
| 400-7010 CEM STABIL BKFL | 210 CY | $250.00 | $350.00 | $138.14 | $21,000 |
| 403-7001 TEMPORARY SPL SHORING | 2,606 SF | $15.00 | $22.00 | $25.56 | $18,242 |
| 401-7001 FLOWABLE BACKFILL | 134 CY | $250.00 | $350.00 | $298.77 | $13,400 |
| 464-7011 RC PIPE (CL III)(48 IN) | 345 LF | $275.00 | $253.00 | $255.07 | -$7,590 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 240 CY | $70.00 | $50.00 | $13.19 | -$4,800 |
| 100-7002 PREPARING ROW | 1 STA | $1,500.00 | $5,000.00 | $6,072.92 | $3,500 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 14 DAY | $350.00 | $100.00 | $87.82 | -$3,500 |
| 530-7010 DRIVEWAYS (ACP) | 95 SY | $110.00 | $75.00 | $54.96 | -$3,325 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 74 CY | $220.00 | $180.00 | $184.74 | -$2,960 |
| 168-7001 VEGETATIVE WATERING | 65 TGL | $10.00 | $50.00 | $8.43 | $2,600 |
| 505-7001 TMA (STATIONARY) | 14 DAY | $350.00 | $500.00 | $217.57 | $2,100 |
| 496-7006 REMOV STR (HEADWALL) | 2 EA | $2,000.00 | $1,000.00 | $1,533.90 | -$2,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $7,000.00 | $5,000.00 | $11,585.04 | -$2,000 |
| 432-7001 RIPRAP (CONC)(4 IN) | 13 CY | $600.00 | $750.00 | $573.24 | $1,950 |
| 506-7002 ROCK FILTER DAMS (INSTALL) (TY 2) | 75 LF | $20.00 | $45.00 | $44.91 | $1,875 |
| 506-7003 ROCK FILTER DAMS (INSTALL) (TY 3) | 25 LF | $25.00 | $80.00 | $71.34 | $1,375 |
| 110-7001 EXCAV (ROADWAY) | 226 CY | $19.00 | $25.00 | $11.68 | $1,356 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 41 LF | $30.00 | $5.00 | $5.96 | -$1,025 |
Positive: the low bidder was cheaper on that item. These 20 items account for $49,398 of the $51,319 gap.
AAD CONTRACTING INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 210 CY | $250.00 | $138.14 | 1.81x | $23,490 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 240 CY | $70.00 | $13.19 | 5.31x | $13,634 |
| 496-7007 REMOV STR (PIPE) | 468 LF | $50.00 | $23.96 | 2.09x | $12,185 |
| 530-7010 DRIVEWAYS (ACP) | 95 SY | $110.00 | $54.96 | 2.00x | $5,229 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 14 DAY | $350.00 | $87.82 | 3.99x | $3,671 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |
| 100-7002 PREPARING ROW | 1 STA | $1,500.00 | $6,072.92 | 0.25x | -$4,573 |
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 210 CY | $350.00 | $138.14 | 2.53x | $44,490 |
| 400-7006 CUT & RESTORING PAV | 176 SY | $350.00 | $171.81 | 2.04x | $31,362 |
| 496-7007 REMOV STR (PIPE) | 468 LF | $50.00 | $23.96 | 2.09x | $12,185 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 240 CY | $50.00 | $13.19 | 3.79x | $8,834 |
| 505-7001 TMA (STATIONARY) | 14 DAY | $500.00 | $217.57 | 2.30x | $3,954 |
| 110-7001 EXCAV (ROADWAY) | 226 CY | $25.00 | $11.68 | 2.14x | $3,010 |
| 168-7001 VEGETATIVE WATERING | 65 TGL | $50.00 | $8.43 | 5.93x | $2,702 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |
| 466-7056 HEADWALL (CH - FW - 45) (DIA= 48 IN) | 2 EA | $12,000.00 | $25,000.00 | 0.48x | -$26,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $5,000.00 | $11,585.04 | 0.43x | -$6,585 |
ED BELL CONSTRUCTION COMPANY: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 210 CY | $350.00 | $138.14 | 2.53x | $44,490 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $42,000.00 | $11,585.04 | 3.63x | $30,415 |
| 100-7002 PREPARING ROW | 1 STA | $31,000.00 | $6,072.92 | 5.10x | $24,927 |
| 496-7006 REMOV STR (HEADWALL) | 2 EA | $5,000.00 | $1,533.90 | 3.26x | $6,932 |
| 530-7010 DRIVEWAYS (ACP) | 95 SY | $125.00 | $54.96 | 2.27x | $6,654 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 240 CY | $40.00 | $13.19 | 3.03x | $6,434 |
| 162-7002 BLOCK SODDING | 435 SY | $15.00 | $4.39 | 3.42x | $4,616 |
| 506-7011 ROCK FILTER DAMS (REMOVE) | 100 LF | $50.00 | $12.47 | 4.01x | $3,753 |
| 506-7002 ROCK FILTER DAMS (INSTALL) (TY 2) | 75 LF | $88.00 | $44.91 | 1.96x | $3,232 |
| 500-7001 MOBILIZATION | 1 LS | $57,500.00 | $523,850.32 | 0.11x | -$466,350 |
| 403-7001 TEMPORARY SPL SHORING | 2,606 SF | $1.00 | $25.56 | 0.04x | -$64,005 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 210 CY | $300.00 | $138.14 | 2.17x | $33,990 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 240 CY | $50.00 | $13.19 | 3.79x | $8,834 |
| 110-7001 EXCAV (ROADWAY) | 226 CY | $50.00 | $11.68 | 4.28x | $8,660 |
| 530-7010 DRIVEWAYS (ACP) | 95 SY | $120.00 | $54.96 | 2.18x | $6,179 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |