Culvert Extension Cross Drainage 07 1025

6486-31-001 · let Oct 15, 2025 · Collin, Dallas · Routine Maintenance Project - Sealed

$444,180Low bid: GARRET SHIELDS INFRASTRUCTURE-30.7% vs estimate $640,676
$264Left on the table0.1% gap to the second bid
4BiddersSpread 16% low to high
23Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1GARRET SHIELDS INFRASTRUCTURE $444,180-30.7% $264 4+$60,507 1-$483,850
2RISE UP CONSTRUCTION LLC $444,444+0.1%-30.6% $34,452 7+$190,896 3-$611,391
3ED BELL CONSTRUCTION COMPANY $478,896+7.8%-25.3% $34,951 8+$127,412 4-$514,227
4HIGHWAY 19 CONSTRUCTION LLC $513,847+15.7%-19.8% 6+$167,784 2-$516,368

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

GARRET SHIELDS INFRASTRUCTURE vs RISE UP CONSTRUCTION LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
7074-7001 SLIP LINING CULVERT PIPE 30"277 LF $600.00$189.21$600.00 -$113,789
512-7008 PORT CTB (FUR & INST)(F-SHAPE)(TY 4)380 LF $80.00$300.00$80.00 $83,600
164-7010 DRILL SEED (PERM_RURAL_CLAY)2,001 SY $0.2000$15.00$0.2111 $29,615
168-7001 VEGETATIVE WATERING303 TGL $10.00$100.00$8.43 $27,270
512-7056 PORT CTB (REMOVE)(F-SHAPE)(TY 4)380 LF $20.00$75.00$20.00 $20,900
403-7001 TEMPORARY SPL SHORING496 SF $80.00$39.00$25.56 -$20,336
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2 MO $10,000.00$1,959.00$11,585.04 -$16,082
464-7007 RC PIPE (CL III)(30 IN)88 LF $300.00$175.00$140.03 -$11,000
466-7118 HEADWALL (CH - PW - S) (DIA= 30 IN)1 EA $25,000.00$15,000.00$11,885.00 -$10,000
100-7002 PREPARING ROW1.78 STA $10,000.00$5,000.00$6,072.92 -$8,900
505-7001 TMA (STATIONARY)68 DAY $300.00$400.00$217.57 $6,800
400-7010 CEM STABIL BKFL39 CY $300.00$450.00$138.14 $5,850
500-7001 MOBILIZATION1 LS $40,000.00$45,500.00$523,850.32 $5,500
496-7007 REMOV STR (PIPE)88 LF $50.00$75.00$23.96 $2,200
545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)2 EA $10,000.00$9,022.00$8,780.51 -$1,956
506-7039 TEMP SEDMT CONT FENCE (INSTALL)520 LF $5.00$7.00$3.92 $1,040
545-7004 CRASH CUSH ATTEN (REMOVE)2 EA $500.00$1.00$941.31 -$998
506-7003 ROCK FILTER DAMS (INSTALL) (TY 3)20 LF $20.00$44.00$71.34 $480
506-7044 BIODEG EROSN CONT LOGS (INSTL) (12")250 LF $8.00$9.00$5.23 $250
506-7011 ROCK FILTER DAMS (REMOVE)20 LF $10.00$1.00$12.47 -$180

Positive: the low bidder was cheaper on that item. These 20 items account for $264 of the $264 gap.

GARRET SHIELDS INFRASTRUCTURE: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
403-7001 TEMPORARY SPL SHORING496 SF $80.00$25.563.13x$27,002
464-7007 RC PIPE (CL III)(30 IN)88 LF $300.00$140.032.14x$14,077
466-7118 HEADWALL (CH - PW - S) (DIA= 30 IN)1 EA $25,000.00$11,885.002.10x$13,115
400-7010 CEM STABIL BKFL39 CY $300.00$138.142.17x$6,312
500-7001 MOBILIZATION1 LS $40,000.00$523,850.320.08x-$483,850

RISE UP CONSTRUCTION LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
512-7008 PORT CTB (FUR & INST)(F-SHAPE)(TY 4)380 LF $300.00$80.003.75x$83,600
164-7010 DRILL SEED (PERM_RURAL_CLAY)2,001 SY $15.00$0.211171.06x$29,593
168-7001 VEGETATIVE WATERING303 TGL $100.00$8.4311.86x$27,745
512-7056 PORT CTB (REMOVE)(F-SHAPE)(TY 4)380 LF $75.00$20.003.75x$20,900
505-7001 TMA (STATIONARY)68 DAY $400.00$217.571.84x$12,405
400-7010 CEM STABIL BKFL39 CY $450.00$138.143.26x$12,162
496-7007 REMOV STR (PIPE)88 LF $75.00$23.963.13x$4,491
500-7001 MOBILIZATION1 LS $45,500.00$523,850.320.09x-$478,350
7074-7001 SLIP LINING CULVERT PIPE 30"277 LF $189.21$600.000.32x-$113,789
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2 MO $1,959.00$11,585.040.17x-$19,252

ED BELL CONSTRUCTION COMPANY: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2 MO $31,500.00$11,585.042.72x$39,830
164-7010 DRILL SEED (PERM_RURAL_CLAY)2,001 SY $12.00$0.211156.85x$23,590
100-7002 PREPARING ROW1.78 STA $16,000.00$6,072.922.63x$17,670
464-7007 RC PIPE (CL III)(30 IN)88 LF $333.00$140.032.38x$16,981
466-7118 HEADWALL (CH - PW - S) (DIA= 30 IN)1 EA $25,000.00$11,885.002.10x$13,115
400-7010 CEM STABIL BKFL39 CY $350.00$138.142.53x$8,262
400-7006 CUT & RESTORING PAV21 SY $400.00$171.812.33x$4,792
496-7007 REMOV STR (PIPE)88 LF $60.00$23.962.50x$3,171
500-7001 MOBILIZATION1 LS $45,000.00$523,850.320.09x-$478,850
512-7008 PORT CTB (FUR & INST)(F-SHAPE)(TY 4)380 LF $40.00$80.000.50x-$15,200
403-7001 TEMPORARY SPL SHORING496 SF $1.00$25.560.04x-$12,182
505-7001 TMA (STATIONARY)68 DAY $100.00$217.570.46x-$7,995

HIGHWAY 19 CONSTRUCTION LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
464-7007 RC PIPE (CL III)(30 IN)88 LF $1,600.00$140.0311.43x$128,477
403-7001 TEMPORARY SPL SHORING496 SF $55.00$25.562.15x$14,602
164-7010 DRILL SEED (PERM_RURAL_CLAY)2,001 SY $5.00$0.211123.69x$9,583
400-7010 CEM STABIL BKFL39 CY $350.00$138.142.53x$8,262
400-7006 CUT & RESTORING PAV21 SY $350.00$171.812.04x$3,742
545-7004 CRASH CUSH ATTEN (REMOVE)2 EA $2,500.00$941.312.66x$3,117
500-7001 MOBILIZATION1 LS $100,000.00$523,850.320.19x-$423,850
7074-7001 SLIP LINING CULVERT PIPE 30"277 LF $266.00$600.000.44x-$92,518