Culvert Extension Cross Drainage 07 1025
6486-31-001 · let Oct 15, 2025 · Collin, Dallas · Routine Maintenance Project - Sealed
$444,180Low bid: GARRET SHIELDS INFRASTRUCTURE-30.7% vs estimate $640,676
$264Left on the table0.1% gap to the second bid
4BiddersSpread 16% low to high
23Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GARRET SHIELDS INFRASTRUCTURE | $444,180 | -30.7% | $264 | 4+$60,507 | 1-$483,850 | |
| 2 | RISE UP CONSTRUCTION LLC | $444,444 | +0.1% | -30.6% | $34,452 | 7+$190,896 | 3-$611,391 |
| 3 | ED BELL CONSTRUCTION COMPANY | $478,896 | +7.8% | -25.3% | $34,951 | 8+$127,412 | 4-$514,227 |
| 4 | HIGHWAY 19 CONSTRUCTION LLC | $513,847 | +15.7% | -19.8% | 6+$167,784 | 2-$516,368 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
GARRET SHIELDS INFRASTRUCTURE vs RISE UP CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 7074-7001 SLIP LINING CULVERT PIPE 30" | 277 LF | $600.00 | $189.21 | $600.00 | -$113,789 |
| 512-7008 PORT CTB (FUR & INST)(F-SHAPE)(TY 4) | 380 LF | $80.00 | $300.00 | $80.00 | $83,600 |
| 164-7010 DRILL SEED (PERM_RURAL_CLAY) | 2,001 SY | $0.2000 | $15.00 | $0.2111 | $29,615 |
| 168-7001 VEGETATIVE WATERING | 303 TGL | $10.00 | $100.00 | $8.43 | $27,270 |
| 512-7056 PORT CTB (REMOVE)(F-SHAPE)(TY 4) | 380 LF | $20.00 | $75.00 | $20.00 | $20,900 |
| 403-7001 TEMPORARY SPL SHORING | 496 SF | $80.00 | $39.00 | $25.56 | -$20,336 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $10,000.00 | $1,959.00 | $11,585.04 | -$16,082 |
| 464-7007 RC PIPE (CL III)(30 IN) | 88 LF | $300.00 | $175.00 | $140.03 | -$11,000 |
| 466-7118 HEADWALL (CH - PW - S) (DIA= 30 IN) | 1 EA | $25,000.00 | $15,000.00 | $11,885.00 | -$10,000 |
| 100-7002 PREPARING ROW | 1.78 STA | $10,000.00 | $5,000.00 | $6,072.92 | -$8,900 |
| 505-7001 TMA (STATIONARY) | 68 DAY | $300.00 | $400.00 | $217.57 | $6,800 |
| 400-7010 CEM STABIL BKFL | 39 CY | $300.00 | $450.00 | $138.14 | $5,850 |
| 500-7001 MOBILIZATION | 1 LS | $40,000.00 | $45,500.00 | $523,850.32 | $5,500 |
| 496-7007 REMOV STR (PIPE) | 88 LF | $50.00 | $75.00 | $23.96 | $2,200 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 2 EA | $10,000.00 | $9,022.00 | $8,780.51 | -$1,956 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 520 LF | $5.00 | $7.00 | $3.92 | $1,040 |
| 545-7004 CRASH CUSH ATTEN (REMOVE) | 2 EA | $500.00 | $1.00 | $941.31 | -$998 |
| 506-7003 ROCK FILTER DAMS (INSTALL) (TY 3) | 20 LF | $20.00 | $44.00 | $71.34 | $480 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 250 LF | $8.00 | $9.00 | $5.23 | $250 |
| 506-7011 ROCK FILTER DAMS (REMOVE) | 20 LF | $10.00 | $1.00 | $12.47 | -$180 |
Positive: the low bidder was cheaper on that item. These 20 items account for $264 of the $264 gap.
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 496 SF | $80.00 | $25.56 | 3.13x | $27,002 |
| 464-7007 RC PIPE (CL III)(30 IN) | 88 LF | $300.00 | $140.03 | 2.14x | $14,077 |
| 466-7118 HEADWALL (CH - PW - S) (DIA= 30 IN) | 1 EA | $25,000.00 | $11,885.00 | 2.10x | $13,115 |
| 400-7010 CEM STABIL BKFL | 39 CY | $300.00 | $138.14 | 2.17x | $6,312 |
| 500-7001 MOBILIZATION | 1 LS | $40,000.00 | $523,850.32 | 0.08x | -$483,850 |
RISE UP CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7008 PORT CTB (FUR & INST)(F-SHAPE)(TY 4) | 380 LF | $300.00 | $80.00 | 3.75x | $83,600 |
| 164-7010 DRILL SEED (PERM_RURAL_CLAY) | 2,001 SY | $15.00 | $0.2111 | 71.06x | $29,593 |
| 168-7001 VEGETATIVE WATERING | 303 TGL | $100.00 | $8.43 | 11.86x | $27,745 |
| 512-7056 PORT CTB (REMOVE)(F-SHAPE)(TY 4) | 380 LF | $75.00 | $20.00 | 3.75x | $20,900 |
| 505-7001 TMA (STATIONARY) | 68 DAY | $400.00 | $217.57 | 1.84x | $12,405 |
| 400-7010 CEM STABIL BKFL | 39 CY | $450.00 | $138.14 | 3.26x | $12,162 |
| 496-7007 REMOV STR (PIPE) | 88 LF | $75.00 | $23.96 | 3.13x | $4,491 |
| 500-7001 MOBILIZATION | 1 LS | $45,500.00 | $523,850.32 | 0.09x | -$478,350 |
| 7074-7001 SLIP LINING CULVERT PIPE 30" | 277 LF | $189.21 | $600.00 | 0.32x | -$113,789 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1,959.00 | $11,585.04 | 0.17x | -$19,252 |
ED BELL CONSTRUCTION COMPANY: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $31,500.00 | $11,585.04 | 2.72x | $39,830 |
| 164-7010 DRILL SEED (PERM_RURAL_CLAY) | 2,001 SY | $12.00 | $0.2111 | 56.85x | $23,590 |
| 100-7002 PREPARING ROW | 1.78 STA | $16,000.00 | $6,072.92 | 2.63x | $17,670 |
| 464-7007 RC PIPE (CL III)(30 IN) | 88 LF | $333.00 | $140.03 | 2.38x | $16,981 |
| 466-7118 HEADWALL (CH - PW - S) (DIA= 30 IN) | 1 EA | $25,000.00 | $11,885.00 | 2.10x | $13,115 |
| 400-7010 CEM STABIL BKFL | 39 CY | $350.00 | $138.14 | 2.53x | $8,262 |
| 400-7006 CUT & RESTORING PAV | 21 SY | $400.00 | $171.81 | 2.33x | $4,792 |
| 496-7007 REMOV STR (PIPE) | 88 LF | $60.00 | $23.96 | 2.50x | $3,171 |
| 500-7001 MOBILIZATION | 1 LS | $45,000.00 | $523,850.32 | 0.09x | -$478,850 |
| 512-7008 PORT CTB (FUR & INST)(F-SHAPE)(TY 4) | 380 LF | $40.00 | $80.00 | 0.50x | -$15,200 |
| 403-7001 TEMPORARY SPL SHORING | 496 SF | $1.00 | $25.56 | 0.04x | -$12,182 |
| 505-7001 TMA (STATIONARY) | 68 DAY | $100.00 | $217.57 | 0.46x | -$7,995 |
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 464-7007 RC PIPE (CL III)(30 IN) | 88 LF | $1,600.00 | $140.03 | 11.43x | $128,477 |
| 403-7001 TEMPORARY SPL SHORING | 496 SF | $55.00 | $25.56 | 2.15x | $14,602 |
| 164-7010 DRILL SEED (PERM_RURAL_CLAY) | 2,001 SY | $5.00 | $0.2111 | 23.69x | $9,583 |
| 400-7010 CEM STABIL BKFL | 39 CY | $350.00 | $138.14 | 2.53x | $8,262 |
| 400-7006 CUT & RESTORING PAV | 21 SY | $350.00 | $171.81 | 2.04x | $3,742 |
| 545-7004 CRASH CUSH ATTEN (REMOVE) | 2 EA | $2,500.00 | $941.31 | 2.66x | $3,117 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 7074-7001 SLIP LINING CULVERT PIPE 30" | 277 LF | $266.00 | $600.00 | 0.44x | -$92,518 |