FM 57 OVERLAY US 180 TO JONES COUNTY
0317-02-017 · let Oct 8, 2025 · Fisher, Abilene · Overlay
$2,898,665Low bid: CK NEWBERRY, LLC-18.8% vs estimate $3,570,712
$83,470Left on the table2.9% gap to the second bid
7BiddersSpread 28% low to high
57Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CK NEWBERRY, LLC | $2,898,665 | -18.8% | $83,470 | 0 | 1-$308,850 | |
| 2 | J. H. STRAIN & SONS, INC. | $2,982,134 | +2.9% | -16.5% | $129,032 | 0 | 1-$373,850 |
| 3 | ZACK BURKETT CO. | $3,111,166 | +7.3% | -12.9% | $56,616 | 0 | 1-$308,850 |
| 4 | RK HALL, LLC | $3,167,782 | +9.3% | -11.3% | $131,550 | 3+$127,237 | 0 |
| 5 | DUININCK, INC. | $3,299,332 | +13.8% | -7.6% | $242,376 | 2+$97,771 | 0 |
| 6 | NOBLES ROAD CONSTRUCTION, INC. | $3,541,708 | +22.2% | -0.8% | $156,290 | ||
| 7 | A. L. HELMCAMP, INC. | $3,697,998 | +27.6% | 3.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CK NEWBERRY, LLC vs J. H. STRAIN & SONS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 134-7001 BACKFILL (TY A) | 533.63 STA | $175.00 | $330.00 | $224.26 | $82,713 |
| 500-7001 MOBILIZATION | 1 LS | $215,000.00 | $150,000.00 | $523,850.32 | -$65,000 |
| 341-7048 D-GR HMA TY-D PG70-22 | 15,839 TON | $122.00 | $123.78 | $126.94 | $28,193 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 104,437 LF | $0.5000 | $0.7000 | $0.4757 | $20,887 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $15,000.00 | $10,000.00 | $11,585.04 | -$20,000 |
| 341-7082 TACK COAT | 27,044 GAL | $4.00 | $4.50 | $3.93 | $13,522 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 5,444 SY | $50.00 | $48.00 | $35.01 | -$10,888 |
| 354-7073 PLANE ASPH CONC PAV (0" TO 1.5") | 3,194 SY | $2.00 | $5.00 | $3.19 | $9,582 |
| 354-7074 PLANE ASPH CONC PAV (1.5") | 3,517 SY | $2.00 | $4.00 | $1.35 | $7,034 |
| 480-7001 CLEAN EXIST CULVERTS | 3 EA | $2,000.00 | $3,000.00 | $1,712.97 | $3,000 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 475 LF | $40.00 | $46.00 | $25.60 | $2,850 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 23,817 LF | $0.6000 | $0.7000 | $0.4986 | $2,382 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 95,264 LF | $0.2000 | $0.2200 | $0.2040 | $1,905 |
| 540-7018 MTL W - BEAM GD FEN (LOW FILL CULVERT) | 175 LF | $95.00 | $105.00 | $90.29 | $1,750 |
| 505-7003 TMA (MOBILE OPERATION) | 22 DAY | $275.00 | $350.00 | $229.60 | $1,650 |
| 505-7001 TMA (STATIONARY) | 65 DAY | $275.00 | $250.00 | $217.57 | -$1,625 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 4 EA | $3,500.00 | $3,850.00 | $3,190.07 | $1,400 |
| 666-7420 REFL PAV MRK TY I (Y)6"(BRK)(100MIL) | 12,080 LF | $0.6000 | $0.7000 | $0.4829 | $1,208 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 4,563 EA | $2.00 | $2.25 | $0.5715 | $1,141 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 48,724 LF | $0.2000 | $0.2200 | $0.2394 | $974 |
Positive: the low bidder was cheaper on that item. These 20 items account for $82,679 of the $83,470 gap.
CK NEWBERRY, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $215,000.00 | $523,850.32 | 0.41x | -$308,850 |
J. H. STRAIN & SONS, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
ZACK BURKETT CO.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $215,000.00 | $523,850.32 | 0.41x | -$308,850 |