US 180 SCURRY COUNTY 0295-03
0295-03-036 · let Oct 9, 2025 · Borden, Abilene · Overlay
$7,299,030Low bid: CK NEWBERRY, LLC-19.9% vs estimate $9,109,160
$106,123Left on the table1.5% gap to the second bid
5BiddersSpread 20% low to high
59Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CK NEWBERRY, LLC | $7,299,030 | -19.9% | $106,123 | 0 | 0 | |
| 2 | RK HALL, LLC | $7,405,153 | +1.5% | -18.7% | $695,386 | 1+$122,780 | 1-$59,654 |
| 3 | ZACK BURKETT CO. | $8,100,539 | +11.0% | -11.1% | $581,875 | 1+$83,575 | 0 |
| 4 | A. L. HELMCAMP, INC. | $8,682,414 | +19.0% | -4.7% | $108,801 | 0 | 0 |
| 5 | DUININCK, INC. | $8,791,215 | +20.4% | -3.5% | 1+$99,660 | 1-$129,249 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CK NEWBERRY, LLC vs RK HALL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $500,000.00 | $381,725.80 | $523,850.32 | -$118,274 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $20,000.00 | $42,280.00 | $11,585.04 | $89,120 |
| 530-7015 DRIVEWAYS (BASE) | 1,200 SY | $20.00 | $51.63 | $27.85 | $37,956 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 15,600 SY | $35.00 | $37.24 | $35.01 | $34,944 |
| 344-7077 TACK COAT | 57,500 GAL | $3.50 | $3.09 | $3.25 | -$23,575 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 26,000 EA | $1.00 | $1.89 | $0.5715 | $23,140 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 167,400 LF | $0.1000 | $0.2100 | $0.2040 | $18,414 |
| 354-7083 PLANE ASPH CONC PAV (0" TO 2-1/2") | 5,900 SY | $5.00 | $7.95 | $2.98 | $17,405 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 83,700 LF | $0.1000 | $0.2500 | $0.2394 | $12,555 |
| 530-7002 INTERSECTIONS (ACP) | 2,327 SY | $30.00 | $25.10 | $50.74 | -$11,402 |
| 530-7018 TURNOUTS (ACP) | 46 SY | $50.00 | $240.86 | $82.59 | $8,780 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $100.00 | $241.97 | $217.57 | $8,518 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 167,400 LF | $0.5000 | $0.5400 | $0.4757 | $6,696 |
| 530-7010 DRIVEWAYS (ACP) | 737 SY | $50.00 | $41.70 | $54.96 | -$6,117 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 720 SF | $145.00 | $153.36 | $95.74 | $6,019 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 22 CY | $600.00 | $340.34 | $110.18 | -$5,713 |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 51 EA | $750.00 | $810.00 | $696.14 | $3,060 |
| 134-7001 BACKFILL (TY A) | 850 STA | $150.00 | $146.54 | $224.26 | -$2,941 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 71,150 LF | $0.5000 | $0.5400 | $0.4986 | $2,846 |
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $100.00 | $335.47 | $229.60 | $2,355 |
Positive: the low bidder was cheaper on that item. These 20 items account for $103,786 of the $106,123 gap.
RK HALL, LLC: unbalanced items
Placed 2ZACK BURKETT CO.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 720 SF | $211.82 | $95.74 | 2.21x | $83,575 |