Bid Day Forecast: 6506-83-001

Montgomery · Dec 8, 2026 Sign up free
Set your company to personalize scores

Routine Maintenance Project - Sealed

CCSJ 6506-83-001 · lets Dec 8, 2026 · Montgomery, Houston · IH0045

$367,699Engineer's estimate Items at market: $686,943 (+86.8%)
$319,466Most likely low bid$275,760 to $352,987 (middle half)
3.7Expected bidders1 plan holders, 0 regular bidders
60/100Worth a lookMarket only. Set your company for a personal score

Where the low bid should land

$221,082 (1 in 10 go lower)$409,131 (1 in 10 go higher)

From 60 comparable let jobs (district + work type, estimates of $147,080 to $919,247, last 3 years). 80% of them went under the estimate; the typical low bid was -13.1% vs estimate.

Bid / no-bid score

  • Competition22 / 25Jobs like this draw about 3.7 bidders.
  • Margin5 / 20Low bids land at 87% of the estimate.

Set your company to add your experience, win rate and size fit.

Comparable jobs

Nov 2026 6506-72-001Harris · 3 bidders $765,790+31.8%
Nov 2026 6507-15-001Brazoria · 4 bidders $539,652-4.5%
Oct 2026 6508-18-001Harris · 2 bidders $699,987+2.9%
Oct 2026 6508-74-001Waller · 3 bidders $384,715-27.8%
Sep 2026 6499-61-001Montgomery · 1 bidders $697,730-4.1%
Sep 2026 6500-36-001Waller · 1 bidders $239,693+9.7%
Sep 2026 6494-58-001Fort Bend · 2 bidders $667,500+25.3%
Aug 2026 6501-01-001Harris · 2 bidders $888,100+15.2%

The field: plan holders and how they bid

Last 3 years in Texas
Plan holderBidsWinsIn HoustonAvg bid vs est.Avg win vs est.Their typical bid here
SHORETEX, LLCBidders 00

"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.

Items that decide this job

21 of 21 items priced from low bids
ItemQtyMarket priceRange of low bidsAt marketShare
760-7003 DITCH CLEAN/RESHAPING(CU YD IN VEHICLE)6 low bids · prices swing 6x 6,500 CY$25.38$5.00 – $30.00 $164,96624.0%
764-7019 STORM SEWER CLEAN (BOX CULV)(48-<96 SF)8 low bids · prices swing 5x 4,450 LF$24.47$10.00 – $50.00 $108,90315.9%
760-7001 DITCH CLEANING AND RESHAPING (FOOT)51 low bids · prices swing 200x 50,000 LF$1.96$1.00 – $200.00 $97,81914.2%
764-7001 DRAIN INLET CLEANING60 low bids · prices swing 138x 600 EA$124.25$20.00 – $2,750.00 $74,54810.9%
764-7010 STORM SEWER CLEANING (PIPE)(31"-36"DIA)20 low bids · prices swing 16x 6,058 LF$6.94$2.85 – $45.00 $42,0296.1%
764-7018 STORM SEWER CLEAN (BOX CULV)(24-<48 SF)12 low bids · prices swing 13x 2,075 LF$17.30$4.00 – $50.00 $35,9075.2%
764-7017 STORM SEWER CLEAN (BOX CULV)(12-<24 SF)12 low bids · prices swing 23x 3,325 LF$9.24$2.00 – $45.00 $30,7374.5%
764-7009 STORM SEWER CLEANING (PIPE)(25"-30"DIA)15 low bids · prices swing 37x 5,500 LF$5.28$2.00 – $74.25 $29,0304.2%
764-7008 STORM SEWER CLEANING (PIPE)(19"-24"DIA)23 low bids · prices swing 64x 6,573 LF$3.96$1.00 – $63.50 $26,0533.8%
764-7007 STORM SEWER CLEANING (PIPE)(12"-18"DIA)23 low bids · prices swing 37x 4,500 LF$3.42$1.29 – $47.25 $15,3852.2%
764-7004 DOWNSPOUT CLEANING10 low bids · prices swing 725x 150 EA$98.97$1.00 – $725.00 $14,8462.2%
764-7016 STORM SEWER CLEAN (BOX CULV) (6-<12 SF)10 low bids · prices swing 23x 800 LF$11.56$2.00 – $45.00 $9,2481.3%
764-7012 STORM SEWER CLEANING (PIPE)(43"-54"DIA)14 low bids · prices swing 33x 678 LF$13.40$3.00 – $100.00 $9,0871.3%
505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x 35 DAY$217.57$0.0010 – $16,487.00 $7,6151.1%
764-7002 PUMP STATION WELL CLEANING11 low bids · prices swing 3x 5 EA$1,318.97$1,000.00 – $3,250.00 $6,5951.0%