Routine Maintenance Project - Sealed
CCSJ 6502-84-001 · lets Dec 8, 2026 · Harris, Houston · FM1093
$261,585Engineer's estimate
Items at market: $776,377 (+196.8%)
$223,751Most likely low bid$192,483 to $250,668 (middle half)
3.6Expected bidders1 plan holders, 1 regular bidders
58/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$223,751
Estimate $261,585
$156,850 (1 in 10 go lower)$287,630 (1 in 10 go higher)
From 43 comparable let jobs (district + work type, estimates of $104,634 to $653,962, last 3 years). 81% of them went under the estimate; the typical low bid was -14.5% vs estimate.
Bid / no-bid score
- Competition22 / 25Jobs like this draw about 3.6 bidders.
- Margin4 / 20Low bids land at 86% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6506-72-001Harris · 3 bidders | $765,790+31.8% |
| Nov 2026 | 6507-15-001Brazoria · 4 bidders | $539,652-4.5% |
| Oct 2026 | 6508-74-001Waller · 3 bidders | $384,715-27.8% |
| Sep 2026 | 6500-36-001Waller · 1 bidders | $239,693+9.7% |
| Sep 2026 | 6494-58-001Fort Bend · 2 bidders | $667,500+25.3% |
| Aug 2026 | 6496-38-001Waller · 3 bidders | $193,948-8.7% |
| Aug 2026 | 6500-14-001Waller · 2 bidders | $398,235-8.3% |
| Jul 2026 | 6499-83-001Waller · 4 bidders | $327,294-37.7% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Houston | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| EMERY SAPP & SON'S INC. SharpestBidders | 7 | 2 | 1 of 2 | 18.7% | 5.5% | $310,611 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
9 of 9 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 67.5% |
| 3017-7001 CONTINUOUS GRINDING-CONCRETE PAVEMENT11 low bids · prices swing 4x | 31,780 SY | $6.23 | $3.10 – $13.00 | $197,972 | 25.5% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 3 MO | $11,585.04 | $0.0010 – $273,686.48 | $34,755 | 4.5% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 60 DAY | $217.57 | $0.0010 – $16,487.00 | $13,054 | 1.7% |
| 666-7184 RE PM TY II (W) 24" (SLD)145 low bids · prices swing 76x | 744 LF | $3.83 | $0.3500 – $26.50 | $2,849 | 0.4% |
| 677-7008 ELIM EXT PM & MRKS (24")436 low bids · prices swing 480x | 744 LF | $2.87 | $0.2500 – $120.00 | $2,136 | 0.3% |
| 505-7003 TMA (MOBILE OPERATION)1256 low bids · prices swing 3,000,000x | 5 DAY | $229.60 | $0.0010 – $3,000.00 | $1,148 | 0.1% |
| 666-7182 RE PM TY II (W) 12" (SLD)79 low bids · prices swing 600x | 180 LF | $2.13 | $0.2500 – $150.00 | $383 | 0.0% |
| 677-7006 ELIM EXT PM & MRKS (12")254 low bids · prices swing 80x | 180 LF | $1.27 | $0.2500 – $20.00 | $229 | 0.0% |