Safety Improvement Projects
CCSJ 1685-05-141 · lets Jan 6, 2027 · Harris, Houston · SH 6 · Install/Upgrade Roadway Lighting
$1,071,674Engineer's estimate
Items at market: $1,895,267 (+76.9%)
$919,413Most likely low bid$797,913 to $1,037,715 (middle half)
4.6Expected bidders0 plan holders, 0 regular bidders
49/100Weak fitMarket only. Set your company for a personal score
Where the low bid should land
$919,413
Estimate $1,071,674
$698,040 (1 in 10 go lower)$1,229,551 (1 in 10 go higher)
From 245 comparable let jobs (district, estimates of $428,670 to $2,679,185, last 3 years). 79% of them went under the estimate; the typical low bid was -14.2% vs estimate.
Bid / no-bid score
- Competition18 / 25Jobs like this draw about 4.6 bidders.
- Margin4 / 20Low bids land at 86% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6507-15-001Brazoria · 4 bidders | $539,652-4.5% |
| Nov 2026 | 6506-72-001Harris · 3 bidders | $765,790+31.8% |
| Nov 2026 | 0500-01-158Galveston · 5 bidders | $607,082+18.9% |
| Nov 2026 | 0271-06-141Harris · 5 bidders | $1,151,035-32.0% |
| Nov 2026 | 6504-89-001Harris · 7 bidders | $2,035,047+53.8% |
| Oct 2026 | 6508-18-001Harris · 2 bidders | $699,987+2.9% |
| Oct 2026 | 6508-74-001Waller · 3 bidders | $384,715-27.8% |
| Oct 2026 | 1414-03-043Brazoria · 2 bidders | $974,716-9.6% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
13 of 16 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 27.6% |
| 610-7198 IN RD IL (TY SA) 50T-10 (400W EQ) LED27 low bids · prices swing 3x | 82 EA | $5,165.17 | $3,705.51 – $12,060.00 | $423,544 | 22.3% |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN)196 low bids · prices swing 12x | 820 LF | $270.84 | $65.00 – $778.01 | $222,091 | 11.7% |
| 618-7054 CONDT (PVC) (SCH 80) (2")207 low bids · prices swing 34x | 18,446 LF | $12.03 | $3.00 – $103.38 | $221,972 | 11.7% |
| 618-7055 CONDT (PVC) (SCH 80) (2") (BORE)224 low bids · prices swing 11x | 7,545 LF | $20.33 | $9.57 – $102.52 | $153,361 | 8.1% |
| 620-7008 ELEC CONDR (NO.8) INSULATED272 low bids · prices swing 11x | 54,456 LF | $2.11 | $0.9500 – $10.00 | $114,785 | 6.1% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 6 MO | $11,585.04 | $0.0010 – $273,686.48 | $69,510 | 3.7% |
| 620-7007 ELEC CONDR (NO.8) BARE269 low bids · prices swing 56x | 27,228 LF | $1.94 | $0.9000 – $50.00 | $52,929 | 2.8% |
| 624-7008 GROUND BOX TY D (162922)W/APRON265 low bids · prices swing 12x | 24 EA | $1,715.49 | $600.00 – $7,000.00 | $41,172 | 2.2% |
| 618-7078 CONDT (RM) (2")68 low bids · prices swing 22x | 433 LF | $49.01 | $5.00 – $110.00 | $21,221 | 1.1% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 90 DAY | $217.57 | $0.0010 – $16,487.00 | $19,581 | 1.0% |
| 432-7007 RIPRAP (CONC) (CL B) (4 IN)60 low bids · prices swing 14x | 30 CY | $564.22 | $370.33 – $5,000.00 | $16,927 | 0.9% |
| 628-7055 ELC SRV TY A 240/480 060(SS)SS(E)GC(U)8 low bids | 2 EA | $7,162.06 | $6,500.00 – $12,000.00 | $14,324 | 0.8% |