Safety Improvement Projects
CCSJ 0227-06-033 · lets Jan 6, 2027 · Dawson, Hockley, Lubbock · SH 137, US 180, US 385 · Intersection Improvement
$374,764Engineer's estimate
Items at market: $809,239 (+115.9%)
$348,864Most likely low bid$312,164 to $381,662 (middle half)
3.0Expected bidders0 plan holders, 0 regular bidders
76/100Strong fit: bid itMarket only. Set your company for a personal score
Where the low bid should land
$348,864
Estimate $374,764
$239,215 (1 in 10 go lower)$409,970 (1 in 10 go higher)
From 91 comparable let jobs (district, estimates of $149,906 to $936,909, last 3 years). 69% of them went under the estimate; the typical low bid was -6.9% vs estimate.
Bid / no-bid score
- Competition25 / 25Jobs like this draw about 3.0 bidders.
- Margin9 / 20Low bids land at 93% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6510-77-001Hale · 4 bidders | $158,004-55.3% |
| Nov 2026 | 6510-78-001Hale · 4 bidders | $297,939-21.9% |
| Nov 2026 | 6510-79-001Lamb · 3 bidders | $331,625-36.1% |
| Nov 2026 | 6510-80-001Hale · 3 bidders | $182,004-63.4% |
| Nov 2026 | 6511-33-001Lubbock · 2 bidders | $141,000-38.7% |
| Sep 2026 | 6509-63-001Lubbock · 2 bidders | $205,600+17.5% |
| Sep 2026 | 6509-65-001Lubbock · 2 bidders | $196,870+9.1% |
| Sep 2026 | 6510-24-001Crosby · 5 bidders | $595,302-13.7% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
36 of 51 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.5 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $261,925 | 32.4% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.25 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $130,963 | 16.2% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.25 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $130,963 | 16.2% |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN)196 low bids · prices swing 12x | 120 LF | $270.84 | $65.00 – $778.01 | $32,501 | 4.0% |
| 618-7054 CONDT (PVC) (SCH 80) (2")207 low bids · prices swing 34x | 2,475 LF | $12.03 | $3.00 – $103.38 | $29,783 | 3.7% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 2 MO | $11,585.04 | $0.0010 – $273,686.48 | $23,170 | 2.9% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 2 MO | $11,585.04 | $0.0010 – $273,686.48 | $23,170 | 2.9% |
| 628-7148 ELC SRV TY D 120/240 060(NS)SS(E)SP(O)61 low bids · prices swing 4x | 2 EA | $9,325.32 | $5,500.00 – $20,000.00 | $18,651 | 2.3% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 68 DAY | $217.57 | $0.0010 – $16,487.00 | $14,795 | 1.8% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 68 DAY | $217.57 | $0.0010 – $16,487.00 | $14,795 | 1.8% |
| 620-7010 ELEC CONDR (NO.6) INSULATED287 low bids · prices swing 12x | 5,330 LF | $2.58 | $1.25 – $15.00 | $13,739 | 1.7% |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN)196 low bids · prices swing 12x | 48 LF | $270.84 | $65.00 – $778.01 | $13,000 | 1.6% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 1 MO | $11,585.04 | $0.0010 – $273,686.48 | $11,585 | 1.4% |
| 628-7148 ELC SRV TY D 120/240 060(NS)SS(E)SP(O)61 low bids · prices swing 4x | 1 EA | $9,325.32 | $5,500.00 – $20,000.00 | $9,325 | 1.2% |
| 628-7148 ELC SRV TY D 120/240 060(NS)SS(E)SP(O)61 low bids · prices swing 4x | 1 EA | $9,325.32 | $5,500.00 – $20,000.00 | $9,325 | 1.2% |