| 10 | ODOT-307 |
Treated Subgrade | 1,920 | SY |
$25.00 |
$20.00 |
$25.00 |
$62.00 |
| 20 | ODOT-414 |
Concrete Pavement | 4,500 | SY |
$315.00 |
$301.00 |
$310.00 |
$330.00 |
| 30 | P-101-004 |
Concrete Pavement Removal | 2,600 | SY |
$90.00 |
$65.00 |
$75.00 |
$95.00 |
| 40 | P-101-005 |
Pavement and Base Removal | 1,920 | SY |
$60.00 |
$45.00 |
$40.00 |
$222.00 |
| 50 | S-502-002 |
Spall Repair | 1,050 | SF |
$350.00 |
$491.00 |
$375.00 |
$215.00 |
| 60 | P-101-030 |
Pavement Marking Removal | 2,325 | SF |
$1.50 |
$4.00 |
$2.00 |
$2.00 |
| 70 | P-605-002 |
Joint Sealant | 67,000 | LF |
$4.00 |
$3.23 |
$2.50 |
$5.00 |
| 80 | P-620-015 |
Reflectorized Pavement Marking | 6,475 | SF |
$3.00 |
$6.25 |
$3.75 |
$3.00 |
| 90 | P-620-016 |
Non-Reflectorized Pavement Marking | 9,900 | SF |
$2.50 |
$5.50 |
$2.50 |
$2.00 |
| 100 | TEMP-001 |
Temporary Marking, Lighting & Barricades | 1 | LSUM |
$40,000.00 |
$50,000.00 |
$50,000.00 |
$75,000.00 |
| 110 | C-100-001 |
Contractor Quality Control Program (CQCP) | 1 | LSUM |
$65,073.00 |
$65,000.00 |
$175,000.00 |
$100,000.00 |
| 120 | C-105-001 |
Mobilization | 1 | LSUM |
$289,215.00 |
$280,000.00 |
$280,000.00 |
$330,000.00 |
| 130 | ODOT-414 |
Concrete Pavement | 700 | SY |
$315.00 |
$301.00 |
$350.00 |
$330.00 |
| 140 | P-101-004 |
Concrete Pavement Removal | 700 | SY |
$90.00 |
$65.00 |
$125.00 |
$95.00 |
| 150 | P-605-002 |
Joint Sealant | 6,600 | LF |
$4.00 |
$3.23 |
$2.50 |
$5.00 |
| 160 | P-620-015 |
Reflectorized Pavement Marking | 400 | SF |
$3.00 |
$6.25 |
$3.75 |
$3.00 |
| 170 | P-620-016 |
Non-Reflectorized Pavement Marking | 350 | SF |
$2.50 |
$5.50 |
$2.50 |
$2.00 |
| 180 | S-502-002 |
Spall Repair | 50 | SF |
$350.00 |
$491.00 |
$375.00 |
$222.00 |
| 190 | ODOT-414 |
Concrete Pavement | 1,650 | SY |
$160.00 |
$301.00 |
$350.00 |
$330.00 |
| 200 | P-101-004 |
Concrete Pavement Removal | 1,650 | SY |
$90.00 |
$65.00 |
$125.00 |
$95.00 |
| 210 | P-605-002 |
Joint Sealant | 25,500 | LF |
$4.00 |
$3.23 |
$2.50 |
$5.00 |
| 220 | P-620-015 |
Reflectorized Pavement Marking | 300 | SF |
$3.00 |
$6.25 |
$3.75 |
$3.00 |
| 230 | P-620-016 |
Non-Reflectorized Pavement Marking | 440 | SF |
$2.50 |
$5.50 |
$2.50 |
$2.00 |
| 240 | S-502-002 |
Spall Repair | 1,100 | SF |
$350.00 |
$491.00 |
$375.00 |
$222.00 |
| 250 | C-100-001 |
Contractor Quality Control Program (CQCP) | 1 | LSUM |
$45,673.00 |
$40,000.00 |
$125,000.00 |
$34,000.00 |
| 260 | C-105-001 |
Mobilization | 1 | LSUM |
$216,185.00 |
$150,000.00 |
$185,000.00 |
$200,000.00 |
| 270 | ODOT-307 |
Treated Subgrade | 4,750 | SY |
$25.00 |
$20.00 |
$15.00 |
$62.00 |
| 280 | ODOT-414 |
Concrete Pavement | 4,750 | SY |
$315.00 |
$250.00 |
$270.00 |
$236.00 |
| 290 | P-101-005 |
Pavement and Base Removal | 4,750 | SY |
$60.00 |
$45.00 |
$40.00 |
$90.00 |
| 300 | C-100-001 |
Contractor Quality Control Program (CQCP) | 1 | LSUM |
$26,794.00 |
$40,000.00 |
$75,000.00 |
$34,000.00 |
| 310 | C-105-001 |
Mobilization | 1 | LSUM |
$132,282.00 |
$100,000.00 |
$110,000.00 |
$180,000.00 |
| 320 | ODOT-307 |
Treated Subgrade | 4,750 | SY |
$25.00 |
$20.00 |
$15.00 |
$62.00 |
| 330 | ODOT-414 |
Concrete Pavement | 4,750 | SY |
$160.00 |
$150.00 |
$160.00 |
$185.00 |
| 340 | P-101-005 |
Pavement and Base Removal | 4,750 | SY |
$60.00 |
$35.00 |
$25.00 |
$90.00 |