Let job
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $2,261,740 | ||
| 1 | J&R Constructors Group Low bidder | $2,389,765 | +5.7% | |
| 2 | THE CUMMINS CONSTRUCTION CO., INC. | $2,679,108 | +18.5% | +12.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J&R Constructor… | #2 THE CUMMINS CON… |
|---|---|---|---|---|---|---|---|
| 10 | 407(A)7200 | FOG SEAL | 6,000 | GAL | $3.25 | $6.00 | $5.05 |
| 20 | 407(C)7400 | (SP) POLYMER MOD. CATIONIC RAPID SET - 1S | 26,200 | GAL | $3.00 | $3.25 | $3.50 |
| 30 | 411(C)1420 | SUPERPAVE, TYPE S4(PG 70-28 OK) | 11,900 | TON | $140.00 | $149.00 | $155.50 |
| 40 | 411(I)2000 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 250 | TON | $260.00 | $215.00 | $264.65 |
| 50 | 412 3100 | COLD MILLING PAVEMENT | 104,500 | SY | $2.00 | $2.30 | $2.20 |
| 60 | 856(A)8207 | (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE) | 85,000 | LF | $0.7500 | $0.7300 | $0.9000 |
| 70 | 880(A)6220 | ARROW DISPLAY(TYPE C) | 90 | SD | $25.00 | $5.00 | $5.15 |
| 80 | 880(J)7100 | (SP) CONSTRUCTION TRAFFIC CONTROL | 45 | SD | $500.00 | $185.00 | $190.55 |
| 90 | 882(A)8210 | PORT.CHANGEABLE MESSAGE SIGN | 118 | SD | $30.00 | $5.00 | $5.15 |
| 100 | 641 2110 | MOBILIZATION | 1 | LSUM | $131,600.00 | $130,000.00 | $324,450.00 |