Rehabilitate Airfield Pavements - Phase 5 At Clinton Sherman Airport.
- Let date
- Thursday, February 19, 2026
- Contract
- 260044 · job page
- J/P numbers
- 39144(04)
- District
- Division 5
- County
- Washita
- Highway
- Limits
- Prequalification requirements and electronic bidding requirements have been waived for this proposal.
- Classification
- Rehabilitate Airfield Pavements - Phase 5 At Clinton Sherman Airport.
- Project number
- CSM-26B-S
- Working days
- 180
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $4,284,427 | ||
| 1 | DIAMOND SURFACE, INC. Low bidder | $3,612,518 | -15.7% | |
| 2 | Stuever Dirtworks, LLC | $3,946,762 | -7.9% | +9.3% |
| 3 | Tri-City Seal Company, Inc. TCS General Contractors | $4,051,987 | -5.4% | +12.2% |
| 4 | RUDY CONSTRUCTION CO. | $4,288,991 | +0.1% | +18.7% |
| 5 | Head, LLC. | $5,235,861 | +22.2% | +44.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 DIAMOND SURFACE… | #2 Stuever Dirtwor… | #3 Tri-City Seal C… | #4 RUDY CONSTRUCTI… | #5 Head, LLC. |
|---|---|---|---|---|---|---|---|---|---|---|
| 10 | ODOT-414 | Concrete Pavement | 5,270 | SY | $330.00 | $318.02 | $300.00 | $300.95 | $310.00 | $336.45 |
| 20 | P-101-004 | Concrete Pavement Removal | 5,270 | SY | $66.00 | $118.26 | $60.00 | $93.20 | $70.00 | $113.92 |
| 30 | P-605-002 | Joint Sealant | 104,830 | LF | $4.40 | $3.21 | $3.80 | $2.87 | $3.15 | $3.08 |
| 40 | S-502-001 | Spall Repair | 1,980 | CF | $500.00 | $228.65 | $584.00 | $506.99 | $600.00 | $682.79 |
| 50 | P-101-030 | Pavement Marking Removal | 60,190 | SF | $1.10 | $0.0700 | $1.00 | $1.01 | $1.30 | $2.08 |
| 60 | P-620-015 | Reflectorized Pavement Marking | 30,630 | SF | $3.63 | $3.13 | $3.25 | $1.66 | $1.50 | $1.63 |
| 70 | P-620-016 | Non-Reflectorized Pavement Marking | 12,160 | SF | $2.75 | $2.31 | $2.50 | $1.18 | $1.15 | $1.50 |
| 80 | TEMP-001 | Temporary Marking, Lighting & Barricades | 1 | LSUM | $20,000.00 | $31,250.00 | $28,750.00 | $95,856.43 | $55,000.00 | $477,789.76 |
| 90 | C-105-001 | Mobilization | 1 | LSUM | $418,778.00 | $330,044.56 | $246,000.00 | $301,599.11 | $425,000.00 | $400,000.00 |
| 100 | C-100-001 | Contractor Quality Control Program (CQCP) | 1 | LSUM | $96,641.00 | $34,621.25 | $30,000.00 | $146,671.97 | $150,000.00 | $116,458.71 |