Bid tab 250128

Let Apr 10, 2025 · Division 5 · Greer

‹ Apr 2025 results

Bridge And Approaches

Let date
Thursday, April 10, 2025
Contract
250128 · job page
J/P numbers
34482(04)
District
Division 5
County
Greer
Highway
COUNTY ROAD (EW 1440)
Limits
COUNTY ROAD (EW 1440): OVER UNNAMED CREEK, 2.00 MILES SOUTH OF SH-9 NEAR GRANITE.
Classification
Bridge And Approaches ·
Project number
STP-228C(035)CI
Working days
90
DBE goal
17.5%

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Wyatt Contracting Low bidder $559,514
2 SEWELL BROS., INC. $590,927 +5.6%
3 K & R BUILDERS, INC. $619,837 +10.8%
4 Haskell Lemon Group, LLC $676,170 +20.8%
5 Lopp Construction, LLC $724,449 +29.5%
6 C3 Construction, Inc. $759,227 +35.7%
7 BRIDGECO CONTRACTORS, INC. $769,730 +37.6%

Bid tab: unit prices 24 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Wyatt Contracti…#2 SEWELL BROS., I…#3 K & R BUILDERS,…#4 Haskell Lemon G…#5 Lopp Constructi…#6 C3 Construction…#7 BRIDGECO CONTRA…
10201(A)1200 CLEARING AND GRUBBING1LSUM $10,000.00 $4,500.00 $25,000.00 $8,000.00 $15,600.00 $25,750.00 $3,677.05 $12,000.00
20202(H)2900 EARTHWORK1LSUM $50,000.00 $35,000.00 $30,000.00 $26,900.00 $56,400.00 $46,350.00 $69,586.26 $79,650.00
30221(B)2300 TEMPORARY SILT FENCE200LF $7.50 $6.25 $7.00 $5.00 $6.45 $6.44 $7.94 $10.00
40221(E)2600 TEMPORARY SILT DIKE300LF $14.00 $8.10 $9.00 $4.00 $8.35 $8.34 $10.29 $20.00
50230(A)7200 SOLID SLAB SODDING5,100SY $3.75 $3.15 $3.50 $4.32 $3.25 $3.24 $4.00 $6.50
60233(A)0200 VEGETATIVE MULCHING1.06AC $1,400.00 $100.00 $1,750.00 $200.00 $1,648.00 $1,648.00 $2,033.12 $4,000.00
70402(E)2600 TRAFFIC BOUND SURFACE COURSE TYPE E430TON $50.00 $45.85 $43.00 $40.10 $42.20 $66.95 $57.60 $53.50
80509(D)0500 CLASS C CONCRETE10CY $425.00 $360.00 $400.00 $275.00 $250.00 $425.00 $529.24 $450.00
90613(B)5516 24" CORR. GALV. STEEL PIPE55LF $70.00 $77.50 $60.00 $52.00 $74.20 $97.85 $75.39 $70.00
100613(M)6904 TYPE B3 CULVERT END TREATMENT2EA $2,300.00 $4,125.00 $2,000.00 $1,520.00 $1,861.00 $2,781.00 $2,635.56 $3,800.00
110853 5100 DELINEATORS(TYPE 1, CODE 1)4EA $100.00 $50.00 $83.00 $50.00 $77.20 $77.25 $95.30 $65.00
120202(A)2210 UNCLASSIFIED EXCAVATION1,218CY $12.00 $12.00 $9.00 $7.85 $11.80 $16.48 $12.17 $10.00
130501(A)1210 STRUCTURAL EXCAVATION UNCLASSIFIED223CY $32.00 $30.00 $18.00 $13.45 $27.70 $41.20 $16.44 $25.00
140509(A)0210 CLASS AA CONCRETE431.25CY $775.00 $399.00 $545.00 $684.00 $612.50 $609.00 $673.03 $560.00
150511(A)2210 REINFORCING STEEL88,147LB $1.50 $1.50 $1.20 $1.22 $1.20 $1.18 $1.34 $1.60
160601(B)1210 TYPE I PLAIN RIPRAP WITH FILTER BLANKET1,080TON $70.00 $60.00 $66.00 $59.50 $65.60 $92.70 $90.20 $70.00
170619(D)6700 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $30,000.00 $15,000.00 $5,000.00 $5,050.00 $20,000.00 $15,000.00 $16,756.43 $40,000.00
180880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF360SD $1.50 $1.25 $1.38 $1.25 $1.30 $1.29 $1.59 $2.00
190880(B)6320 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF540SD $1.75 $1.25 $3.30 $1.25 $3.10 $3.09 $3.81 $2.00
200880(C)6410 CONSTRUCTION BARRICADES(TYPE III)900SD $2.50 $1.25 $2.20 $1.25 $2.05 $2.06 $2.54 $2.00
210880(E)6600 WARNING LIGHTS(TYPE A)1,980SD $0.9000 $0.5000 $1.10 $0.5000 $1.05 $1.03 $1.27 $0.7500
220642(B)3300 CONSTRUCTION STAKING LEVEL II1LSUM $7,500.00 $1,500.00 $5,500.00 $5,500.00 $12,625.00 $5,150.00 $7,327.64 $8,500.00
230220 1100 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $7,500.00 $1,500.00 $3,000.00 $1,775.00 $1,590.00 $2,800.00 $3,176.76 $4,000.00
240641 2100 MOBILIZATION1LSUM $62,000.00 $52,500.00 $35,000.00 $39,500.00 $51,700.00 $61,000.00 $59,917.10 $60,000.00