Resurface (Asphalt)
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $4,537,363 | ||
| 1 | J&R Constructors Group Low bidder | $3,860,220 | -14.9% | |
| 2 | THE CUMMINS CONSTRUCTION CO., INC. | $3,934,410 | -13.3% | +1.9% |
| 3 | OVERLAND CORPORATION | $4,581,438 | +1.0% | +18.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J&R Constructor… | #2 THE CUMMINS CON… | #3 OVERLAND CORPOR… |
|---|---|---|---|---|---|---|---|---|
| 10 | 407(C)7400 | (SP) POLYMER MOD. CATIONIC RAPID SET - 1S | 57,650 | GAL | $4.25 | $3.00 | $3.15 | $3.00 |
| 20 | 411(C)1420 | SUPERPAVE, TYPE S4(PG 70-28 OK) | 25,850 | TON | $120.00 | $120.00 | $111.25 | $136.75 |
| 30 | 412 3100 | COLD MILLING PAVEMENT | 231,000 | SY | $3.50 | $1.30 | $2.05 | $2.00 |
| 40 | 856(A)8207 | (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE) | 192,000 | LF | $0.7000 | $0.7200 | $0.8000 | $0.7500 |
| 50 | 880(A)6220 | ARROW DISPLAY(TYPE C) | 90 | SD | $15.00 | $3.00 | $26.50 | $25.00 |
| 60 | 880(J)7100 | (SP) CONSTRUCTION TRAFFIC CONTROL | 45 | SD | $100.00 | $564.00 | $424.00 | $400.00 |
| 70 | 882(A)8210 | PORT.CHANGEABLE MESSAGE SIGN | 90 | SD | $40.00 | $12.00 | $26.50 | $25.00 |
| 80 | 641 2110 | MOBILIZATION | 1 | LSUM | $238,000.00 | $120,000.00 | $226,000.00 | $245,000.00 |