Bid tab 250063

Let May 15, 2025 · Division 2 · Bryan

‹ May 2025 results

Pedestrian Improvements (Sidewalk)

Let date
Thursday, May 15, 2025
Contract
250063 · job page
J/P numbers
35662(04)
District
Division 2
County
Bryan
Highway
SH-22
Limits
SH-22: FROM 0.1 MI EAST OF THE US-69 INTERSECTION, EXTEND EAST IN CADDO.
Classification
Pedestrian Improvements (Sidewalk) ·
Project number
STP-207C(130)AD
Working days
150

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$653,294
1 HUB Construction, Inc. Low bidder $667,635 +2.2%
2 SCHIRALLI CONSTRUCTION CORP. $695,443 +6.5% +4.2%
3 Treas Construction Inc $730,229 +11.8% +9.4%
4 L & N BRIDGE, LLC $782,404 +19.8% +17.2%
5 Built Right Construction, LLC $788,144 +20.6% +18.1%
6 TI-ZACK CONCRETE, LLC $942,175 +44.2% +41.1%
7 RUDY CONSTRUCTION CO. $1,049,487 +60.6% +57.2%

Bid tab: unit prices 46 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 HUB Constructio…#2 SCHIRALLI CONST…#3 Treas Construct…#4 L & N BRIDGE, L…#5 Built Right Con…#6 TI-ZACK CONCRET…#7 RUDY CONSTRUCTI…
10201(A)1200 CLEARING AND GRUBBING1LSUM $15,000.00 $2,500.00 $6,291.24 $15,260.00 $10,000.00 $2,000.00 $11,550.00 $10,000.00
20201(B)1300 SELECTIVE CLEARING1LSUM $5,000.00 $5,500.00 $4,417.94 $4,087.50 $7,500.00 $3,500.00 $11,550.00 $10,000.00
30202(A)2200 UNCLASSIFIED EXCAVATION71.25CY $10.00 $12.00 $86.38 $21.80 $20.00 $25.00 $63.49 $35.00
40202(D)2500 UNCLASSIFIED BORROW97.5CY $15.00 $71.00 $73.76 $38.15 $30.00 $25.00 $57.99 $50.00
50221(B)2300 TEMPORARY SILT FENCE4,182LF $3.00 $2.50 $2.75 $4.36 $2.50 $4.00 $1.10 $5.00
60221(E)2600 TEMPORARY SILT DIKE7LF $15.00 $10.00 $8.80 $54.50 $8.00 $25.00 $5.50 $25.00
70230(A)7200 SOLID SLAB SODDING2,938SY $7.50 $5.00 $4.95 $6.54 $4.50 $5.00 $7.70 $5.00
80232(B)9300 SEEDING METHOD B0.58AC $1,500.00 $250.00 $990.00 $2,725.00 $900.00 $1,500.00 $11,000.00 $12,000.00
90233(A)0200 VEGETATIVE MULCHING0.58AC $1,500.00 $550.00 $1,320.00 $2,725.00 $1,200.00 $2,000.00 $55,000.00 $5,000.00
100303(A)1200 AGGREGATE BASE TYPE A109.25CY $115.00 $105.00 $108.74 $107.91 $175.00 $85.00 $45.98 $80.00
110609(B)4330 1'-8" COMB.CRB.& GUT.(6" BARRIER)230LF $45.00 $35.00 $48.15 $27.25 $70.00 $50.00 $63.40 $60.00
120609(C)4400 CONCRETE HEADER CURB (6"X 16")365LF $35.00 $25.00 $39.71 $27.25 $35.00 $40.00 $53.65 $55.00
130610(A)5200 4" CONCRETE SIDEWALK2,719.75SY $65.00 $70.00 $73.57 $67.53 $92.00 $80.00 $96.53 $125.00
140610(A)5220 6" CONCRETE SIDEWALK426.01SY $65.00 $75.00 $85.18 $80.30 $105.00 $90.00 $131.46 $250.00
150610(B)5300 6" CONCRETE DRIVEWAY (H.E.S.)570SY $75.00 $95.00 $86.96 $80.30 $125.00 $100.00 $131.46 $150.00
160610(I)6000 TACTILE WARNING DEVICE-NEW417SF $35.00 $35.00 $44.04 $31.66 $26.40 $35.00 $42.00 $45.00
170611(G)7700 SPECIAL INLET DRAIN6EA $6,000.00 $3,200.00 $4,342.79 $5,277.23 $2,500.00 $2,500.00 $165.00 $4,000.00
180613(E)5900 18" CORRUGATED POLYETHYLENE PIPE16LF $125.00 $70.29 $148.27 $66.23 $100.00 $75.00 $165.00 $125.00
190613(EE)5965 15" CORRUGATED POLYPROPYLENE PIPE5LF $100.00 $120.00 $178.22 $58.90 $150.00 $100.00 $137.50 $110.00
200613(L)6704 15" PREFAB. CULVERT END SEC., ROUND1EA $750.00 $1,400.00 $525.54 $486.65 $200.00 $550.00 $825.00 $500.00
210613(L)6708 18" PREFAB. CULVERT END SEC., ROUND4EA $900.00 $1,800.00 $586.78 $670.21 $250.00 $550.00 $1,100.00 $750.00
220619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $2,000.00 $3,500.00 $6,291.24 $2,725.00 $2,000.00 $2,000.00 $5,654.40 $5,000.00
230619(B)6356 REMOVAL OF CURB AND GUTTER12LF $10.00 $35.00 $39.97 $21.80 $15.00 $15.00 $47.12 $25.00
240619(B)6380 REMOVAL OF CONCRETE DRIVEWAY130SY $10.00 $25.00 $15.71 $16.35 $15.00 $10.00 $4.35 $25.00
250619(B)6384 REMOVAL OF ASPHALT DRIVEWAY242SY $10.00 $15.00 $13.37 $10.90 $6.00 $10.00 $23.37 $25.00
260619(B)6386 REMOVAL OF GRAVEL DRIVEWAY335SY $10.00 $10.00 $8.37 $10.90 $4.00 $10.00 $16.88 $25.00
270619(B)6404 REMOVAL OF SIDEWALK1,154SY $10.00 $8.00 $10.40 $13.08 $4.00 $10.00 $29.40 $25.00
280619(B)6440 REMOVAL OF EXISTING PIPE30LF $10.00 $20.00 $33.99 $5.45 $15.00 $10.00 $27.50 $25.00
290619(C)6600 SAWING PAVEMENT725LF $7.00 $8.00 $5.54 $6.54 $6.00 $13.00 $5.50 $5.00
300622(A)0210 1 1/2" PIPE RAILING417LF $100.00 $150.00 $119.11 $140.06 $157.00 $250.00 $280.50 $150.00
310629(D)7500 REMOVE AND RESET MAILBOX2EA $320.00 $200.00 $306.25 $327.00 $250.00 $350.00 $495.00 $500.00
320805(D)3504 (PL)REMOVE & RESET LIGHT POLE5EA $3,500.00 $8,600.00 $5,500.00 $8,556.50 $7,850.00 $10,000.00 $8,635.00 $9,500.00
330805(D)3528 (PL)REMOVE & RESET EXISTING SIGNS4EA $175.00 $400.00 $275.00 $436.00 $400.00 $500.00 $495.00 $1,500.00
340836 7100 REGULATORY OR WARNING SIGN ASSEMBLY4EA $6,000.00 $9,400.00 $9,350.00 $10,137.00 $9,300.00 $11,000.00 $10,230.00 $11,000.00
350850(A)1200 SHEET ALUMINUM SIGNS95SF $25.00 $18.00 $27.50 $19.62 $18.00 $25.00 $19.80 $80.00
360851(C)2415 2" SQUARE TUBE POST22LF $13.00 $8.00 $16.50 $8.72 $8.00 $11.00 $8.80 $80.00
370856(A)8219 (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(24" WIDE)685LF $20.00 $22.00 $19.80 $24.85 $22.80 $25.00 $25.08 $30.00
380880(B)6300 CONSTRUCTION SIGNS 0 TO 6.25 SF2,760SD $0.7500 $4.92 $1.10 $5.34 $4.90 $4.90 $5.39 $0.0100
390880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF2,415SD $1.25 $4.95 $1.65 $5.34 $4.90 $4.90 $5.39 $0.0100
400880(C)6410 CONSTRUCTION BARRICADES(TYPE III)4,485SD $2.50 $1.20 $0.1100 $1.09 $1.00 $1.00 $1.10 $0.0100
410880(E)6607 WARNING LIGHTS(TYPE B)43,125SD $0.1500 $0.0500 $0.0100 $0.0200 $0.0200 $0.0200 $0.0200 $0.0100
420880(G)6805 CHANNELIZER CONES39,392.45SD $0.7500 $0.0500 $0.3300 $0.0200 $0.0200 $0.0200 $0.0200 $0.0100
430880(I)7000 FLAGGER50SD $100.00 $150.00 $110.02 $163.50 $120.00 $5.00 $71.50 $300.00
440642(B)3300 CONSTRUCTION STAKING LEVEL II1LSUM $10,000.00 $5,000.00 $10,529.62 $19,620.00 $11,000.00 $21,000.00 $9,350.00 $15,000.00
450220 1100 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $2,500.00 $5,071.41 $2,725.00 $1,500.00 $3,500.00 $6,050.00 $5,000.00
460641 2110 MOBILIZATION1LSUM $55,014.43 $35,000.00 $63,232.34 $64,277.76 $64,000.00 $55,000.00 $50,062.73 $70,000.00