| 10 | AWOS-001 |
Replace Existing Automated Weather Observing System (AWOS) Components | 1 | LSUM |
$102,000.00 |
$103,180.00 |
$147,000.00 |
| 20 | C-105-001 |
Mobilization | 1 | LSUM |
$11,500.00 |
$3,000.00 |
$10,000.00 |
| 30 | TEMP-001 |
Temporary Marking, Lighting & Barricades | 1 | LSUM |
$5,000.00 |
$0.00 |
$3,500.00 |
| 40 | AWOS-001 |
Replace Existing Automated Weather Observing System (AWOS) Components | 1 | LSUM |
$102,000.00 |
$103,180.00 |
$147,000.00 |
| 50 | C-105-001 |
Mobilization | 1 | LSUM |
$11,500.00 |
$3,000.00 |
$10,000.00 |
| 60 | TEMP-001 |
Temporary Marking, Lighting & Barricades | 1 | LSUM |
$5,000.00 |
$0.00 |
$3,500.00 |
| 70 | AWOS-001 |
Replace Existing Automated Weather Observing System (AWOS) Components | 1 | LSUM |
$102,000.00 |
$103,180.00 |
$147,000.00 |
| 80 | C-105-001 |
Mobilization | 1 | LSUM |
$11,500.00 |
$3,000.00 |
$15,000.00 |
| 90 | TEMP-001 |
Temporary Marking, Lighting & Barricades | 1 | LSUM |
$5,000.00 |
$0.00 |
$3,500.00 |
| 100 | AWOS-002 |
Furnish and Install Automated Weather Observing System (AWOS) | 1 | LSUM |
$215,500.00 |
$199,385.00 |
$168,000.00 |
| 110 | C-105-001 |
Mobilization | 1 | LSUM |
$23,000.00 |
$7,000.00 |
$10,000.00 |
| 120 | TEMP-001 |
Temporary Marking, Lighting & Barricades | 1 | LSUM |
$12,000.00 |
$4,000.00 |
$3,500.00 |