RIGHT-OF-WAY CLEARANCE SH-28: FROM 8.1 MILES EAST OF THE US -69 JUNCTION, EXTEND NORTHEAST NEAR LANGLEY . PROJECT LENGTH = 4.771 MILES
- Let date
- Thursday, February 17, 2022
- Contract
- 220064
- J/P numbers
- 23270(08)
- District
- Division 8
- County
- Mayes
- Highway
- Limits
- RIGHT-OF-WAY CLEARANCE SH-28: FROM 8.1 MILES EAST OF THE US -69 JUNCTION, EXTEND NORTHEAST NEAR LANGLEY . PROJECT LENGTH = 4.771 MILES
- Project number
- SSP-249C(073)RW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $188,800 | ||
| 1 | Rosscon, LLC Low bidder | $156,700 | -17.0% | |
| 2 | Robin Hausner Demolition, LLC | $168,000 | -11.0% | +7.2% |
| 3 | Timber Wolf Excavating, LLC | $743,200 | +293.6% | +374.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Rosscon, LLC | #2 Robin Hausner D… | #3 Timber Wolf Exc… |
|---|---|---|---|---|---|---|---|---|
| 10 | 233(A)0200 | VEGETATIVE MULCHING | 1 | AC | $7,800.00 | $3,500.00 | $100.00 | $15,000.00 |
| 20 | 619(G)7000 | RIGHT-OF-WAY CLEARANCE | 1 | LSUM | $166,000.00 | $122,700.00 | $165,900.00 | $485,000.00 |
| 30 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $5,000.00 | $5,500.00 | $500.00 | $158,200.00 |
| 40 | 641 2110 | MOBILIZATION | 1 | LSUM | $10,000.00 | $25,000.00 | $1,500.00 | $85,000.00 |