RIGHT-OF-WAY CLEARANCE SH-29: FROM 11.5 MILES EAST OF THE US -81 JUNCTION, EXTEND EAST NEAR BRAY . PROJECT LENGTH = 5.890 MILES
- Let date
- Thursday, May 20, 2021
- Contract
- 210157
- J/P numbers
- 29657(14)
- District
- Division 7
- County
- Stephens
- Highway
- Limits
- RIGHT-OF-WAY CLEARANCE SH-29: FROM 11.5 MILES EAST OF THE US -81 JUNCTION, EXTEND EAST NEAR BRAY . PROJECT LENGTH = 5.890 MILES
- Project number
- SSP-269B(087)RW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $131,100 | ||
| 1 | Robin Hausner Demolition, LLC Low bidder | $87,288 | -33.4% | |
| 2 | Built Right Construction, LLC | $97,500 | -25.6% | +11.7% |
| 3 | CONCRETE SERVICES CORPORATION | $200,000 | +52.6% | +129.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Robin Hausner D… | #2 Built Right Con… | #3 CONCRETE SERVIC… |
|---|---|---|---|---|---|---|---|---|
| 10 | 233(A)0200 | VEGETATIVE MULCHING | 1 | AC | $1,000.00 | $100.00 | $2,500.00 | $2,450.00 |
| 20 | 619(G)7000 | RIGHT-OF-WAY CLEARANCE | 1 | LSUM | $123,100.00 | $84,188.00 | $80,000.00 | $178,000.00 |
| 30 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $1,000.00 | $500.00 | $5,000.00 | $1,550.00 |
| 40 | 641 2110 | MOBILIZATION | 1 | LSUM | $6,000.00 | $2,500.00 | $10,000.00 | $18,000.00 |