RESURFACE (ASPHALT ) COUNTY ROAD (NS-359/BRIDGEVIEW ROAD): FROM THE SH -199 JUNCTION, EXTEND SOUTH NEAR LITTLE CITY. PROJECT LENGTH = 4.000 MILES
- Let date
- Thursday, March 14, 2019
- Contract
- 190118
- J/P numbers
- 32355(04)
- District
- Division 2
- County
- Marshall
- Highway
- Limits
- RESURFACE (ASPHALT ) COUNTY ROAD (NS-359/BRIDGEVIEW ROAD): FROM THE SH -199 JUNCTION, EXTEND SOUTH NEAR LITTLE CITY. PROJECT LENGTH = 4.000 MILES
- Project number
- CIRB-248D(041)RB
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,002,839 | ||
| 1 | THE CUMMINS CONSTRUCTION CO., INC. Low bidder | $939,291 | -6.3% | |
| 2 | OVERLAND CORPORATION | $1,143,552 | +14.0% | +21.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 THE CUMMINS CON… | #2 OVERLAND CORPOR… |
|---|---|---|---|---|---|---|---|
| 1 | 402(E) 0225 | TRAFFIC BOUND SURFACE COURSE TYPE E | 1,900 | TON | $21.50 | $24.60 | $25.95 |
| 2 | 407(D) 0401 | (SP) NT TACK MATERIAL | 8,270 | GAL | $3.00 | $3.05 | $2.01 |
| 3 | 411(C) 5960 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 4,440 | TON | $85.00 | $71.65 | $85.25 |
| 4 | 411(H) 6210 | SUPERPAVE, TYPE S3(PATCH)(PG64-22OK) | 1,750 | TON | $65.00 | $80.00 | $118.70 |
| 5 | 411(J) 6410 | (SP) RICH INTERMEDIATE LAYER | 4,440 | TON | $75.00 | $76.70 | $95.65 |
| 6 | 854(A) 8800 | TRAFFIC STRIPE(PAINT)(4" WIDE) | 84,480 | LF | $0.1700 | $0.0900 | $0.0900 |
| 7 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $7,500.00 | $13,350.00 | $36,600.00 |
| 8 | 641 1552 | MOBILIZATION | 1 | LSUM | $91,167.00 | $47,700.00 | $22,500.00 |