| 1 | 407(C) 0301 |
(SP) POLYMER MODIFIED CATIONIC RAPID SET - 1S | 45,253 | GAL |
$2.50 |
$1.90 |
$2.20 |
$2.00 |
$1.99 |
| 2 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 15,200 | TON |
$78.00 |
$75.50 |
$70.93 |
$79.00 |
$78.00 |
| 3 | 411(I) 6310 |
SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 250 | TON |
$125.00 |
$125.00 |
$125.00 |
$140.00 |
$175.00 |
| 4 | 412 5267 |
COLD MILLING PAVEMENT | 116,340 | SY |
$2.25 |
$0.7700 |
$1.49 |
$1.00 |
$0.7100 |
| 5 | 413(A) 4870 |
RUMBLE STRIP-CENTERLINE HMA-CON | 35,675 | LF |
$0.2500 |
$0.1600 |
$0.4100 |
$0.2000 |
$0.3800 |
| 6 | 413(B) 4863 |
RUMBLE STRIP-METHOD HMA-CYC | 78,355 | LF |
$0.2000 |
$0.1300 |
$0.3800 |
$0.2000 |
$0.2300 |
| 7 | 856(A) 8535 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 119,860 | LF |
$0.7000 |
$0.4800 |
$0.4800 |
$0.4800 |
$0.4800 |
| 8 | 856(A) 8548 |
TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 960 | LF |
$2.50 |
$1.18 |
$1.18 |
$1.18 |
$1.18 |
| 9 | 856(B) 8860 |
TRAFFIC STRIPE(MULTI-POLY.)(ARROWS) | 9 | EA |
$200.00 |
$65.00 |
$65.00 |
$65.00 |
$65.00 |
| 10 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$14,000.00 |
$15,000.00 |
$7,910.00 |
$30,000.00 |
$65,215.00 |
| 11 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$100,000.00 |
$103,000.00 |
$100,000.00 |
$70,000.00 |
$108,000.00 |