Bid tab 170219

Let Jul 20, 2017 · Division 1 · Cherokee Sign up free

‹ Jul 2017 results

RIGHT-OF-WAY CLEARANCE US-62/SH-51: US-62, FROM 0.3 MI NE OF THE SH -51 JCT, EXT W . SH-51: FROM SH-62 JCT, EXTEND SOUTH NEAR ELDON. PROJECT LENGTH = 1.25 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE

Let date
Thursday, July 20, 2017
Contract
170219
J/P numbers
10437(07)
District
Division 1
County
Cherokee
Highway
Limits
RIGHT-OF-WAY CLEARANCE US-62/SH-51: US-62, FROM 0.3 MI NE OF THE SH -51 JCT, EXT W . SH-51: FROM SH-62 JCT, EXTEND SOUTH NEAR ELDON. PROJECT LENGTH = 1.25 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE
Project number
STPY-211C(028)RW

Bidders 11

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$112,738
1 Robin Hausner Demolition, LLC Low bidder $32,222 -71.4%
2 M & M WRECKING, INC. $36,116 -68.0% +12.1%
3 J.E. DIRT WURX, LLC $44,400 -60.6% +37.8%
4 T. McDonald Construction, Inc. $54,500 -51.7% +69.1%
5 RMR DEMOLITION, LLC $58,300 -48.3% +80.9%
6 RCR CONSTRUCTION, INC $87,475 -22.4% +171.5%
7 ZENITH CONSTRUCTION CO. $117,700 +4.4% +265.3%
8 Bronze Oak, LLC $120,500 +6.9% +274.0%
9 WOLFPACK TRUCKING GRADING L.L.C $129,485 +14.9% +301.9%
10 GLOVER & ASSOCIATES, INC. $130,000 +15.3% +303.5%
11 MIDWEST WRECKING, INC. $136,175 +20.8% +322.6%

Bid tab: unit prices 2 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Robin Hausner D…#2 M & M WRECKING,…#3 J.E. DIRT WURX,…#4 T. McDonald Con…#5 RMR DEMOLITION,…#6 RCR CONSTRUCTIO…#7 ZENITH CONSTRUC…#8 Bronze Oak, LLC
1619(G) 0094 RIGHT-OF-WAY CLEARANCE1LSUM $107,738.00 $31,222.00 $36,116.00 $42,400.00 $47,500.00 $58,150.00 $82,475.00 $110,700.00 $115,000.00
2880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $5,000.00 $1,000.00 $0.00 $2,000.00 $7,000.00 $150.00 $5,000.00 $7,000.00 $5,500.00

Showing the first 8 bidders. The Excel and CSV downloads include all 11.