$309.12Avg low bid / EA
$347.66Avg of all bids
$218.33Avg engineer's estimate
3Jobs · 731 EA
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 1 | 38 | $948.55 | $1,380.56 |
| 2020 | 1 | 20 | $612.50 | $830.06 |
| 2018 | 1 | 673 | $264.00 | $289.67 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 15, 2021 | 210197 | Stp-270c(036)ad | 26 EA | $1,020.00 | RUDY CONSTRUCTION CO. |
| Jul 15, 2021 | 210197 | Stp-270c(036)ad | 5 EA | $925.00 | RUDY CONSTRUCTION CO. |
| Jul 15, 2021 | 210197 | Stp-270c(036)ad | 7 EA | $700.00 | RUDY CONSTRUCTION CO. |
| Oct 15, 2020 | 200319 | OklahomaDivision 4 | 7 EA | $650.00 | CGC, LLC. |
| Oct 15, 2020 | 200319 | OklahomaDivision 4 | 1 EA | $500.00 | CGC, LLC. |
| Oct 15, 2020 | 200319 | OklahomaDivision 4 | 12 EA | $600.00 | CGC, LLC. |
| May 17, 2018 | 180190 | ClevelandDivision 3 | 673 EA | $264.00 | Silver Star Construction Company, Inc. |