MT. VERNON
- Let date
- Friday, January 18, 2019
- Contract
- MV064
- District
- District 9
- County
- Jefferson
- Highway
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stutz Excavating, Inc. Low bidder | $90,728 | ||
| 2 | Rooter's American Maintenance, Inc. | $105,097 | +15.8% | |
| 3 | Southern Illinois Asphalt Co., Inc. | $148,276 | +63.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stutz Excavatin… | #2 Rooter's Americ… | #3 Southern Illino… |
|---|---|---|---|---|---|---|---|---|
| 1 | AR150520 | MOBILIZATION | 1 | L.S. | $7,125.00 | $2,175.00 | $29,806.69 | |
| 2 | AR152480 | SHOULDER ADJUSTMENT | 1,245 | S.Y. | $8.85 | $9.85 | $13.53 | |
| 3 | AR156520 | INLET PROTECTION | 4 | EACH | $75.00 | $250.00 | $297.50 | |
| 4 | AR401111 | PAVEMENT PREPARATION | 1,930 | S.Y. | $6.30 | $10.60 | $7.70 | |
| 5 | AR401613 | BIT. SURF. CSE.-METHOD I, SUPERPAVE | 225 | TON | $122.00 | $125.00 | $174.87 | |
| 6 | AR401620 | BIT. SURFACE COURSE, LEVELING | 225 | TON | $120.00 | $125.00 | $174.87 | |
| 7 | AR401655 | BUTT JOINT CONSTRUCTION | 70 | S.Y. | $6.90 | $7.15 | $39.08 | |
| 8 | AR602510 | BITUMINOUS PRIME COAT | 676 | GAL. | $4.60 | $6.95 | $0.00 | |
| 9 | AR603510 | BITUMINOUS TACK COAT | 290 | GAL. | $0.0100 | $8.80 | $0.00 | |
| 10 | AR901510 | SEEDING | 0.26 | ACRE | $4,000.00 | $12,000.00 | $8,568.00 | |
| 11 | AR908510 | MULCHING | 0.26 | ACRE | $4,000.00 | $8,000.00 | $7,378.00 |