DUPAGE
- Let date
- Friday, July 30, 2021
- Contract
- DU089
- District
- District 1
- County
- Dupage
- Highway
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Hecker and Company, Inc. Low bidder | $711,930 | ||
| 2 | J. Ranck Electric, Inc. | $824,043 | +15.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Hecker and Comp… | #2 J. Ranck Electr… |
|---|---|---|---|---|---|---|---|
| 1 | AR108108 | 1/C #8 5 KV UG CABLE | 54,930 | L.F. | $1.71 | $1.50 | |
| 2 | AR108706 | 1/C #6 COUNTERPOISE | 4,220 | L.F. | $3.40 | $1.50 | |
| 3 | AR108960 | REMOVE CABLE | 54,930 | L.F. | $0.3000 | $0.2500 | |
| 4 | AR109440 | TEMPORARY WIRING | 1 | L.S. | $8,430.00 | $5,000.00 | |
| 5 | AR110000 | DIRECTIONAL BORE | 1,300 | L.F. | $74.00 | $72.00 | |
| 6 | AR110501 | 1-WAY CONC. ENCASED DUCT | 120 | L.F. | $82.50 | $60.00 | |
| 7 | AR110506 | 6-WAY CONCRETE ENCASED DUCT | 2,800 | L.F. | $103.00 | $110.00 | |
| 8 | AR110610 | ELECTRICAL HANDHOLE | 10 | EACH | $10,600.00 | $10,500.00 | |
| 9 | AR110906 | REMOVE ELECTRICAL HANDHOLE | 2 | EACH | $1,390.00 | $1,750.00 | |
| 10 | AR150520 | MOBILIZATION | 1 | L.S. | $42,700.00 | $169,250.00 | |
| 11 | AR150530 | TRAFFIC MAINTENANCE | 1 | L.S. | $18,100.00 | $20,000.00 | |
| 12 | AR156515 | STRAW WATTLE | 125 | L.F. | $19.00 | $15.00 | |
| 13 | AR156520 | INLET PROTECTION | 12 | EACH | $377.00 | $300.00 | |
| 14 | AR901510 | SEEDING | 0.6 | ACRE | $6,040.00 | $3,500.00 | |
| 15 | AR908510 | MULCHING | 0.6 | ACRE | $6,900.00 | $4,100.00 |