23-00170-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $1,930,584 | ||
| 2 | Samron Midwest Contracting, Inc. | $1,967,967 | +1.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X4060101 | TRACKLESS TACK | 77,387 | POUND | $0.0100 | $0.0100 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $53,083.99 | $36,000.00 | |
| 3 | 40600982 | HMA SURF REM BUTT JT | 381 | SQ YD | $19.84 | $15.00 | |
| 4 | 40600990 | TEMPORARY RAMP | 127 | SQ YD | $17.10 | $10.00 | |
| 5 | 40602985 | HMA BC IL-9.5 N70 | 9,930 | TON | $77.55 | $79.00 | |
| 6 | 40604052 | HMA SC IL-9.5 C N70 | 10,450 | TON | $79.11 | $84.00 | |
| 7 | 44000151 | HMA SURF REM 1/2 | 1,629 | SQ YD | $5.13 | $7.00 | |
| 8 | 48100100 | AGGREGATE SHLDS A | 2,140 | TON | $53.53 | $34.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $97,677.33 | $114,487.04 | |
| 10 | 70300100 | SHORT TERM PAVT MKING | 8,500 | FOOT | $1.38 | $1.50 | |
| 11 | 70300150 | SHRT TRM PAVT MK REM | 2,835 | SQ FT | $0.0100 | $1.75 | |
| 12 | 78001110 | PAINT PVT MK LINE 4 | 124,906 | FOOT | $0.1300 | $0.1400 | |
| 13 | 78100100 | RAISED REFL PAVT MKR | 530 | EACH | $37.45 | $43.00 | |
| 14 | 78300200 | RAISED REF PVT MK REM | 530 | EACH | $3.38 | $10.00 |