21-00226-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $3,038,200 | ||
| 2 | Samron Midwest Contracting, Inc. | $3,121,846 | +2.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | XX006821 | CONC TRUCK WASHOUT | 1 | L SUM | $3,569.69 | $1,200.00 | |
| 2 | XX008385 | CONC REM SPEC | 2 | EACH | $6,345.73 | $7,000.00 | |
| 3 | X0325893 | CLEAN EX END SECTION | 5 | EACH | $1,756.42 | $800.00 | |
| 4 | X0326697 | CENTERLN RUM STRIP 8 | 2,566 | FOOT | $5.03 | $2.00 | |
| 5 | X0358300 | REM & RELAY END SECT | 18 | EACH | $1,440.54 | $1,750.00 | |
| 6 | X0900064 | MEMBR WTRPR SYS B STR | 21 | SQ YD | $281.44 | $35.00 | |
| 7 | X4401198 | HMA SURF REM VAR DP | 1,063 | SQ YD | $8.26 | $17.00 | |
| 8 | X5500458 | STORM SEWER 18 SPL | 20 | FOOT | $325.31 | $117.00 | |
| 9 | X5510008 | STORM SEWER REPAIR | 150 | FOOT | $159.00 | $114.00 | |
| 10 | X6330725 | SPBGR (SHORT RADIUS) | 135 | FOOT | $74.20 | $50.00 | |
| 11 | 20100110 | TREE REMOV 6-15 | 72 | UNIT | $90.69 | $27.00 | |
| 12 | 20100210 | TREE REMOV OVER 15 | 50 | UNIT | $130.59 | $40.00 | |
| 13 | 20200100 | EARTH EXCAVATION | 1,733 | CU YD | $31.77 | $0.0100 | |
| 14 | 20200600 | EXC & GR EX SHOULDER | 683 | UNIT | $245.60 | $175.00 | |
| 15 | 20400800 | FURNISHED EXCAVATION | 1,000 | CU YD | $41.34 | $0.0100 | |
| 16 | 20700110 | POROUS GRAN EMBANK | 109 | TON | $121.44 | $30.00 | |
| 17 | 21400100 | GRADING & SHAP DITCH | 2,173 | FOOT | $18.67 | $10.00 | |
| 18 | 25000312 | SEEDING CL 4A | 4.75 | ACRE | $3,630.50 | $3,800.00 | |
| 19 | 25000314 | SEEDING CL 4B | 0.41 | ACRE | $8,718.51 | $9,000.00 | |
| 20 | 25000400 | NITROGEN FERT NUTR | 465 | POUND | $1.70 | $2.00 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 465 | POUND | $1.70 | $2.00 | |
| 22 | 25100635 | HD EROS CONTR BLANKET | 25,000 | SQ YD | $1.96 | $2.00 | |
| 23 | 28000250 | TEMP EROS CONTR SEED | 516 | POUND | $9.01 | $2.00 | |
| 24 | 28100107 | STONE RIPRAP CL A4 | 29 | SQ YD | $193.64 | $77.00 | |
| 25 | 28200200 | FILTER FABRIC | 29 | SQ YD | $29.57 | $20.00 | |
| 26 | 31101900 | SUB GRAN MAT C | 3,036 | TON | $51.99 | $60.00 | |
| 27 | 40200800 | AGG SURF CSE B | 86 | TON | $48.34 | $45.00 | |
| 28 | 40600290 | BIT MATLS TACK CT | 54,242 | POUND | $0.0100 | $0.0100 | |
| 29 | 40600370 | LONG JOINT SEALANT | 21,443 | FOOT | $2.77 | $3.50 | |
| 30 | 40600982 | HMA SURF REM BUTT JT | 500 | SQ YD | $14.26 | $15.00 | |
| 31 | 40600990 | TEMPORARY RAMP | 50 | SQ YD | $63.83 | $25.00 | |
| 32 | 40602970 | HMA BC IL-9.5FG N70 | 4,170 | TON | $107.40 | $105.00 | |
| 33 | 40604002 | HMA SC IL-9.5FG C N70 | 4,866 | TON | $104.95 | $110.00 | |
| 34 | 48102100 | AGG WEDGE SHLD TYPE B | 1,766 | TON | $48.34 | $49.00 | |
| 35 | 48203011 | HMA SHOULDERS 3 1/2 | 9,432 | SQ YD | $21.50 | $30.00 | |
| 36 | 48203021 | HMA SHOULDERS 6 | 5,750 | SQ YD | $36.24 | $50.00 | |
| 37 | 50104400 | CONC HDWL REM | 4 | EACH | $1,367.93 | $500.00 | |
| 38 | 50800105 | REINFORCEMENT BARS | 4,190 | POUND | $2.85 | $2.00 | |
| 39 | 52200020 | TEMP SOIL RETEN SYSTM | 256 | SQ FT | $199.71 | $300.00 | |
| 40 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $16,820.39 | $30,000.00 | |
| 41 | 54001002 | BOX CUL END SEC C2 | 2 | EACH | $23,970.39 | $30,000.00 | |
| 42 | 54213663 | PRC FLAR END SEC 18 | 2 | EACH | $4,107.50 | $2,000.00 | |
| 43 | 54248510 | CONCRETE COLLAR | 9 | CU YD | $5,436.20 | $170.00 | |
| 44 | 59100100 | GEOCOMPOSITE WALL DR | 21 | SQ YD | $84.30 | $25.00 | |
| 45 | 60600605 | CONC CURB TB | 160 | FOOT | $59.80 | $118.00 | |
| 46 | 63000003 | SPBGR TY A 9FT POSTS | 2,888 | FOOT | $37.10 | $38.00 | |
| 47 | 63000350 | LSG OV CUL 12'6" SPAN | 150 | FOOT | $47.70 | $62.00 | |
| 48 | 63100085 | TRAF BAR TERM T6 | 8 | EACH | $4,770.00 | $5,000.00 | |
| 49 | 63100167 | TR BAR TRM T1 SPL TAN | 14 | EACH | $4,134.00 | $3,500.00 | |
| 50 | 63200310 | GUARDRAIL REMOV | 1,164 | FOOT | $5.83 | $6.50 | |
| 51 | 64200108 | SHOULDER RUM STRIP 8 | 63,177 | FOOT | $0.1800 | $0.4000 | |
| 52 | 67100100 | MOBILIZATION | 1 | L SUM | $164,029.95 | $185,000.00 | |
| 53 | 70100100 | TRAF CONT-PROT 701316 | 2 | EACH | $10,049.38 | $50,000.00 | |
| 54 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $91,688.85 | $31,500.00 | |
| 55 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.0100 | $0.0100 | |
| 56 | 70103815 | TR CONT SURVEILLANCE | 80 | CAL DA | $0.0100 | $0.0100 | |
| 57 | 70300100 | SHORT TERM PAVT MKING | 4,289 | FOOT | $1.48 | $1.00 | |
| 58 | 70300150 | SHRT TRM PAVT MK REM | 1,430 | SQ FT | $0.0100 | $3.00 | |
| 59 | 72000100 | SIGN PANEL T1 | 176 | SQ FT | $29.68 | $40.00 | |
| 60 | 72400310 | REMOV SIGN PANEL T1 | 50 | SQ FT | $34.59 | $40.00 | |
| 61 | 72501000 | TERMINAL MARKER - DA | 14 | EACH | $53.00 | $45.00 | |
| 62 | 72900100 | METAL POST TY A | 430 | FOOT | $21.20 | $25.00 | |
| 63 | 78000200 | THPL PVT MK LINE 4 | 95,130 | FOOT | $0.7600 | $0.8000 |