20-00189-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $967,116 | ||
| 2 | Samron Midwest Contracting, Inc. | $1,033,370 | +6.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | 40200800 | AGG SURF CSE B | 39 | TON | $47.70 | $85.00 | |
| 2 | 40600275 | BIT MATLS PR CT | 3,290 | POUND | $0.0100 | $0.0100 | |
| 3 | 40600982 | HMA SURF REM BUTT JT | 307 | SQ YD | $25.86 | $10.00 | |
| 4 | 40603085 | HMA BC IL-19.0 N70 | 3,965 | TON | $91.61 | $95.00 | |
| 5 | 40604052 | HMA SC IL-9.5 C N70 | 3,101 | TON | $100.94 | $106.00 | |
| 6 | 48100100 | AGGREGATE SHLDS A | 4,600 | TON | $47.70 | $45.29 | |
| 7 | 67100100 | MOBILIZATION | 1 | L SUM | $29,703.62 | $62,000.00 | |
| 8 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $22,022.75 | $39,500.00 | |
| 9 | 70300100 | SHORT TERM PAVT MKING | 2,719 | FOOT | $1.32 | $2.00 | |
| 10 | 78001110 | PAINT PVT MK LINE 4 | 39,372 | FOOT | $0.1600 | $0.1600 |