07-00163-00-RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $989,256 | ||
| 2 | Southern Illinois Asphalt Co., Inc. | $1,016,026 | +2.7% | |
| 3 | Samron Midwest Contracting, Inc. | $1,094,752 | +10.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Southern Illino… | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 1,543 | SQ YD | $5.32 | $6.05 | $7.75 | |
| 2 | 40200800 | AGG SURF CSE B | 51 | TON | $36.75 | $34.34 | $37.50 | |
| 3 | 40600275 | BIT MATLS PR CT | 124,456 | POUND | $0.00 | $0.00 | $0.0100 | |
| 4 | 40600982 | HMA SURF REM BUTT JT | 313 | SQ YD | $19.92 | $6.16 | $4.00 | |
| 5 | 40603085 | HMA BC IL-19.0 N70 | 5,800 | TON | $65.73 | $68.09 | $72.00 | |
| 6 | 40604052 | HMA SC IL-9.5 C N70 | 4,775 | TON | $75.07 | $87.39 | $92.50 | |
| 7 | 48100100 | AGGREGATE SHLDS A | 4,500 | TON | $32.09 | $34.34 | $32.50 | |
| 8 | 56109210 | WATER VALVES ADJUST | 1 | EACH | $44.00 | $77.36 | $100.00 | |
| 9 | 60255500 | MAN ADJUST | 3 | EACH | $200.00 | $180.51 | $250.00 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $50,181.80 | $13,751.79 | $54,800.00 | |
| 11 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $24,167.05 | $10,403.01 | $5,000.00 | |
| 12 | 70300100 | SHORT TERM PAVT MKING | 3,936 | FOOT | $1.17 | $0.7400 | $0.7500 | |
| 13 | 78001110 | PAINT PVT MK LINE 4 | 65,520 | FOOT | $0.1400 | $0.1300 | $0.1400 | |
| 14 | 78001130 | PAINT PVT MK LINE 6 | 66 | FOOT | $1.05 | $1.03 | $1.10 |