13-11118-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Depew and Owen Builders, Inc. Low bidder | $214,888 | ||
| 2 | Dees, Inc. | $217,586 | +1.3% | |
| 3 | Lake Contracting, Inc. | $217,758 | +1.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Depew and Owen … | #2 Dees, Inc. | #3 Lake Contractin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.8 | ACRE | $4,700.00 | $5,000.00 | $5,000.00 | |
| 2 | 20200100 | EARTH EXCAVATION | 918 | CU YD | $8.00 | $12.00 | $5.50 | |
| 3 | 20300100 | CHANNEL EXCAVATION | 178 | CU YD | $8.00 | $12.00 | $5.50 | |
| 4 | 20400100 | BORROW EXCAVATION | 1,391 | CU YD | $14.00 | $15.00 | $14.60 | |
| 5 | 28100807 | STONE DUMP RIP CL A4 | 370 | TON | $26.00 | $27.00 | $32.00 | |
| 6 | 40200800 | AGG SURF CSE B | 881 | TON | $22.00 | $23.00 | $20.90 | |
| 7 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $8,500.00 | $5,000.00 | $4,230.00 | |
| 8 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $2,000.00 | $600.00 | $500.00 | |
| 9 | 50105220 | PIPE CULVERT REMOV | 53 | FOOT | $2.00 | $5.00 | $2.50 | |
| 10 | 50200100 | STRUCTURE EXCAVATION | 24 | CU YD | $10.00 | $12.00 | $7.00 | |
| 11 | 50300225 | CONC STRUCT | 16.8 | CU YD | $650.00 | $625.00 | $825.00 | |
| 12 | 50300280 | CONCRETE ENCASEMENT | 2.7 | CU YD | $650.00 | $600.00 | $610.00 | |
| 13 | 50400405 | P P CONC DK BM 21 DP | 1,224 | SQ FT | $68.00 | $65.00 | $71.00 | |
| 14 | 50800105 | REINFORCEMENT BARS | 2,282 | POUND | $1.50 | $2.00 | $1.20 | |
| 15 | 50900205 | STEEL RAILING TY S1 | 104 | FOOT | $125.00 | $117.00 | $125.00 | |
| 16 | 51201400 | FUR STL PILE HP10X42 | 333 | FOOT | $24.00 | $52.00 | $51.00 | |
| 17 | 51202305 | DRIVING PILES | 333 | FOOT | $1.00 | $1.00 | $2.00 | |
| 18 | 51203400 | TEST PILE ST HP10X42 | 1 | EACH | $10,000.00 | $7,000.00 | $7,500.00 | |
| 19 | 51500100 | NAME PLATES | 1 | EACH | $350.00 | $400.00 | $350.00 | |
| 20 | 542C0220 | P CUL CL C 1 15 | 34 | FOOT | $40.00 | $20.00 | $23.00 | |
| 21 | 542C0229 | P CUL CL C 1 24 | 32 | FOOT | $45.00 | $31.00 | $35.20 | |
| 22 | 59300100 | CONTR LOW-STRENG MATL | 8.7 | CU YD | $110.00 | $100.00 | $161.00 | |
| 23 | 67100100 | MOBILIZATION | 1 | L SUM | $8,116.00 | $7,000.00 | $5,000.00 | |
| 24 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $40.00 | $40.00 | $45.00 |