21-00110-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | C-Hill Civil Contractors, Inc. Low bidder | $729,988 | ||
| 2 | Samron Midwest Contracting, Inc. | $794,794 | +8.9% | |
| 3 | Plocher Construction Company, Inc. | $1,006,000 | +37.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 C-Hill Civil Co… | #2 Samron Midwest … | #3 Plocher Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2810708 | STONE DMP RIP C A4 SP | 491 | SQ YD | $51.00 | $45.00 | $65.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $7,245.00 | $7,500.00 | $15,000.00 | |
| 3 | 20300100 | CHANNEL EXCAVATION | 280 | CU YD | $43.00 | $38.00 | $67.00 | |
| 4 | 28000400 | PERIMETER EROS BAR | 760 | FOOT | $5.00 | $0.0100 | $6.00 | |
| 5 | 28100205 | STONE RIPRAP CL A3 | 710 | TON | $54.00 | $58.00 | $72.00 | |
| 6 | 40600290 | BIT MATLS TACK CT | 432 | POUND | $0.0100 | $15.00 | $11.52 | |
| 7 | 40602965 | HMA BC IL-9.5FG N50 | 210 | TON | $206.00 | $325.00 | $293.00 | |
| 8 | 40604050 | HMA SC IL-9.5 C N50 | 94 | TON | $258.00 | $275.00 | $253.00 | |
| 9 | 48102100 | AGG WEDGE SHLD TYPE B | 300 | TON | $45.00 | $60.00 | $92.00 | |
| 10 | 50100100 | REM EXIST STRUCT | 1 | EACH | $46,500.00 | $43,000.00 | $57,398.00 | |
| 11 | 50200100 | STRUCTURE EXCAVATION | 81 | CU YD | $37.00 | $34.00 | $52.00 | |
| 12 | 50300225 | CONC STRUCT | 31 | CU YD | $950.00 | $880.00 | $1,250.00 | |
| 13 | 50300280 | CONCRETE ENCASEMENT | 3.5 | CU YD | $950.00 | $880.00 | $4,900.00 | |
| 14 | 50400605 | P P CONC DK BM 33 DP | 2,217 | SQ FT | $130.50 | $128.00 | $156.00 | |
| 15 | 50800205 | REINF BARS, EPOXY CTD | 4,320 | POUND | $2.00 | $2.00 | $2.10 | |
| 16 | 50901050 | STEEL RAILING TY SM | 161 | FOOT | $232.00 | $245.00 | $227.50 | |
| 17 | 51201400 | FUR STL PILE HP10X42 | 210 | FOOT | $45.50 | $45.00 | $65.00 | |
| 18 | 51265001 | DRILL & SET PILES (IS) | 323 | CU FT | $41.00 | $45.00 | $215.00 | |
| 19 | 51265002 | DRILL & SET PILES (IR) | 157 | CU FT | $187.00 | $265.00 | $95.00 | |
| 20 | 51500100 | NAME PLATES | 1 | EACH | $880.00 | $915.00 | $1,430.11 | |
| 21 | 58100200 | WATERPRF MEMBRANE SYS | 246 | SQ YD | $80.00 | $100.00 | $120.00 | |
| 22 | 58300100 | PC MORTAR FAIRING CSE | 475 | FOOT | $0.0100 | $3.00 | $0.0100 | |
| 23 | 59300100 | CONTR LOW-STRENG MATL | 48.2 | CU YD | $150.00 | $255.00 | $350.00 | |
| 24 | 63100087 | TRAF BAR TERM T6A | 4 | EACH | $4,900.00 | $5,150.00 | $4,795.00 | |
| 25 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,250.00 | $3,400.00 | $3,880.00 | |
| 26 | 63200310 | GUARDRAIL REMOV | 164 | FOOT | $9.00 | $10.00 | $40.00 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $30,719.43 | $45,971.40 | $70,400.00 | |
| 28 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $44.00 | $46.00 | $50.00 |