21-00057-00-BT
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | DMS Contracting, Inc. Low bidder | $355,694 | ||
| 2 | Baxmeyer Construction, Inc. | $365,558 | +2.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 DMS Contracting… | #2 Baxmeyer Constr… |
|---|---|---|---|---|---|---|---|
| 1 | X1400326 | R R FL BEACON A COMP | 2 | EACH | $13,800.00 | $7,440.00 | |
| 2 | X6024242 | INLETS SPL N1 | 1 | EACH | $3,800.00 | $2,875.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $2,100.00 | $4,275.00 | |
| 4 | X8030106 | LOC UNDERGR UTILITIES | 10 | FOOT | $305.00 | $436.00 | |
| 5 | Z0004002 | BOLLARDS | 12 | EACH | $1,200.00 | $1,410.00 | |
| 6 | 20200100 | EARTH EXCAVATION | 1,284 | CU YD | $58.00 | $39.00 | |
| 7 | 20800150 | TRENCH BACKFILL | 88 | CU YD | $44.00 | $36.00 | |
| 8 | 25000100 | SEEDING CL 1 | 1 | ACRE | $3,725.00 | $2,700.00 | |
| 9 | 25000400 | NITROGEN FERT NUTR | 90 | POUND | $2.30 | $10.25 | |
| 10 | 25000500 | PHOSPHORUS FERT NUTR | 90 | POUND | $2.30 | $5.60 | |
| 11 | 25000600 | POTASSIUM FERT NUTR | 90 | POUND | $2.30 | $5.60 | |
| 12 | 25100115 | MULCH METHOD 2 | 1 | ACRE | $7,200.00 | $2,935.00 | |
| 13 | 28000250 | TEMP EROS CONTR SEED | 100 | POUND | $6.00 | $3.50 | |
| 14 | 28000400 | PERIMETER EROS BAR | 1,308 | FOOT | $4.50 | $6.80 | |
| 15 | 28000500 | INLET & PIPE PROTECT | 5 | EACH | $298.00 | $305.00 | |
| 16 | 28001100 | TEMP EROS CONTR BLANK | 1,529 | SQ YD | $1.00 | $3.75 | |
| 17 | 35100700 | AGG BASE CSE A 8 | 2,095 | SQ YD | $12.60 | $17.00 | |
| 18 | 35101600 | AGG BASE CSE B 4 | 79 | SQ YD | $17.25 | $14.25 | |
| 19 | 40201000 | AGGREGATE-TEMP ACCESS | 20 | TON | $44.00 | $42.00 | |
| 20 | 40600275 | BIT MATLS PR CT | 4,358 | POUND | $0.8000 | $0.8500 | |
| 21 | 40604090 | HMA SC IL-9.5L C N30 | 325 | TON | $155.00 | $192.00 | |
| 22 | 42300200 | PCC DRIVEWAY PAVT 6 | 79 | SQ YD | $105.25 | $87.00 | |
| 23 | 42400100 | PC CONC SIDEWALK 4 | 1,652 | SQ FT | $10.50 | $10.50 | |
| 24 | 42400800 | DETECTABLE WARNINGS | 90 | SQ FT | $65.00 | $36.00 | |
| 25 | 44000500 | COMB CURB GUTTER REM | 88 | FOOT | $18.75 | $24.00 | |
| 26 | 44000600 | SIDEWALK REM | 2,937 | SQ FT | $3.00 | $1.75 | |
| 27 | 50105220 | PIPE CULVERT REMOV | 21 | FOOT | $20.75 | $20.35 | |
| 28 | 550A2520 | SS RG CL A 2 12 | 29 | FOOT | $82.75 | $52.00 | |
| 29 | 550A2530 | SS RG CL A 2 15 | 61 | FOOT | $111.75 | $81.00 | |
| 30 | 550A2560 | SS RG CL A 2 24 | 50 | FOOT | $120.00 | $63.50 | |
| 31 | 60218300 | MAN TA 4 DIA T1F OL | 1 | EACH | $6,165.00 | $4,080.00 | |
| 32 | 60234200 | INLETS TA T1F OL | 1 | EACH | $4,700.00 | $2,050.00 | |
| 33 | 60255500 | MAN ADJUST | 1 | EACH | $1,910.00 | $532.00 | |
| 34 | 60258200 | MAN RECON NEW T1F CL | 1 | EACH | $2,010.00 | $2,324.00 | |
| 35 | 60261530 | INLETS ADJ NEW T23F&G | 1 | EACH | $1,835.00 | $1,025.00 | |
| 36 | 60500060 | REMOV INLETS | 1 | EACH | $555.00 | $550.00 | |
| 37 | 60600605 | CONC CURB TB | 35 | FOOT | $57.00 | $61.70 | |
| 38 | 60604400 | COMB CC&G TB6.18 | 88 | FOOT | $62.00 | $90.75 | |
| 39 | 67100100 | MOBILIZATION | 1 | L SUM | $23,000.00 | $57,620.02 | |
| 40 | 72000100 | SIGN PANEL T1 | 26 | SQ FT | $67.00 | $55.50 | |
| 41 | 72900100 | METAL POST TY A | 74 | FOOT | $24.00 | $28.00 | |
| 42 | 78008250 | POLYUREA PM T1 LN 12 | 139 | FOOT | $80.00 | $83.25 | |
| 43 | 78008270 | POLYUREA PM T1 LN 24 | 12 | FOOT | $106.00 | $111.00 | |
| 44 | 78300202 | PAVMT MRKG REM WTR BL | 157 | SQ FT | $10.75 | $11.10 |