15-00237-00-PV
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Charles E. Mahoney Co. Low bidder | $622,115 | ||
| 2 | Stutz Excavating, Inc. | $658,014 | +5.8% | |
| 3 | Christ Bros. Asphalt, Inc. | $716,787 | +15.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Charles E. Maho… | #2 Stutz Excavatin… | #3 Christ Bros. As… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2020410 | EARTH EXCAVATION SPL | 5 | CU YD | $145.12 | $126.25 | $115.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $22,000.00 | $13,750.00 | $33,089.00 | |
| 3 | X7030005 | TEMP PAVT MKING REMOV | 2,515 | SQ FT | $0.0100 | $1.15 | $0.00 | |
| 4 | 20201200 | REM & DISP UNS MATL | 20 | CU YD | $35.00 | $20.00 | $70.00 | |
| 5 | 31101100 | SUB GRAN MAT B | 20 | CU YD | $50.00 | $31.00 | $85.00 | |
| 6 | 40600295 | P BIT MATLS TACK CT | 6,484 | POUND | $0.9900 | $0.8000 | $1.33 | |
| 7 | 40600837 | P LEV BIND MM N70 | 1,211 | TON | $102.70 | $105.00 | $118.43 | |
| 8 | 40600990 | TEMPORARY RAMP | 53 | SQ YD | $61.72 | $12.00 | $24.77 | |
| 9 | 40603540 | P HMA SC "D" N70 | 1,211 | TON | $106.54 | $106.00 | $118.43 | |
| 10 | 40800050 | INCIDENTAL HMA SURF | 11 | TON | $312.80 | $185.00 | $118.43 | |
| 11 | 42400100 | PC CONC SIDEWALK 4 | 4,122 | SQ FT | $10.00 | $7.70 | $15.00 | |
| 12 | 42400800 | DETECTABLE WARNINGS | 335 | SQ FT | $35.00 | $42.00 | $45.00 | |
| 13 | 44000161 | HMA SURF REM 3 | 14,408 | SQ YD | $4.23 | $2.50 | $5.04 | |
| 14 | 44000300 | CURB REM | 532 | FOOT | $14.00 | $11.00 | $40.00 | |
| 15 | 44000500 | COMB CURB GUTTER REM | 18 | FOOT | $14.00 | $15.00 | $13.50 | |
| 16 | 44000600 | SIDEWALK REM | 3,313 | SQ FT | $3.00 | $1.80 | $6.50 | |
| 17 | 44200050 | WELDED WIRE REINF | 427 | SQ YD | $12.00 | $22.20 | $7.00 | |
| 18 | 44200140 | PAVT PATCH T1 12 | 66 | SQ YD | $173.32 | $250.00 | $140.00 | |
| 19 | 44200144 | PAVT PATCH T2 12 | 142 | SQ YD | $158.43 | $250.00 | $140.00 | |
| 20 | 44200148 | PAVT PATCH T3 12 | 64 | SQ YD | $151.80 | $250.00 | $140.00 | |
| 21 | 44200929 | CL B PATCH T1 8 | 3 | SQ YD | $170.00 | $545.00 | $100.00 | |
| 22 | 44200944 | CL B PATCH T4 8 | 427 | SQ YD | $110.00 | $156.00 | $100.00 | |
| 23 | 44201298 | DOWEL BARS 1 1/4 | 624 | EACH | $16.00 | $18.30 | $20.00 | |
| 24 | 44213200 | SAW CUTS | 701 | FOOT | $3.00 | $9.45 | $0.0100 | |
| 25 | 60264100 | INL RECON NEW T15F&L | 1 | EACH | $2,400.00 | $625.00 | $2,500.00 | |
| 26 | 60600605 | CONC CURB TB | 550 | FOOT | $41.00 | $58.00 | $40.00 | |
| 27 | 67000500 | ENGR FIELD OFFICE B | 4 | CAL MO | $1,900.00 | $2,200.00 | $1,500.00 | |
| 28 | 67100100 | MOBILIZATION | 1 | L SUM | $29,000.00 | $35,000.00 | $29,963.00 | |
| 29 | 70300100 | SHORT TERM PAVT MKING | 2,610 | FOOT | $1.12 | $0.5000 | $2.16 | |
| 30 | 70300150 | SHRT TRM PAVT MK REM | 888 | SQ FT | $0.00 | $1.00 | $0.00 | |
| 31 | 70300210 | TEMP PVT MK LTR & SYM | 44 | SQ FT | $0.0100 | $15.75 | $0.00 | |
| 32 | 70300220 | TEMP PVT MK LINE 4 | 7,395 | FOOT | $0.0100 | $0.3700 | $0.00 | |
| 33 | 70300240 | TEMP PVT MK LINE 6 | 501 | FOOT | $0.0100 | $5.60 | $0.00 | |
| 34 | 70300260 | TEMP PVT MK LINE 12 | 775 | FOOT | $0.0100 | $7.60 | $0.00 | |
| 35 | 72000100 | SIGN PANEL T1 | 99 | SQ FT | $20.50 | $21.50 | $20.50 | |
| 36 | 72800100 | TELES STL SIN SUPPORT | 209 | FOOT | $12.25 | $12.85 | $12.25 | |
| 37 | 78000100 | THPL PVT MK LTR & SYM | 44 | SQ FT | $21.25 | $22.30 | $21.25 | |
| 38 | 78000200 | THPL PVT MK LINE 4 | 7,395 | FOOT | $1.10 | $1.15 | $1.10 | |
| 39 | 78000400 | THPL PVT MK LINE 6 | 501 | FOOT | $6.20 | $6.50 | $6.20 | |
| 40 | 78000600 | THPL PVT MK LINE 12 | 775 | FOOT | $7.75 | $8.15 | $7.75 | |
| 41 | 78001130 | PAINT PVT MK LINE 6 | 639 | FOOT | $4.85 | $5.10 | $4.85 | |
| 42 | 78001150 | PAINT PVT MK LINE 12 | 105 | FOOT | $8.00 | $8.40 | $8.00 |