23-00022-00-PV
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | A&A Concrete LLC Low bidder | $274,477 | ||
| 2 | McCarthy Improvement Company | $311,700 | +13.6% | |
| 3 | A & R Mechanical Service, Inc. | $312,690 | +13.9% | |
| 4 | Samron Midwest Contracting, Inc. | $315,315 | +14.9% | |
| 5 | Kieffer Bros. Construction Co., Inc. | $324,055 | +18.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 A&A Concrete LLC | #2 McCarthy Improv… | #3 A & R Mechanica… | #4 Samron Midwest … | #5 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X6026050 | SANITARY MANHOLE ADJ | 9 | EACH | $375.00 | $1,700.00 | $900.92 | $500.00 | $657.20 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $8,500.00 | $44,142.33 | $32,473.95 | $6,500.00 | $69,536.00 | |
| 3 | 42000060 | WELDED WIRE REINF | 706 | SQ YD | $14.00 | $10.25 | $14.37 | $15.00 | $15.79 | |
| 4 | 42000301 | PCC PVT 8 JOINTED | 706 | SQ YD | $155.00 | $124.00 | $134.78 | $155.00 | $136.74 | |
| 5 | 42400100 | PC CONC SIDEWALK 4 | 934 | SQ FT | $11.50 | $25.00 | $12.48 | $50.00 | $18.34 | |
| 6 | 42400800 | DETECTABLE WARNINGS | 140 | SQ FT | $45.00 | $69.00 | $28.34 | $50.00 | $50.88 | |
| 7 | 44000100 | PAVEMENT REM | 765 | SQ YD | $27.00 | $22.50 | $84.64 | $31.00 | $22.90 | |
| 8 | 44000500 | COMB CURB GUTTER REM | 290 | FOOT | $13.00 | $24.00 | $31.21 | $5.00 | $19.40 | |
| 9 | 44000600 | SIDEWALK REM | 870 | SQ FT | $4.00 | $3.50 | $4.54 | $2.50 | $4.82 | |
| 10 | 60255500 | MAN ADJUST | 1 | EACH | $550.00 | $1,800.00 | $601.72 | $250.00 | $487.60 | |
| 11 | 60260505 | INLETS ADJ NEW T3VF&G | 12 | EACH | $1,750.00 | $1,900.00 | $1,348.49 | $1,000.00 | $1,616.50 | |
| 12 | 60265700 | VV ADJUST | 3 | EACH | $1,500.00 | $330.00 | $349.40 | $100.00 | $275.60 | |
| 13 | 60603800 | COMB CC&G TB6.12 | 320 | FOOT | $82.00 | $69.00 | $66.68 | $110.00 | $84.27 | |
| 14 | 60605000 | COMB CC&G TY B-6.24 | 124 | FOOT | $93.00 | $92.00 | $81.76 | $110.00 | $96.88 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $19,500.00 | $18,900.00 | $6,672.65 | $28,503.00 | $11,660.00 | |
| 16 | 72400500 | RELOC SIN PAN ASSY TA | 6 | EACH | $450.00 | $720.00 | $257.23 | $350.00 | $90.10 | |
| 17 | 78009006 | MOD URETH PM LINE 6 | 394 | FOOT | $22.00 | $20.59 | $21.91 | $21.00 | $24.01 | |
| 18 | 78009024 | MOD URETH PM LINE 24 | 83 | FOOT | $44.00 | $82.40 | $87.68 | $36.00 | $96.08 |