24-00067-00-SW
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kieffer Bros. Construction Co., Inc. Low bidder | $215,353 | ||
| 2 | Feutz Contractors, Inc. | $297,020 | +37.9% | |
| 3 | Shores Builders, Inc. | $379,696 | +76.3% | |
| 4 | Samron Midwest Contracting, Inc. | $408,191 | +89.5% | |
| 5 | Phoenix Corporation of the Quad Cities | $428,668 | +99.1% | |
| 6 | McCarthy Improvement Company | $439,096 | +103.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kieffer Bros. C… | #2 Feutz Contracto… | #3 Shores Builders… | #4 Samron Midwest … | #5 Phoenix Corpora… | #6 McCarthy Improv… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | XX008958 | EARTH EXC SOIL MGMT | 1 | L SUM | $6,148.00 | $30,600.00 | $44,509.00 | $68,000.00 | $28,600.00 | $98,000.00 | |
| 2 | X2500900 | SEEDING CL 1 SPL | 0.75 | ACRE | $6,492.50 | $10,900.00 | $10,500.00 | $10,000.00 | $6,000.00 | $12,000.00 | |
| 3 | X6010202 | TRENCH DRAIN | 3 | EACH | $2,120.00 | $3,600.00 | $2,371.00 | $3,300.00 | $6,200.00 | $2,250.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,127.00 | $9,000.00 | $28,963.00 | $14,000.00 | $8,200.00 | $95,000.00 | |
| 5 | 42300200 | PCC DRIVEWAY PAVT 6 | 275 | SQ YD | $94.66 | $108.00 | $82.17 | $100.00 | $189.00 | $125.00 | |
| 6 | 42400100 | PC CONC SIDEWALK 4 | 11,064 | SQ FT | $9.54 | $11.10 | $13.89 | $15.00 | $14.00 | $9.75 | |
| 7 | 42400300 | PC CONC SIDEWALK 6 | 1,013 | SQ FT | $11.21 | $12.00 | $13.94 | $22.00 | $21.25 | $11.90 | |
| 8 | 44000200 | DRIVE PAVEMENT REM | 287 | SQ YD | $16.75 | $35.00 | $30.78 | $30.00 | $42.00 | $20.50 | |
| 9 | 44000600 | SIDEWALK REM | 2,981 | SQ FT | $3.82 | $4.50 | $4.20 | $4.00 | $6.00 | $3.15 | |
| 10 | 50105220 | PIPE CULVERT REMOV | 235 | FOOT | $15.58 | $23.15 | $32.08 | $6.00 | $90.00 | $24.25 | |
| 11 | 542A0217 | P CUL CL A 1 12 | 174 | FOOT | $58.83 | $62.00 | $123.78 | $111.00 | $141.00 | $64.25 | |
| 12 | 550A2320 | SS RG CL A 1 12 | 167 | FOOT | $58.83 | $63.00 | $175.26 | $111.00 | $141.00 | $65.75 | |
| 13 | 56500300 | DOM MET VLTS ADJ | 1 | EACH | $159.00 | $1,900.00 | $725.00 | $400.00 | $2,300.00 | $200.00 | |
| 14 | 60236200 | INLETS TA T8G | 2 | EACH | $1,902.70 | $2,200.00 | $2,800.00 | $4,200.00 | $4,200.00 | $3,000.00 | |
| 15 | 60265700 | VV ADJUST | 1 | EACH | $79.50 | $270.00 | $725.00 | $450.00 | $1,000.00 | $510.00 | |
| 16 | 67100100 | MOBILIZATION | 1 | L SUM | $7,950.00 | $17,000.00 | $14,090.00 | $24,000.00 | $29,500.00 | $26,200.00 |