20-00131-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $837,511 | ||
| 2 | C-Hill Civil Contractors, Inc. | $839,996 | +0.3% | |
| 3 | Lake Contracting, Inc. | $891,613 | +6.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 C-Hill Civil Co… | #3 Lake Contractin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.95 | ACRE | $6,500.00 | $7,000.00 | $7,500.00 | |
| 2 | 20200100 | EARTH EXCAVATION | 1,040 | CU YD | $16.00 | $15.50 | $17.50 | |
| 3 | 20300100 | CHANNEL EXCAVATION | 785 | CU YD | $16.00 | $15.50 | $17.50 | |
| 4 | 20400800 | FURNISHED EXCAVATION | 575 | CU YD | $27.00 | $26.00 | $27.50 | |
| 5 | 28100807 | STONE DUMP RIP CL A4 | 500 | TON | $64.00 | $63.00 | $68.00 | |
| 6 | 35101400 | AGG BASE CSE B | 1,925 | TON | $42.00 | $42.00 | $46.00 | |
| 7 | 40200800 | AGG SURF COURSE TY B | 115 | TON | $42.00 | $42.00 | $44.00 | |
| 8 | 40600275 | BIT MATLS PR CT | 4,855 | POUND | $1.15 | $1.15 | $1.20 | |
| 9 | 40600290 | BIT MATLS TACK CT | 1,345 | POUND | $0.3500 | $0.3500 | $0.3600 | |
| 10 | 40600370 | LONG JOINT SEALANT | 950 | FOOT | $16.00 | $16.00 | $17.70 | |
| 11 | 40604052 | HMA SC IL-9.5 C N70 | 540 | TON | $190.00 | $189.00 | $200.00 | |
| 12 | 44000100 | PAVEMENT REM | 2,324 | SQ YD | $4.50 | $4.20 | $5.40 | |
| 13 | 48101200 | AGGREGATE SHLDS B | 160 | TON | $65.00 | $71.00 | $119.25 | |
| 14 | 50100100 | REM EXIST STRUCT | 1 | EACH | $28,000.00 | $18,000.00 | $37,200.00 | |
| 15 | 50300225 | CONC STRUCT | 40.4 | CU YD | $800.00 | $850.00 | $850.00 | |
| 16 | 50300280 | CONCRETE ENCASEMENT | 3.5 | CU YD | $800.00 | $975.00 | $850.00 | |
| 17 | 50400505 | P P CONC DK BM 27 DP | 2,010 | SQ FT | $123.00 | $115.00 | $117.50 | |
| 18 | 50800205 | REINF BARS, EPOXY CTD | 5,660 | POUND | $2.00 | $2.50 | $1.85 | |
| 19 | 50901050 | STEEL RAILING TY SM | 138 | FOOT | $214.00 | $242.00 | $225.00 | |
| 20 | 51201600 | FUR STL PILE HP12X53 | 459 | FOOT | $55.00 | $35.00 | $104.00 | |
| 21 | 51202305 | DRIVING PILES | 459 | FOOT | $0.0100 | $0.0100 | $1.50 | |
| 22 | 51203600 | TEST PILE ST HP12X53 | 1 | EACH | $15,000.00 | $20,000.00 | $17,500.00 | |
| 23 | 51204650 | PILE SHOES | 9 | EACH | $135.00 | $137.00 | $120.00 | |
| 24 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $525.00 | $350.00 | |
| 25 | 542D0220 | P CUL CL D 1 15 | 40 | FOOT | $58.00 | $58.00 | $60.50 | |
| 26 | 542D0229 | P CUL CL D 1 24 | 200 | FOOT | $53.00 | $52.00 | $55.00 | |
| 27 | 542D0235 | P CUL CL D 1 30 | 60 | FOOT | $74.00 | $73.00 | $77.00 | |
| 28 | 542D0241 | P CUL CL D 1 36 | 280 | FOOT | $74.00 | $73.00 | $77.00 | |
| 29 | 59300100 | CONTR LOW-STRENG MATL | 58 | CU YD | $158.00 | $157.00 | $165.00 | |
| 30 | 63000001 | SPBGR TY A 6FT POSTS | 112.5 | FOOT | $32.00 | $31.50 | $35.00 | |
| 31 | 63100087 | TRAF BAR TERM T6A | 4 | EACH | $4,100.00 | $4,095.00 | $4,250.00 | |
| 32 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,400.00 | $3,360.00 | $3,500.00 | |
| 33 | 67100100 | MOBILIZATION | 1 | L SUM | $50,000.00 | $75,999.86 | $42,500.00 | |
| 34 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $52.00 | $52.00 | $50.00 |