21-00070-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $425,523 | ||
| 2 | E. T. Simonds Construction Company | $446,090 | +4.8% | |
| 3 | Kieffer Bros. Construction Co., Inc. | $475,877 | +11.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… | #3 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.1 | ACRE | $30,000.00 | $66,021.90 | $69,983.32 | |
| 2 | X5810103 | MEMB WTRPRF SYS B STR | 83 | SQ YD | $30.00 | $64.88 | $83.95 | |
| 3 | X6311205 | TRAF BAR TERM T5A SPL | 1 | EACH | $2,400.00 | $2,420.00 | $2,565.20 | |
| 4 | X6330725 | SPBGR (SHORT RADIUS) | 12.5 | FOOT | $83.00 | $82.50 | $87.45 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $7,500.00 | $9,535.45 | $5,829.02 | |
| 6 | 20200100 | EARTH EXCAVATION | 65 | CU YD | $60.00 | $244.63 | $31.80 | |
| 7 | 20700110 | POROUS GRAN EMBANK | 600 | TON | $47.00 | $62.47 | $75.74 | |
| 8 | 20900110 | POROUS GRAN BACKFILL | 31 | CU YD | $99.00 | $123.41 | $116.71 | |
| 9 | 28100807 | STONE DUMP RIP CL A4 | 235 | TON | $60.00 | $64.11 | $97.68 | |
| 10 | 35101400 | AGG BASE CSE B | 84 | TON | $45.00 | $64.30 | $72.56 | |
| 11 | 48101200 | AGGREGATE SHLDS B | 54 | TON | $45.00 | $92.02 | $64.08 | |
| 12 | 50100100 | REM EXIST STRUCT | 1 | EACH | $40,000.00 | $25,478.98 | $19,843.20 | |
| 13 | 50800205 | REINF BARS, EPOXY CTD | 34,560 | POUND | $2.00 | $1.60 | $2.51 | |
| 14 | 50900205 | STEEL RAILING TY S1 | 39 | FOOT | $310.00 | $313.50 | $332.31 | |
| 15 | 51500100 | NAME PLATES | 1 | EACH | $575.00 | $699.45 | $1,211.05 | |
| 16 | 54003000 | CONC BOX CUL | 136.9 | CU YD | $1,470.00 | $1,370.10 | $1,681.37 | |
| 17 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $4,600.00 | $4,620.00 | $4,897.20 | |
| 18 | 63200310 | GUARDRAIL REMOV | 96 | FOOT | $8.00 | $18.77 | $9.33 | |
| 19 | 67100100 | MOBILIZATION | 1 | L SUM | $25,000.00 | $50,561.31 | $11,819.00 | |
| 20 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $55.00 | $55.00 | $58.30 |