| EE | Engineer's estimate | — | ||
| 1 | Kieffer Bros. Construction Co., Inc. Low bidder | $886,837 | ||
| 2 | Samron Midwest Contracting, Inc. | $1,115,691 | +25.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kieffer Bros. C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X6026050 | SANITARY MANHOLE ADJ | 3 | EACH | $504.00 | $1,500.00 | |
| 2 | Z0000600 | ADJ FRAMES FOR INLETS | 2 | EACH | $217.00 | $1,500.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $66,483.00 | $50,000.00 | |
| 4 | Z0051500 | REM & RESET ST SIGNS | 2 | EACH | $80.00 | $500.00 | |
| 5 | 28000500 | INLET & PIPE PROTECT | 11 | EACH | $69.00 | $250.00 | |
| 6 | 40201000 | AGGREGATE-TEMP ACCESS | 271 | TON | $60.00 | $65.00 | |
| 7 | 40600290 | BIT MATLS TACK CT | 1,469 | POUND | $0.5800 | $0.6000 | |
| 8 | 40600982 | HMA SURF REM BUTT JT | 357 | SQ YD | $13.80 | $14.00 | |
| 9 | 40600990 | TEMPORARY RAMP | 28 | SQ YD | $29.15 | $30.00 | |
| 10 | 40604052 | HMA SC IL-9.5 C N70 | 247 | TON | $227.36 | $235.00 | |
| 11 | 40800050 | INCIDENTAL HMA SURF | 31 | TON | $227.36 | $235.00 | |
| 12 | 42300200 | PCC DRIVEWAY PAVT 6 | 35 | SQ YD | $100.00 | $225.00 | |
| 13 | 42300400 | PCC DRIVEWAY PAVT 8 | 251 | SQ YD | $112.00 | $255.00 | |
| 14 | 42400100 | PC CONC SIDEWALK 4 | 8,332 | SQ FT | $19.00 | $21.00 | |
| 15 | 42400300 | PC CONC SIDEWALK 6 | 3,993 | SQ FT | $20.50 | $25.00 | |
| 16 | 42400410 | PC CONC SIDEWALK 8 | 2,152 | SQ FT | $22.00 | $27.00 | |
| 17 | 42400800 | DETECTABLE WARNINGS | 339 | SQ FT | $43.00 | $50.00 | |
| 18 | 44000155 | HMA SURF REM 1 1/2 | 3,068 | SQ YD | $13.80 | $20.00 | |
| 19 | 44000200 | DRIVE PAVEMENT REM | 541 | SQ YD | $44.00 | $55.00 | |
| 20 | 44000300 | CURB REM | 367 | FOOT | $30.00 | $20.00 | |
| 21 | 44000500 | COMB CURB GUTTER REM | 2,107 | FOOT | $25.00 | $25.00 | |
| 22 | 44000600 | SIDEWALK REM | 11,218 | SQ FT | $6.00 | $6.75 | |
| 23 | 56109210 | WATER VALVES ADJUST | 1 | EACH | $79.00 | $250.00 | |
| 24 | 60235700 | INLETS TA T3F&G | 4 | EACH | $1,908.00 | $6,000.00 | |
| 25 | 60603800 | COMB CC&G TB6.12 | 740 | FOOT | $52.00 | $70.00 | |
| 26 | 60604400 | COMB CC&G TB6.18 | 2,169 | FOOT | $54.00 | $75.00 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $24,060.00 | $66,000.00 | |
| 28 | 70300100 | SHORT TERM PAVT MKING | 239 | FOOT | $1.75 | $1.80 | |
| 29 | 70300150 | SHRT TRM PAVT MK REM | 40 | SQ FT | $19.71 | $20.00 | |
| 30 | 78000200 | THPL PVT MK LINE 4 | 298 | FOOT | $9.27 | $6.00 | |
| 31 | 78000400 | THPL PVT MK LINE 6 | 467 | FOOT | $13.27 | $13.00 | |
| 32 | 78000600 | THPL PVT MK LINE 12 | 119 | FOOT | $25.65 | $20.00 |