08-09133-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | C-Hill Civil Contractors, Inc. Low bidder | $498,833 | ||
| 2 | Samron Midwest Contracting, Inc. | $514,714 | +3.2% | |
| 3 | Plocher Construction Company, Inc. | $797,900 | +60.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 C-Hill Civil Co… | #2 Samron Midwest … | #3 Plocher Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0322916 | PRO SS CONN TO EX SS | 1 | EACH | $1,040.00 | $2,500.00 | $7,100.00 | |
| 2 | X0327301 | RELOCATE EX MAILBOX | 1 | EACH | $200.00 | $400.00 | $1,900.00 | |
| 3 | X2300007 | TRAF BAR TERM TY 1 | 1 | EACH | $2,785.00 | $2,900.00 | $3,650.00 | |
| 4 | X2501000 | SEEDING CL 2 SPL | 0.65 | ACRE | $8,000.00 | $9,000.00 | $8,200.00 | |
| 5 | X2830495 | AGGREGATE DITCH SPL | 315 | TON | $72.00 | $68.00 | $125.00 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,195.00 | $12,000.00 | $15,000.00 | |
| 7 | 20100500 | TREE REMOV ACRES | 0.2 | ACRE | $54,000.00 | $4,900.00 | $35,000.00 | |
| 8 | 20200100 | EARTH EXCAVATION | 930 | CU YD | $27.00 | $22.00 | $70.00 | |
| 9 | 20300100 | CHANNEL EXCAVATION | 505 | CU YD | $30.00 | $28.00 | $70.00 | |
| 10 | 20700110 | POROUS GRAN EMBANK | 100 | TON | $45.00 | $45.00 | $48.00 | |
| 11 | 20800150 | TRENCH BACKFILL | 50 | CU YD | $60.00 | $90.00 | $95.00 | |
| 12 | 28100807 | STONE DUMP RIP CL A4 | 528 | TON | $80.00 | $68.00 | $130.00 | |
| 13 | 40200800 | AGG SURF COURSE TY B | 715 | TON | $46.00 | $48.00 | $41.41 | |
| 14 | 50100100 | REM EXIST STRUCT | 1 | EACH | $21,000.00 | $15,000.00 | $33,500.00 | |
| 15 | 50105220 | PIPE CULVERT REMOV | 94 | FOOT | $14.00 | $11.00 | $20.00 | |
| 16 | 50300225 | CONC STRUCT | 31.2 | CU YD | $1,000.00 | $1,250.00 | $2,250.00 | |
| 17 | 50300280 | CONCRETE ENCASEMENT | 2.8 | CU YD | $1,000.00 | $1,250.00 | $5,000.00 | |
| 18 | 50400405 | P P CONC DK BM 21 DP | 1,344 | SQ FT | $110.00 | $121.00 | $145.00 | |
| 19 | 50800105 | REINFORCEMENT BARS | 4,080 | POUND | $3.00 | $3.00 | $4.00 | |
| 20 | 50900205 | STEEL RAILING TY S1 | 117 | FOOT | $186.00 | $195.00 | $151.35 | |
| 21 | 51201600 | FUR STL PILE HP12X53 | 161 | FOOT | $47.00 | $175.00 | $84.00 | |
| 22 | 51202305 | DRIVING PILES | 161 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 23 | 51203600 | TEST PILE ST HP12X53 | 1 | EACH | $23,500.00 | $10,000.00 | $39,150.00 | |
| 24 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $500.00 | $763.29 | |
| 25 | 542D0217 | P CUL CL D 1 12 | 40 | FOOT | $34.00 | $55.00 | $85.00 | |
| 26 | 542D0220 | P CUL CL D 1 15 | 40 | FOOT | $38.00 | $55.00 | $90.00 | |
| 27 | 54213450 | END SECTIONS 15 | 1 | EACH | $530.00 | $350.00 | $400.00 | |
| 28 | 550B0360 | STORM SEW CL B 2 15 | 60 | FOOT | $41.00 | $80.00 | $70.00 | |
| 29 | 550B0410 | STORM SEW CL B 2 24 | 60 | FOOT | $64.00 | $100.00 | $100.00 | |
| 30 | 60100915 | PIPE DRAINS 6 | 20 | FOOT | $46.00 | $50.00 | $610.00 | |
| 31 | 60219000 | MAN TA 4 DIA T8G | 2 | EACH | $3,315.00 | $3,600.00 | $7,000.00 | |
| 32 | 63100075 | TRAF BAR TERM T5A | 2 | EACH | $1,185.00 | $1,250.00 | $1,965.00 | |
| 33 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $3,310.00 | $3,500.00 | $4,590.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $34,200.00 | $30,000.00 | $55,850.00 | |
| 35 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $44.00 | $50.00 | $50.00 |