19-00309-00-RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Howell Paving, Inc. Low bidder | $1,320,207 | ||
| 2 | Feutz Contractors, Inc. | $1,376,508 | +4.3% | |
| 3 | Kinney Contractors, Inc. | $1,653,823 | +25.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Howell Paving, … | #2 Feutz Contracto… | #3 Kinney Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0323360 | WOOD POLE REMOVAL | 1 | EACH | $209.19 | $672.62 | $1,000.00 | |
| 2 | X0327008 | REM/REL SIGN SPECIAL | 2 | EACH | $209.18 | $390.00 | $500.00 | |
| 3 | X0327618 | LANDSCAPING, SPECIAL | 1 | L SUM | $3,500.00 | $15,200.00 | $4,000.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $49,558.17 | $29,000.00 | $25,000.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 50 | CU YD | $39.91 | $95.00 | $110.00 | |
| 6 | 31101200 | SUB GRAN MAT B 4 | 152 | SQ YD | $29.24 | $22.00 | $45.00 | |
| 7 | 40600290 | BIT MATLS TACK CT | 14,020 | POUND | $1.27 | $1.30 | $1.30 | |
| 8 | 40600982 | HMA SURF REM BUTT JT | 486 | SQ YD | $4.62 | $4.00 | $11.00 | |
| 9 | 40600990 | TEMPORARY RAMP | 178 | SQ YD | $15.56 | $16.50 | $16.00 | |
| 10 | 40603085 | HMA BC IL-19.0 N70 | 1,986 | TON | $71.28 | $75.00 | $73.50 | |
| 11 | 40604062 | HMA SC IL-9.5 D N70 | 2,053 | TON | $81.48 | $86.00 | $85.00 | |
| 12 | 40800029 | BIT MATLS TACK CT | 1,078 | POUND | $1.75 | $1.85 | $2.00 | |
| 13 | 40800050 | INCIDENTAL HMA SURF | 81 | TON | $236.87 | $250.00 | $295.00 | |
| 14 | 42400200 | PC CONC SIDEWALK 5 | 6,276 | SQ FT | $17.06 | $8.00 | $12.00 | |
| 15 | 42400400 | PC CONC SIDEWALK 7 | 6,733 | SQ FT | $16.77 | $11.00 | $21.00 | |
| 16 | 42400800 | DETECTABLE WARNINGS | 906 | SQ FT | $0.0100 | $14.00 | $40.00 | |
| 17 | 44000159 | HMA SURF REM 2 1/2 | 19,720 | SQ YD | $2.23 | $1.75 | $3.00 | |
| 18 | 44000500 | COMB CURB GUTTER REM | 739 | FOOT | $24.56 | $16.00 | $21.00 | |
| 19 | 44000600 | SIDEWALK REM | 12,988 | SQ FT | $2.48 | $2.35 | $3.00 | |
| 20 | 44200074 | PAVT PATCH T1 7 | 25 | SQ YD | $351.34 | $530.00 | $180.00 | |
| 21 | 44201329 | CL C PATCH T2 8 | 658 | SQ YD | $71.57 | $107.00 | $150.00 | |
| 22 | 44201333 | CL C PATCH T3 8 | 825 | SQ YD | $71.56 | $100.00 | $130.00 | |
| 23 | 44201335 | CL C PATCH T4 8 | 4,386 | SQ YD | $71.56 | $94.00 | $102.00 | |
| 24 | 44201717 | CL D PATCH T2 6 | 26 | SQ YD | $171.41 | $118.00 | $130.00 | |
| 25 | 44201721 | CL D PATCH T3 6 | 19 | SQ YD | $139.38 | $112.00 | $128.00 | |
| 26 | 56500100 | DOM MET VLTS MOVED | 1 | EACH | $1,001.61 | $830.00 | $1,000.00 | |
| 27 | 60255500 | MAN ADJUST | 5 | EACH | $479.92 | $715.00 | $825.00 | |
| 28 | 60260100 | INLETS ADJUST | 7 | EACH | $277.33 | $715.00 | $600.00 | |
| 29 | 60266600 | VALVE BOX ADJ | 1 | EACH | $196.07 | $355.00 | $500.00 | |
| 30 | 60603800 | COMB CC&G TB6.12 | 481 | FOOT | $89.10 | $49.00 | $78.00 | |
| 31 | 60605000 | COMB CC&G TB6.24 | 258 | FOOT | $89.77 | $55.00 | $90.00 | |
| 32 | 67100100 | MOBILIZATION | 1 | L SUM | $26,228.17 | $56,300.00 | $71,500.00 | |
| 33 | 70300100 | SHORT TERM PAVT MKING | 520 | FOOT | $3.48 | $1.60 | $2.50 | |
| 34 | 70300150 | SHRT TRM PAVT MK REM | 347 | SQ FT | $5.15 | $0.3000 | $8.00 | |
| 35 | 70306210 | TEMP PVT MK L24 T3 TAPE | 87 | FOOT | $15.34 | $5.85 | $10.00 | |
| 36 | 78009004 | MOD URETH PM LINE 4 | 12,297 | FOOT | $4.05 | $3.60 | $4.50 | |
| 37 | 78009006 | MOD URETH PM LINE 6 | 273 | FOOT | $7.37 | $11.00 | $8.00 | |
| 38 | 78009024 | MOD URETH PM LINE 24 | 87 | FOOT | $30.00 | $22.00 | $32.00 |