20-00277-01-GR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $933,441 | ||
| 2 | White Construction LLC | $1,280,714 | +37.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 White Construct… |
|---|---|---|---|---|---|---|---|
| 1 | X1200050 | BOX CULVERT REMOVAL | 60 | FOOT | $300.00 | $250.00 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 2 | ACRE | $5,500.00 | $5,200.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $22,800.00 | $155,200.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 2,195 | CU YD | $18.00 | $40.00 | |
| 5 | 20400800 | FURNISHED EXCAVATION | 235 | CU YD | $20.00 | $25.00 | |
| 6 | 20800150 | TRENCH BACKFILL | 656 | CU YD | $58.00 | $100.00 | |
| 7 | 21400100 | GRADING & SHAP DITCH | 226 | FOOT | $20.00 | $8.00 | |
| 8 | 28000250 | TEMP EROS CONTR SEED | 182 | POUND | $1.00 | $10.00 | |
| 9 | 28000400 | PERIMETER EROS BAR | 184 | FOOT | $3.00 | $3.00 | |
| 10 | 28000500 | INLET & PIPE PROTECT | 4 | EACH | $110.00 | $200.00 | |
| 11 | 28100207 | STONE RIPRAP CL A4 | 1,516 | TON | $52.00 | $85.00 | |
| 12 | 28100805 | STONE DUMP RIP CL A3 | 325 | TON | $51.00 | $55.00 | |
| 13 | 40200800 | AGG SURF CSE B | 54 | TON | $36.00 | $100.00 | |
| 14 | 44004000 | PAVED DITCH REMOVAL | 2,062 | FOOT | $14.00 | $18.00 | |
| 15 | 44201796 | CL D PATCH T4 12 | 190 | SQ YD | $250.00 | $215.00 | |
| 16 | 50104400 | CONC HDWL REM | 1 | EACH | $3,000.00 | $2,000.00 | |
| 17 | 50105220 | PIPE CULVERT REMOV | 308 | FOOT | $24.00 | $50.00 | |
| 18 | 50800205 | REINF BARS, EPOXY CTD | 34,060 | POUND | $1.80 | $1.80 | |
| 19 | 54001007 | BOX CUL END SEC C7 | 2 | EACH | $3,000.00 | $6,000.00 | |
| 20 | 54002020 | EXPAN BOLTS 3/4 | 50 | EACH | $60.00 | $100.00 | |
| 21 | 54003000 | CONC BOX CUL | 182.5 | CU YD | $1,860.00 | $2,100.00 | |
| 22 | 54010504 | PCBC 5X4 | 80 | FOOT | $760.00 | $725.00 | |
| 23 | 542D0220 | P CUL CL D 1 15 | 102 | FOOT | $45.00 | $90.00 | |
| 24 | 542D0223 | P CUL CL D 1 18 | 36 | FOOT | $53.00 | $125.00 | |
| 25 | 542D0229 | P CUL CL D 1 24 | 42 | FOOT | $53.00 | $140.00 | |
| 26 | 63000003 | SPBGR TY A 9FT POSTS | 437.5 | FOOT | $44.00 | $42.24 | |
| 27 | 63000009 | SPBGR TY B 9FT POSTS | 100 | FOOT | $56.00 | $52.54 | |
| 28 | 63000030 | SPGR ATT TO CULVERT | 50 | FOOT | $189.00 | $161.75 | |
| 29 | 63100045 | TRAF BAR TERM T2 | 1 | EACH | $2,350.00 | $2,034.73 | |
| 30 | 63100167 | TR BAR TRM T1 SPL TAN | 7 | EACH | $4,600.00 | $4,012.80 | |
| 31 | 63200310 | GUARDRAIL REMOV | 738 | FOOT | $8.00 | $14.68 | |
| 32 | 67100100 | MOBILIZATION | 1 | L SUM | $55,000.00 | $76,000.00 | |
| 33 | 72501000 | TERMINAL MARKER - DA | 7 | EACH | $50.00 | $42.24 | |
| 34 | 78200005 | GRDRAIL REF TYPE A | 16 | EACH | $12.00 | $10.30 |