17-00170-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Howell Paving, Inc. Low bidder | $670,296 | ||
| 2 | Depew and Owen Builders, Inc. | $689,888 | +2.9% | |
| 3 | Kinney Contractors, Inc. | $854,852 | +27.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Howell Paving, … | #2 Depew and Owen … | #3 Kinney Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0326440 | SURF REM VAR DP (SPL) | 1,203 | SQ YD | $5.83 | $1.25 | $3.00 | |
| 2 | X2300017 | STL RAILING TY SM SPL | 134 | FOOT | $147.20 | $150.00 | $155.00 | |
| 3 | X4400196 | HMA SURF REM SPL | 3,012 | SQ YD | $2.53 | $1.25 | $1.20 | |
| 4 | X5030305 | CONC WEARING SURF 5 | 224 | SQ YD | $170.00 | $110.00 | $290.00 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $2,803.47 | $2,500.00 | $7,250.00 | |
| 6 | X7240300 | SIGN REMOVAL | 4 | EACH | $111.38 | $50.00 | $100.00 | |
| 7 | Z0046304 | P UNDR FOR STRUCT 4 | 120 | FOOT | $30.98 | $25.00 | $27.00 | |
| 8 | 20200100 | EARTH EXCAVATION | 3,723 | CU YD | $12.16 | $10.00 | $15.85 | |
| 9 | 20300100 | CHANNEL EXCAVATION | 385 | CU YD | $9.60 | $12.00 | $34.50 | |
| 10 | 25000200 | SEEDING CL 2 | 1.5 | ACRE | $1,733.33 | $1,000.00 | $2,000.00 | |
| 11 | 25000400 | NITROGEN FERT NUTR | 135 | POUND | $1.42 | $3.00 | $1.50 | |
| 12 | 25000500 | PHOSPHORUS FERT NUTR | 135 | POUND | $1.42 | $3.00 | $1.50 | |
| 13 | 25000600 | POTASSIUM FERT NUTR | 135 | POUND | $1.42 | $3.00 | $1.50 | |
| 14 | 25100115 | MULCH METHOD 2 | 1.5 | ACRE | $2,114.00 | $1,000.00 | $2,600.00 | |
| 15 | 28000250 | TEMP EROS CONTR SEED | 150 | POUND | $1.96 | $5.00 | $5.10 | |
| 16 | 28000305 | TEMP DITCH CHECKS | 275 | FOOT | $14.39 | $6.00 | $9.00 | |
| 17 | 28000400 | PERIMETER EROS BAR | 248 | FOOT | $3.10 | $6.00 | $8.00 | |
| 18 | 28000500 | INLET & PIPE PROTECT | 4 | EACH | $88.28 | $100.00 | $255.00 | |
| 19 | 28100107 | STONE RIPRAP CL A4 | 331 | SQ YD | $53.53 | $61.00 | $48.00 | |
| 20 | 28200200 | FILTER FABRIC | 331 | SQ YD | $2.30 | $3.00 | $4.50 | |
| 21 | 35101100 | AGG BASE CSE A 12 | 3,053 | SQ YD | $18.17 | $24.55 | $24.00 | |
| 22 | 40200100 | AGG SURF CSE A | 188 | TON | $30.11 | $33.00 | $40.00 | |
| 23 | 40600275 | BIT MATLS PR CT | 4,255 | POUND | $1.04 | $1.05 | $1.10 | |
| 24 | 40600290 | BIT MATLS TACK CT | 1,632 | POUND | $0.00 | $0.00 | $0.0100 | |
| 25 | 40603085 | HMA BC IL-19.0 N70 | 932 | TON | $95.98 | $96.00 | $101.00 | |
| 26 | 40604002 | HMA SC IL-9.5FG C N70 | 279 | TON | $110.47 | $111.00 | $116.00 | |
| 27 | 44000100 | PAVEMENT REM | 134 | SQ YD | $22.11 | $3.00 | $15.00 | |
| 28 | 48100500 | AGGREGATE SHLDS A 6 | 912 | SQ YD | $10.51 | $15.00 | $13.50 | |
| 29 | 50100100 | REM EXIST STRUCT | 1 | EACH | $11,452.27 | $4,000.00 | $30,000.00 | |
| 30 | 50105220 | PIPE CULVERT REMOV | 157 | FOOT | $8.76 | $3.00 | $16.50 | |
| 31 | 50200100 | STRUCTURE EXCAVATION | 52 | CU YD | $24.41 | $10.00 | $31.00 | |
| 32 | 50300225 | CONC STRUCT | 32 | CU YD | $649.02 | $800.00 | $875.00 | |
| 33 | 50300260 | BR DECK GROOVING | 217 | SQ YD | $21.20 | $16.00 | $24.00 | |
| 34 | 50300300 | PROTECTIVE COAT | 232 | SQ YD | $4.02 | $12.00 | $7.00 | |
| 35 | 50400505 | P P CONC DK BM 27 DP | 2,016 | SQ FT | $72.00 | $81.00 | $86.25 | |
| 36 | 50800205 | REINF BARS, EPOXY CTD | 7,050 | POUND | $1.63 | $2.00 | $2.15 | |
| 37 | 51200958 | FUR M S PILE 14X0.250 | 590 | FOOT | $76.24 | $36.00 | $104.00 | |
| 38 | 51202305 | DRIVING PILES | 590 | FOOT | $0.00 | $1.00 | $0.0100 | |
| 39 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $6,182.76 | $13,500.00 | $8,200.00 | |
| 40 | 51500100 | NAME PLATES | 1 | EACH | $478.25 | $438.35 | $750.00 | |
| 41 | 542D0229 | P CUL CL D 1 24 | 356 | FOOT | $31.21 | $30.00 | $38.75 | |
| 42 | 59100100 | GEOCOMPOSITE WALL DR | 38 | SQ YD | $37.42 | $50.00 | $58.00 | |
| 43 | 59300100 | CONTR LOW-STRENG MATL | 38 | CU YD | $115.60 | $90.00 | $90.00 | |
| 44 | 60100060 | CONC HDWL FOR P DRAIN | 4 | EACH | $426.96 | $350.00 | $350.00 | |
| 45 | 63000001 | SPBGR TY A 6FT POSTS | 75 | FOOT | $29.10 | $30.00 | $31.00 | |
| 46 | 63100075 | TRAF BAR TERM T5A | 2 | EACH | $1,560.00 | $1,560.00 | $1,650.00 | |
| 47 | 63100169 | TR BAR TRM T1 SPL FLR | 2 | EACH | $3,785.00 | $3,785.00 | $3,975.00 | |
| 48 | 67100100 | MOBILIZATION | 1 | L SUM | $16,424.26 | $30,000.00 | $40,000.93 | |
| 49 | 70107025 | CHANGEABLE MESSAGE SN | 60 | CAL DA | $120.78 | $100.00 | $100.00 | |
| 50 | 70300100 | SHORT TERM PAVT MKING | 116 | FOOT | $0.00 | $5.00 | $1.85 | |
| 51 | 70300150 | SHRT TRM PAVT MK REM | 39 | SQ FT | $0.00 | $5.00 | $15.50 | |
| 52 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $40.00 | $40.00 | $50.00 | |
| 53 | 78001110 | PAINT PVT MK LINE 4 | 2,342 | FOOT | $1.34 | $5.00 | $1.40 |