18-00805-00-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sangamo Construction Company Low bidder | $1,070,724 | ||
| 2 | Otto Baum Company, Inc. | $1,073,543 | +0.3% | |
| 3 | Halverson Construction Co., Inc. | $1,188,359 | +11.0% | |
| 4 | Plocher Construction Company, Inc. | $1,551,797 | +44.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sangamo Constru… | #2 Otto Baum Compa… | #3 Halverson Const… | #4 Plocher Constru… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327094 | VALVE BOX 6" | 1 | EACH | $371.17 | $353.50 | $500.00 | $500.00 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 0.25 | ACRE | $13,255.92 | $20,337.48 | $12,500.00 | $10,000.00 | |
| 3 | X5610651 | ABAN EX WM FILL CLSM | 202 | FOOT | $22.27 | $21.21 | $25.00 | $25.00 | |
| 4 | X5630712 | CONN TO EX W MAIN 12 | 2 | EACH | $2,120.95 | $2,020.00 | $2,500.00 | $2,500.00 | |
| 5 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $5,405.45 | $5,832.64 | $5,290.00 | $11,000.00 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $13,053.58 | $6,395.44 | $12,000.00 | $10,000.00 | |
| 7 | Z0046304 | P UNDR FOR STRUCT 4 | 155 | FOOT | $21.22 | $27.03 | $40.00 | $35.00 | |
| 8 | Z0056648 | SS 1 WAT MN 12 | 53 | FOOT | $80.60 | $66.32 | $65.00 | $65.00 | |
| 9 | Z0056670 | SS 2 WAT MN 18 | 43 | FOOT | $92.26 | $86.26 | $75.00 | $75.00 | |
| 10 | 20100110 | TREE REMOV 6-15 | 100 | UNIT | $86.87 | $76.75 | $48.00 | $65.00 | |
| 11 | 20100210 | TREE REMOV OVER 15 | 90 | UNIT | $86.87 | $97.21 | $112.00 | $85.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 172 | CU YD | $35.39 | $44.86 | $17.40 | $26.00 | |
| 13 | 20300100 | CHANNEL EXCAVATION | 814 | CU YD | $18.38 | $20.56 | $13.80 | $33.00 | |
| 14 | 20400800 | FURNISHED EXCAVATION | 135 | CU YD | $15.82 | $18.49 | $117.50 | $65.00 | |
| 15 | 20800150 | TRENCH BACKFILL | 22.7 | CU YD | $47.72 | $61.18 | $79.65 | $70.00 | |
| 16 | 25100635 | HD EROS CONTR BLANKET | 402 | SQ YD | $1.64 | $4.60 | $1.50 | $1.50 | |
| 17 | 28000250 | TEMP EROS CONTR SEED | 75 | POUND | $7.19 | $5.12 | $2.25 | $9.00 | |
| 18 | 28000305 | TEMP DITCH CHECKS | 10 | FOOT | $21.79 | $8.19 | $49.50 | $48.00 | |
| 19 | 28000400 | PERIMETER EROS BAR | 493 | FOOT | $4.38 | $4.75 | $7.10 | $3.00 | |
| 20 | 28000500 | INLET & PIPE PROTECT | 2 | EACH | $179.52 | $102.33 | $315.00 | $100.00 | |
| 21 | 28100109 | STONE RIPRAP CL A5 | 720 | SQ YD | $82.66 | $91.53 | $106.00 | $131.00 | |
| 22 | 28200200 | FILTER FABRIC | 720 | SQ YD | $4.20 | $3.52 | $3.30 | $2.00 | |
| 23 | 30300112 | AGG SUBGRADE IMPR 12 | 534 | SQ YD | $24.30 | $24.41 | $41.45 | $24.00 | |
| 24 | 31100300 | SUB GRAN MAT A 4 | 42 | SQ YD | $18.09 | $17.14 | $25.00 | $46.00 | |
| 25 | 40600275 | BIT MATLS PR CT | 1,199 | POUND | $1.48 | $1.43 | $1.40 | $3.25 | |
| 26 | 40600290 | BIT MATLS TACK CT | 240 | POUND | $2.92 | $2.81 | $2.75 | $3.25 | |
| 27 | 40701801 | HMA PAVT FD 6 | 380 | SQ YD | $68.29 | $65.90 | $64.40 | $86.00 | |
| 28 | 42000070 | PVT CON HMA BR APP SL | 127 | SQ YD | $162.73 | $157.02 | $153.45 | $220.00 | |
| 29 | 44000100 | PAVEMENT REM | 733 | SQ YD | $18.04 | $10.13 | $24.25 | $9.00 | |
| 30 | 44000500 | COMB CURB GUTTER REM | 85 | FOOT | $15.02 | $8.41 | $11.50 | $32.00 | |
| 31 | 48100100 | AGGREGATE SHLDS A | 51 | TON | $69.93 | $62.70 | $59.75 | $151.00 | |
| 32 | 50100100 | REM EXIST STRUCT | 1 | EACH | $26,720.64 | $28,197.86 | $60,000.00 | $151,000.00 | |
| 33 | 50200100 | STRUCTURE EXCAVATION | 297 | CU YD | $28.34 | $24.98 | $16.75 | $65.00 | |
| 34 | 50300100 | FLOOR DRAINS | 10 | EACH | $413.96 | $265.40 | $543.00 | $470.00 | |
| 35 | 50300225 | CONC STRUCT | 73.3 | CU YD | $732.55 | $559.97 | $755.00 | $600.00 | |
| 36 | 50300255 | CONC SUP-STR | 154.1 | CU YD | $1,068.94 | $1,361.82 | $1,050.00 | $1,120.00 | |
| 37 | 50300260 | BR DECK GROOVING | 513 | SQ YD | $9.50 | $8.81 | $8.70 | $8.00 | |
| 38 | 50300300 | PROTECTIVE COAT | 667 | SQ YD | $2.79 | $2.34 | $1.50 | $2.00 | |
| 39 | 50301350 | CONC SUPSTR APP SLAB | 94.7 | CU YD | $441.91 | $574.47 | $421.00 | $430.00 | |
| 40 | 50401315 | F&E PP CON BEAM IL36N | 466.3 | FOOT | $332.59 | $330.51 | $410.00 | $720.00 | |
| 41 | 50800205 | REINF BARS, EPOXY CTD | 80,580 | POUND | $1.34 | $1.23 | $1.50 | $1.65 | |
| 42 | 51201710 | FUR STL PILE HP12X84 | 480 | FOOT | $79.88 | $102.87 | $34.60 | $47.00 | |
| 43 | 51202305 | DRIVING PILES | 480 | FOOT | $0.0200 | $0.0100 | $0.1000 | $1.00 | |
| 44 | 51203710 | TEST PILE ST HP12X84 | 2 | EACH | $6,285.68 | $5,845.53 | $15,000.00 | $33,000.00 | |
| 45 | 51500100 | NAME PLATES | 1 | EACH | $540.98 | $538.08 | $750.00 | $450.00 | |
| 46 | 54213663 | PRC FLAR END SEC 18 | 1 | EACH | $1,271.64 | $1,288.60 | $1,800.00 | $1,800.00 | |
| 47 | 55100900 | STORM SEWER REM 18 | 110 | FOOT | $47.72 | $26.08 | $35.00 | $35.00 | |
| 48 | 56100900 | WATER MAIN 12 | 285 | FOOT | $275.72 | $262.60 | $300.00 | $300.00 | |
| 49 | 56105200 | WATER VALVES 12 | 1 | EACH | $3,817.71 | $3,636.00 | $6,500.00 | $6,500.00 | |
| 50 | 58600101 | GRANULAR BACKFILL STR | 105 | CU YD | $51.18 | $83.18 | $57.00 | $66.00 | |
| 51 | 59100100 | GEOCOMPOSITE WALL DR | 73 | SQ YD | $23.45 | $20.44 | $40.00 | $32.00 | |
| 52 | 60218400 | MAN TA 4 DIA T1F CL | 1 | EACH | $4,984.23 | $2,771.37 | $2,500.00 | $2,500.00 | |
| 53 | 60218500 | MAN TA 4 DIA T3F&G | 1 | EACH | $5,196.33 | $3,005.36 | $2,600.00 | $2,600.00 | |
| 54 | 60235700 | INLETS TA T3F&G | 1 | EACH | $2,651.19 | $1,378.92 | $1,900.00 | $1,900.00 | |
| 55 | 60500040 | REMOV MANHOLES | 2 | EACH | $1,060.48 | $758.74 | $1,300.00 | $1,300.00 | |
| 56 | 60605300 | COMB CC&G TB6.24 MOD | 76 | FOOT | $62.30 | $94.97 | $65.00 | $73.00 | |
| 57 | 61000050 | CONC THRUST BLOCKS | 2 | EACH | $552.29 | $812.44 | $500.00 | $500.00 | |
| 58 | 63000001 | SPBGR TY A 6FT POSTS | 287.5 | FOOT | $25.77 | $24.87 | $21.50 | $24.30 | |
| 59 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $3,913.15 | $3,775.87 | $3,300.00 | $3,690.00 | |
| 60 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $3,441.24 | $3,320.51 | $3,000.00 | $3,245.00 | |
| 61 | 63200310 | GUARDRAIL REMOV | 529 | FOOT | $6.38 | $10.95 | $10.00 | $10.00 | |
| 62 | 67100100 | MOBILIZATION | 1 | L SUM | $63,172.70 | $27,500.00 | $71,301.56 | $93,000.00 | |
| 63 | 72501000 | TERMINAL MARKER - DA | 1 | EACH | $42.42 | $40.93 | $50.00 | $40.00 | |
| 64 | 78009006 | MOD URETH PM LINE 6 | 1,380 | FOOT | $6.71 | $8.19 | $6.33 | $8.00 | |
| 65 | 78200006 | GRDRAIL REF TYPE B | 8 | EACH | $15.91 | $15.35 | $10.00 | $15.00 | |
| 66 | 78200010 | BARR WALL REF TYPE B | 8 | EACH | $10.61 | $51.16 | $12.00 | $10.00 |