17-02120-00-BR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Depew and Owen Builders, Inc. Low bidder | $546,988 | ||
| 2 | County Contractors, Inc. | $595,291 | +8.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Depew and Owen … | #2 County Contract… |
|---|---|---|---|---|---|---|---|
| 1 | 20100500 | TREE REMOV ACRES | 0.7 | ACRE | $15,000.00 | $20,000.00 | |
| 2 | 20200100 | EARTH EXCAVATION | 118 | CU YD | $25.00 | $15.00 | |
| 3 | 20300100 | CHANNEL EXCAVATION | 1,103 | CU YD | $20.00 | $10.00 | |
| 4 | 20400800 | FURNISHED EXCAVATION | 1,062 | CU YD | $35.00 | $22.00 | |
| 5 | 25000200 | SEEDING CL 2 | 0.5 | ACRE | $4,565.00 | $4,800.00 | |
| 6 | 25000400 | NITROGEN FERT NUTR | 45 | POUND | $2.00 | $1.90 | |
| 7 | 25000500 | PHOSPHORUS FERT NUTR | 45 | POUND | $2.00 | $1.90 | |
| 8 | 25000600 | POTASSIUM FERT NUTR | 45 | POUND | $2.00 | $1.90 | |
| 9 | 25100115 | MULCH METHOD 2 | 0.5 | ACRE | $4,345.00 | $4,600.00 | |
| 10 | 28000250 | TEMP EROS CONTR SEED | 100 | POUND | $5.00 | $1.00 | |
| 11 | 28000305 | TEMP DITCH CHECKS | 110 | FOOT | $18.00 | $6.50 | |
| 12 | 28000400 | PERIMETER EROS BAR | 340 | FOOT | $5.00 | $2.50 | |
| 13 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $150.00 | $224.43 | |
| 14 | 28100205 | STONE RIPRAP CL A3 | 5 | TON | $50.00 | $140.00 | |
| 15 | 28100207 | STONE RIPRAP CL A4 | 333 | TON | $60.00 | $85.00 | |
| 16 | 28200200 | FILTER FABRIC | 480 | SQ YD | $3.00 | $3.50 | |
| 17 | 40200800 | AGG SURF CSE B | 578 | TON | $36.00 | $37.00 | |
| 18 | 50100100 | REM EXIST STRUCT | 1 | EACH | $15,000.00 | $20,000.00 | |
| 19 | 50200100 | STRUCTURE EXCAVATION | 123 | CU YD | $20.00 | $15.00 | |
| 20 | 50300225 | CONC STRUCT | 60.2 | CU YD | $800.00 | $750.00 | |
| 21 | 50300280 | CONCRETE ENCASEMENT | 34.1 | CU YD | $800.00 | $1,375.00 | |
| 22 | 50400405 | P P CONC DK BM 21 DP | 2,760 | SQ FT | $73.00 | $72.00 | |
| 23 | 50800205 | REINF BARS, EPOXY CTD | 7,820 | POUND | $2.00 | $1.75 | |
| 24 | 50900205 | STEEL RAILING TY S1 | 236 | FOOT | $96.00 | $101.00 | |
| 25 | 51201600 | FUR STL PILE HP12X53 | 444 | FOOT | $27.00 | $52.00 | |
| 26 | 51201800 | FUR STL PILE HP14X73 | 555 | FOOT | $34.00 | $63.00 | |
| 27 | 51202305 | DRIVING PILES | 999 | FOOT | $1.00 | $0.1000 | |
| 28 | 51203600 | TEST PILE ST HP12X53 | 2 | EACH | $7,000.00 | $4,600.00 | |
| 29 | 51203800 | TEST PILE ST HP14X73 | 2 | EACH | $7,000.00 | $5,500.00 | |
| 30 | 51204650 | PILE SHOES | 22 | EACH | $150.00 | $200.00 | |
| 31 | 51500100 | NAME PLATES | 1 | EACH | $350.00 | $600.00 | |
| 32 | 542D0220 | P CUL CL D 1 15 | 38 | FOOT | $50.00 | $40.00 | |
| 33 | 60603800 | COMB CC&G TB6.12 | 153 | FOOT | $65.00 | $65.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $14,587.00 | $41,100.00 | |
| 35 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $40.00 | $42.25 |