19-00102-00-BR
- Let date
- Friday, June 17, 2022
- Contract
- 93786 · job page
- District
- District 6
- County
- Macoupin
- Highway
- Limits
- Replace bearings and joints at both abutments, partial depth deck patches, substructure concrete repairs and steel repairs to the structure carrying Stanton-Bunker Hill Road over West Fork of Cahokia Creek.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Keeley & Sons, Inc. Low bidder | $234,890 | ||
| 2 | Keller Construction, Inc. | $243,342 | +3.6% | |
| 3 | The Kilian Corporation | $270,537 | +15.2% | |
| 4 | White Construction LLC | $317,311 | +35.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Keeley & Sons, … | #2 Keller Construc… | #3 The Kilian Corp… | #4 White Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $6,170.00 | $4,105.00 | $10,000.00 | $6,500.00 | |
| 2 | Z0001899 | JACK & REM EX BEARING | 12 | EACH | $1,994.50 | $816.50 | $750.00 | $2,000.00 | |
| 3 | Z0001903 | STRUCT STEEL REMOV | 1,480 | POUND | $8.95 | $17.25 | $5.00 | $4.75 | |
| 4 | Z0001905 | STRUCT STEEL REPAIR | 1,570 | POUND | $17.90 | $15.00 | $17.00 | $24.50 | |
| 5 | Z0010400 | CLEANING BRIDGE SEATS | 214 | SQ FT | $21.80 | $4.34 | $17.00 | $20.00 | |
| 6 | Z0016200 | DECK SLAB REP (PART) | 23.5 | SQ YD | $397.90 | $575.00 | $625.00 | $1,200.00 | |
| 7 | 50102400 | CONC REM | 9.7 | CU YD | $1,685.00 | $2,100.00 | $3,100.00 | $4,500.00 | |
| 8 | 50300255 | CONC SUP-STR | 9.7 | CU YD | $2,790.00 | $2,700.00 | $3,800.00 | $5,000.00 | |
| 9 | 50500405 | F & E STRUCT STEEL | 3,365 | POUND | $12.15 | $5.92 | $10.50 | $12.00 | |
| 10 | 50800205 | REINF BARS, EPOXY CTD | 1,310 | POUND | $5.95 | $4.65 | $4.00 | $6.40 | |
| 11 | 52000110 | PREF JT STRIP SEAL | 74 | FOOT | $287.90 | $356.00 | $336.00 | $320.00 | |
| 12 | 52100010 | ELAST BEARING ASSY T1 | 12 | EACH | $1,390.00 | $1,580.00 | $1,550.00 | $1,500.00 | |
| 13 | 52100510 | ANCHOR BOLTS 3/4 | 24 | EACH | $169.00 | $174.00 | $143.50 | $175.00 | |
| 14 | 59000200 | EPOXY CRACK INJECTION | 33 | FOOT | $63.45 | $86.35 | $72.00 | $91.00 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $13,200.00 | $41,016.13 | $42,335.00 | $19,038.63 |