15-00138-00-BR
- Let date
- Friday, March 10, 2023
- Contract
- 93778 · job page
- District
- District 6
- County
- Montgomery
- Highway
- Limits
- Replace the bridge carrying CH 9 over Shoal Creek, 3 miles south of Coffeen. , Replace the bridge carrying CH 9 at East Fork over Shoal Creek, 3 miles south of Coffeen.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | C-Hill Civil Contractors, Inc. and Sierra Bravo, LLC JV Low bidder | $2,084,484 | ||
| 2 | Stutz Excavating, Inc. | $2,430,269 | +16.6% | |
| 3 | Plocher Construction Company, Inc. | $2,822,082 | +35.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 C-Hill Civil Co… | #2 Stutz Excavatin… | #3 Plocher Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | LR403200 | BIT MATL PR CT | 6.1 | TON | $1,860.00 | $2,070.00 | $1,860.00 | |
| 2 | LR403400 | BIT MATLS C&S CT | 27.3 | TON | $995.00 | $1,370.00 | $995.00 | |
| 3 | LR403500 | COVER COAT AGG | 145 | TON | $73.50 | $79.00 | $73.50 | |
| 4 | LR403600 | SEAL COAT AGG | 55 | TON | $70.00 | $83.65 | $70.00 | |
| 5 | X0327301 | RELOCATE EX MAILBOX | 1 | EACH | $500.00 | $225.00 | $1,600.00 | |
| 6 | X0900064 | MEMBR WTRPR SYS B STR | 53 | SQ YD | $149.20 | $125.00 | $117.00 | |
| 7 | X1200140 | PCBC SPL | 22 | FOOT | $2,000.00 | $3,450.00 | $5,000.00 | |
| 8 | X5030305 | CONC WEARING SURF 5 | 752 | SQ YD | $65.00 | $140.00 | $125.00 | |
| 9 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $10,000.00 | $18,000.00 | $35,000.00 | |
| 10 | Z0054500 | ROCK FILL | 62 | TON | $75.00 | $89.00 | $57.00 | |
| 11 | Z0076600 | TRAINEES | 1,500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 12 | Z0076604 | TRAINEES TPG | 1,500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 13 | 20200100 | EARTH EXCAVATION | 4,879 | CU YD | $14.25 | $36.00 | $21.00 | |
| 14 | 20300100 | CHANNEL EXCAVATION | 1,879 | CU YD | $25.00 | $22.00 | $23.00 | |
| 15 | 20400800 | FURNISHED EXCAVATION | 5,672 | CU YD | $25.00 | $8.20 | $46.00 | |
| 16 | 20700220 | POROUS GRAN EMBANK | 128 | CU YD | $75.00 | $41.60 | $90.00 | |
| 17 | 20800150 | TRENCH BACKFILL | 149 | CU YD | $75.00 | $62.00 | $86.00 | |
| 18 | 25000300 | SEEDING CL 3 | 3 | ACRE | $2,975.00 | $3,125.00 | $1,500.00 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 259 | POUND | $1.60 | $1.70 | $2.00 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 259 | POUND | $1.60 | $1.70 | $2.00 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 259 | POUND | $1.60 | $1.70 | $2.00 | |
| 22 | 25000700 | AGR GROUND LIMESTONE | 6 | TON | $350.00 | $367.50 | $100.00 | |
| 23 | 25100115 | MULCH METHOD 2 | 3 | ACRE | $1,100.00 | $1,155.00 | $1,240.00 | |
| 24 | 25100630 | EROSION CONTR BLANKET | 6,261 | SQ YD | $1.50 | $1.60 | $1.40 | |
| 25 | 28000250 | TEMP EROS CONTR SEED | 289 | POUND | $0.0100 | $6.00 | $8.00 | |
| 26 | 28000305 | TEMP DITCH CHECKS | 854 | FOOT | $15.00 | $12.00 | $3.00 | |
| 27 | 28000400 | PERIMETER EROS BAR | 118 | FOOT | $7.00 | $7.00 | $6.00 | |
| 28 | 28000500 | INLET & PIPE PROTECT | 6 | EACH | $150.00 | $65.00 | $250.00 | |
| 29 | 28100207 | STONE RIPRAP CL A4 | 311 | TON | $70.00 | $90.55 | $100.00 | |
| 30 | 28100209 | STONE RIPRAP CL A5 | 714 | TON | $75.00 | $99.10 | $87.00 | |
| 31 | 28100211 | STONE RIPRAP CL A6 | 324 | TON | $85.00 | $99.75 | $87.00 | |
| 32 | 28200200 | FILTER FABRIC | 1,195 | SQ YD | $3.00 | $5.40 | $7.00 | |
| 33 | 35100700 | AGG BASE CSE A 8 | 5,038 | SQ YD | $15.75 | $17.65 | $19.00 | |
| 34 | 40200300 | AGG SURF CSE A 4 | 4,308 | SQ YD | $9.00 | $11.65 | $14.00 | |
| 35 | 40200800 | AGG SURF CSE B | 337 | TON | $40.00 | $47.50 | $18.00 | |
| 36 | 42400200 | PC CONC SIDEWALK 5 | 52 | SQ FT | $75.00 | $21.00 | $145.00 | |
| 37 | 44000100 | PAVEMENT REM | 4,836 | SQ YD | $8.00 | $3.80 | $22.00 | |
| 38 | 48101200 | AGGREGATE SHLDS B | 268 | TON | $45.00 | $62.20 | $67.00 | |
| 39 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $30,000.00 | $44,000.00 | $67,000.00 | |
| 40 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $7,500.00 | $4,900.00 | $10,000.00 | |
| 41 | 50105220 | PIPE CULVERT REMOV | 149 | FOOT | $30.00 | $16.50 | $35.00 | |
| 42 | 50200100 | STRUCTURE EXCAVATION | 207 | CU YD | $30.00 | $21.40 | $32.00 | |
| 43 | 50200450 | REM/DISP UNS MATL-STR | 35 | CU YD | $85.00 | $38.20 | $38.00 | |
| 44 | 50300225 | CONC STRUCT | 132 | CU YD | $900.00 | $1,270.00 | $875.00 | |
| 45 | 50300260 | BR DECK GROOVING | 702 | SQ YD | $15.00 | $15.50 | $20.00 | |
| 46 | 50300280 | CONCRETE ENCASEMENT | 3 | CU YD | $1,000.00 | $2,350.00 | $3,500.00 | |
| 47 | 50300300 | PROTECTIVE COAT | 787 | SQ YD | $2.75 | $3.25 | $3.00 | |
| 48 | 50400605 | P P CONC DK BM 33 DP | 6,763 | SQ FT | $95.00 | $101.00 | $112.00 | |
| 49 | 50800205 | REINF BARS, EPOXY CTD | 22,170 | POUND | $1.75 | $2.15 | $2.00 | |
| 50 | 50901050 | STEEL RAILING TY SM | 452 | FOOT | $194.75 | $204.50 | $195.00 | |
| 51 | 51201600 | FUR STL PILE HP12X53 | 280 | FOOT | $45.00 | $83.00 | $59.00 | |
| 52 | 51201800 | FUR STL PILE HP14X73 | 576 | FOOT | $60.00 | $102.00 | $67.00 | |
| 53 | 51202305 | DRIVING PILES | 856 | FOOT | $0.0100 | $1.00 | $0.1000 | |
| 54 | 51203600 | TEST PILE ST HP12X53 | 2 | EACH | $10,500.00 | $7,825.00 | $23,000.00 | |
| 55 | 51203800 | TEST PILE ST HP14X73 | 2 | EACH | $11,500.00 | $8,725.00 | $23,000.00 | |
| 56 | 51500100 | NAME PLATES | 1 | EACH | $495.00 | $750.00 | $500.00 | |
| 57 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $23,700.00 | $35,000.00 | $63,000.00 | |
| 58 | 542D1060 | P CUL CL D 2 15 | 46 | FOOT | $92.00 | $66.60 | $200.00 | |
| 59 | 542D1063 | P CUL CL D 2 18 | 220 | FOOT | $58.00 | $64.35 | $123.00 | |
| 60 | 542D1069 | P CUL CL D 2 24 | 70 | FOOT | $88.00 | $121.00 | $170.00 | |
| 61 | 63000001 | SPBGR TY A 6FT POSTS | 500 | FOOT | $30.65 | $32.00 | $31.00 | |
| 62 | 63100087 | TRAF BAR TERM T6A | 4 | EACH | $4,250.00 | $4,465.00 | $4,250.00 | |
| 63 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,605.00 | $3,785.00 | $3,600.00 | |
| 64 | 66600105 | FUR ERECT ROW MARKERS | 26 | EACH | $150.00 | $385.00 | $500.00 | |
| 65 | 67100100 | MOBILIZATION | 1 | L SUM | $111,000.00 | $140,475.00 | $106,000.00 | |
| 66 | 72000100 | SIGN PANEL T1 | 23 | SQ FT | $40.00 | $35.00 | $48.00 | |
| 67 | 72400600 | RELOC SIN PAN ASSY TB | 4 | EACH | $120.00 | $225.00 | $600.00 | |
| 68 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $47.50 | $50.00 | $50.00 | |
| 69 | 78200005 | GRDRAIL REF TYPE A | 16 | EACH | $9.50 | $10.00 | $10.00 |