Bid tab 93748

Let Jul 31, 2020 · District 6 · Sangamon Sign up free

‹ Jul 2020 results

16-00048-05-PP

Let date
Friday, July 31, 2020
Contract
93748 · job page
District
District 6
County
Sangamon
Highway
Limits
Cold-in-place recycling with HMA overlay, HMA shoulders and aggregate shoulders on CH 12 from south of the I-72 Interchange to west of the Sangamon River bridge.

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 P. H. Broughton & Sons, Inc. Low bidder $2,080,789
2 Truman L. Flatt & Sons Co., Inc. $2,149,854 +3.3%
3 Illinois Valley Paving, a div of UCM, Inc. $2,465,385 +18.5%

Bid tab: unit prices 26 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 P. H. Broughton…#2 Truman L. Flatt…#3 Illinois Valley…
1LR400005 CIR-FDR EMULS ASPHALT83,518GALLON $2.22 $2.19 $2.22
2LR400750 CIP RECYCLING 5.052,199SQ YD $5.10 $5.04 $5.09
3LR403300 SURFACE PROFILE MILL52,199SQ YD $0.5000 $0.6700 $0.3700
4X0327301 RELOCATE EX MAILBOX82EACH $278.83 $249.60 $252.00
5X4404260 PAVED SHLD REMOVAL SP16,754SQ YD $5.54 $7.90 $11.95
6X7010216 TRAF CONT & PROT SPL1L SUM $43,015.71 $8,180.68 $38,236.37
7Z0010700 COLD MILLING52,199SQ YD $1.15 $1.27 $1.29
8Z0033700 LONG JOINT SEALANT21,354FOOT $2.57 $2.42 $2.45
9Z0076600 TRAINEES1,500HOUR $0.8000 $0.8000 $0.8000
10Z0076604 TRAINEES TPG1,500HOUR $15.00 $15.00 $15.00
1135101598 AGG BASE CSE B 316,754SQ YD $7.97 $7.12 $7.19
1240200800 AGG SURF CSE B90TON $53.72 $119.15 $228.89
1340201000 AGGREGATE-TEMP ACCESS208TON $25.57 $43.53 $342.66
1440600275 BIT MATLS PR CT4,414POUND $3.22 $1.44 $1.61
1540600990 TEMPORARY RAMP778SQ YD $10.69 $12.44 $8.24
1640602978 HMA BC IL-9.5 N504,515TON $78.60 $77.70 $95.74
1740604050 HMA SC IL-9.5 C N504,759TON $78.60 $85.16 $98.39
1840800050 INCIDENTAL HMA SURF277TON $226.70 $285.71 $302.68
1944000155 HMA SURF REM 1 1/23,343SQ YD $11.94 $13.38 $14.36
2044000400 GUTTER REM40FOOT $15.78 $26.25 $34.94
2148102100 AGG WEDGE SHLD TYPE B101TON $173.61 $150.80 $152.25
2248203010 HMA SHOULDERS 3 1/416,754SQ YD $15.60 $15.86 $17.13
2367100100 MOBILIZATION1L SUM $11,544.57 $27,059.63 $13,998.30
2470300100 SHORT TERM PAVT MKING3,157FOOT $1.05 $2.05 $1.09
2570300150 SHRT TRM PAVT MK REM1,052SQ FT $1.90 $3.91 $1.50
2678001120 PAINT PVT MK LINE 576,747FOOT $0.1500 $0.1500 $0.1500