(230,236)RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Open Road Paving Company LLC Low bidder | $1,725,901 | ||
| 2 | Cross Construction, Inc. | $1,893,520 | +9.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Open Road Pavin… | #2 Cross Construct… |
|---|---|---|---|---|---|---|---|
| 1 | XZ193400 | SURVEY MARKER T2 SPL | 14 | EACH | $375.00 | $800.00 | |
| 2 | X0327996 | CIP RECYCLING 3.0 | 52,318 | SQ YD | $3.35 | $3.70 | |
| 3 | X4200001 | CIR-FDR EMULS ASPHALT | 62,781 | GALLON | $2.85 | $2.80 | |
| 4 | X4400196 | HMA SURF REM SPL | 2,221 | SQ YD | $12.95 | $24.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 52,134 | SQ YD | $0.6500 | $2.40 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,100.00 | $22,000.00 | |
| 7 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $8,124.00 | $22,000.00 | |
| 8 | Z0070202 | SURVEY MARKER VAULT | 5 | EACH | $1,450.00 | $1,400.00 | |
| 9 | 35101800 | AGG BASE CSE B 6 | 1,135 | SQ YD | $40.85 | $40.00 | |
| 10 | 35800100 | PREPARATION OF BASE | 196 | SQ YD | $115.00 | $65.00 | |
| 11 | 40600290 | BIT MATLS TACK CT | 25,532 | POUND | $1.00 | $0.9000 | |
| 12 | 40600370 | LONG JOINT SEALANT | 21,666 | FOOT | $2.29 | $2.75 | |
| 13 | 40600982 | HMA SURF REM BUTT JT | 783 | SQ YD | $17.50 | $20.00 | |
| 14 | 40600985 | PCC SURF REM BUTT JT | 45 | SQ YD | $65.00 | $48.00 | |
| 15 | 40600990 | TEMPORARY RAMP | 194 | SQ YD | $41.50 | $80.00 | |
| 16 | 40604050 | HMA SC IL-9.5 C N50 | 4,463 | TON | $117.65 | $118.00 | |
| 17 | 40800025 | BIT MATLS PR CT | 2,469 | POUND | $1.00 | $3.20 | |
| 18 | 40800029 | BIT MATLS TACK CT | 1,252 | POUND | $1.00 | $4.50 | |
| 19 | 40800050 | INCIDENTAL HMA SURF | 409 | TON | $280.95 | $320.00 | |
| 20 | 42400200 | PC CONC SIDEWALK 5 | 188 | SQ FT | $36.75 | $30.00 | |
| 21 | 42400800 | DETECTABLE WARNINGS | 17 | SQ FT | $35.70 | $35.00 | |
| 22 | 44000155 | HMA SURF REM 1 1/2 | 210 | SQ YD | $33.55 | $20.00 | |
| 23 | 44000200 | DRIVE PAVEMENT REM | 104 | SQ YD | $17.70 | $44.00 | |
| 24 | 44000500 | COMB CURB GUTTER REM | 14 | FOOT | $30.00 | $55.00 | |
| 25 | 44000600 | SIDEWALK REM | 196 | SQ FT | $6.00 | $7.00 | |
| 26 | 44201765 | CL D PATCH T2 10 | 162 | SQ YD | $386.45 | $280.00 | |
| 27 | 44201769 | CL D PATCH T3 10 | 176 | SQ YD | $316.90 | $275.00 | |
| 28 | 44201771 | CL D PATCH T4 10 | 208 | SQ YD | $281.30 | $275.00 | |
| 29 | 48101200 | AGGREGATE SHLDS B | 2,158 | TON | $25.60 | $35.00 | |
| 30 | 60605000 | COMB CC&G TB6.24 | 14 | FOOT | $267.75 | $105.00 | |
| 31 | 67000500 | ENGR FIELD OFFICE B | 5 | CAL MO | $2,200.00 | $2,750.00 | |
| 32 | 67100100 | MOBILIZATION | 1 | L SUM | $100,900.00 | $68,000.00 | |
| 33 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $13,000.00 | $23,000.00 | |
| 34 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $27,500.00 | $40,000.00 | |
| 35 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $3,100.00 | $1,500.00 | |
| 36 | 70300100 | SHORT TERM PAVT MKING | 7,080 | FOOT | $2.50 | $1.50 | |
| 37 | 70300150 | SHRT TRM PAVT MK REM | 816 | SQ FT | $5.85 | $7.80 | |
| 38 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 245 | SQ FT | $2.75 | $0.0100 | |
| 39 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 51,805 | FOOT | $0.1300 | $0.0100 | |
| 40 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 150 | FOOT | $3.00 | $0.0100 | |
| 41 | 78000100 | THPL PVT MK LTR & SYM | 245 | SQ FT | $18.50 | $8.30 | |
| 42 | 78000650 | THPL PVT MK LINE 24 | 150 | FOOT | $18.25 | $8.00 | |
| 43 | 78001110 | PAINT PVT MK LINE 4 | 51,805 | FOOT | $0.1300 | $0.1600 | |
| 44 | 78011000 | GRV RCSD PM LTR & SYM | 245 | SQ FT | $17.50 | $10.00 | |
| 45 | 78011125 | GRV RCSD PVT MRKG 25 | 150 | FOOT | $16.00 | $20.00 | |
| 46 | 78100100 | RAISED REFL PAVT MKR | 300 | EACH | $35.00 | $42.00 |