22-00049-00-SW
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $138,200 | ||
| 2 | R. A. Cullinan and Son, a div of UCM, Inc. | $151,000 | +9.3% | |
| 3 | Illinois Civil Contractors, Inc. | $152,441 | +10.3% | |
| 4 | Miller and Son Construction Co. | $169,984 | +23.0% | |
| 5 | Knapp Concrete Contractors, Inc. | $181,875 | +31.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 R. A. Cullinan … | #3 Illinois Civil … | #4 Miller and Son … | #5 Knapp Concrete … |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X4240420 | PC CONC SIDEWALK 4 SP | 5,752 | SQ FT | $8.23 | $10.15 | $14.34 | $11.00 | $16.80 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $7,930.40 | $2,520.00 | $4,550.43 | $5,000.00 | $3,900.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $4,864.22 | $1,311.90 | $3,907.58 | $15,000.00 | $17,880.00 | |
| 4 | 25200100 | SODDING | 506 | SQ YD | $37.78 | $37.28 | $39.63 | $60.00 | $43.20 | |
| 5 | 35101600 | AGG BASE CSE B 4 | 616 | SQ YD | $21.78 | $22.01 | $15.68 | $30.00 | $12.96 | |
| 6 | 42400800 | DETECTABLE WARNINGS | 23 | SQ FT | $56.40 | $48.44 | $41.27 | $100.00 | $54.00 | |
| 7 | 44000500 | COMB CURB GUTTER REM | 55 | FOOT | $39.87 | $34.04 | $24.09 | $50.00 | $14.40 | |
| 8 | 44000600 | SIDEWALK REM | 2,574 | SQ FT | $4.30 | $4.70 | $2.59 | $3.00 | $4.80 | |
| 9 | 44201335 | CL C PATCH T4 8 | 45 | SQ YD | $215.29 | $180.93 | $177.26 | $200.00 | $114.00 | |
| 10 | 60603800 | COMB CC&G TB6.12 | 55 | FOOT | $86.16 | $170.96 | $87.15 | $100.00 | $72.00 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $16,114.38 | $23,212.04 | $9,146.46 | $10,000.00 | $9,600.00 | |
| 12 | 72400500 | RELOC SIN PAN ASSY TA | 1 | EACH | $433.78 | $522.60 | $930.44 | $600.00 | $540.00 |