22-00022-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $1,169,900 | ||
| 2 | Laverdiere Construction, Inc. | $1,385,179 | +18.4% | |
| 3 | Stark Excavating, Inc. | $1,394,981 | +19.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 Laverdiere Cons… | #3 Stark Excavatin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2300017 | STL RAILING TY SM SPL | 197 | FOOT | $265.79 | $323.00 | $252.00 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 0.25 | ACRE | $21,263.28 | $17,150.00 | $13,800.00 | |
| 3 | X5080530 | BAR TERMINATORS | 444 | EACH | $23.02 | $27.00 | $27.00 | |
| 4 | X6310088 | TRAF BAR TERM T6A SPL | 1 | EACH | $4,624.76 | $7,931.00 | $4,400.00 | |
| 5 | X6330725 | SPBGR (SHORT RADIUS) | 12.5 | FOOT | $106.32 | $77.50 | $102.00 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,209.50 | $9,850.00 | $5,000.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $12,731.38 | $15,000.00 | $10,000.00 | |
| 8 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 10 | 20100110 | TREE REMOV 6-15 | 104 | UNIT | $45.24 | $63.00 | $75.00 | |
| 11 | 20100210 | TREE REMOV OVER 15 | 56 | UNIT | $68.07 | $65.00 | $78.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 275 | CU YD | $53.24 | $36.00 | $76.00 | |
| 13 | 20300100 | CHANNEL EXCAVATION | 390 | CU YD | $32.10 | $41.00 | $29.00 | |
| 14 | 20400800 | FURNISHED EXCAVATION | 35 | CU YD | $49.57 | $50.00 | $55.00 | |
| 15 | 20700220 | POROUS GRAN EMBANK | 220 | CU YD | $129.37 | $115.00 | $128.00 | |
| 16 | 28000250 | TEMP EROS CONTR SEED | 250 | POUND | $3.45 | $3.00 | $4.00 | |
| 17 | 28000305 | TEMP DITCH CHECKS | 12 | FOOT | $40.10 | $19.00 | $17.50 | |
| 18 | 28000400 | PERIMETER EROS BAR | 500 | FOOT | $4.44 | $5.00 | $4.50 | |
| 19 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $536.01 | $200.00 | $128.00 | |
| 20 | 28100209 | STONE RIPRAP CL A5 | 1,150 | TON | $63.72 | $97.00 | $122.00 | |
| 21 | 28200200 | FILTER FABRIC | 685 | SQ YD | $2.67 | $3.00 | $6.60 | |
| 22 | 35100100 | AGG BASE CSE A | 486 | TON | $53.13 | $52.00 | $72.00 | |
| 23 | 40200800 | AGG SURF COURSE TY B | 78 | TON | $57.32 | $67.00 | $106.00 | |
| 24 | 40600275 | BIT MATLS PR CT | 1,479 | POUND | $1.33 | $2.50 | $1.30 | |
| 25 | 40600290 | BIT MATLS TACK CT | 465 | POUND | $1.33 | $6.40 | $1.30 | |
| 26 | 40603080 | HMA BC IL-19.0 N50 | 91 | TON | $289.18 | $312.00 | $273.00 | |
| 27 | 40604050 | HMA SC IL-9.5 C N50 | 54 | TON | $303.00 | $373.00 | $288.00 | |
| 28 | 48101200 | AGGREGATE SHLDS B | 105 | TON | $63.27 | $96.00 | $113.00 | |
| 29 | 50100100 | REM EXIST STRUCT | 1 | EACH | $28,789.14 | $25,000.00 | $75,000.00 | |
| 30 | 50105220 | PIPE CULVERT REMOV | 40 | FOOT | $19.98 | $40.00 | $20.00 | |
| 31 | 50200100 | STRUCTURE EXCAVATION | 485 | CU YD | $32.25 | $30.00 | $27.00 | |
| 32 | 50300225 | CONC STRUCT | 62.5 | CU YD | $705.78 | $1,225.00 | $1,058.00 | |
| 33 | 50300255 | CONC SUP-STR | 128.9 | CU YD | $1,309.88 | $1,600.00 | $1,453.00 | |
| 34 | 50300260 | BR DECK GROOVING | 310 | SQ YD | $19.78 | $15.00 | $18.00 | |
| 35 | 50300280 | CONCRETE ENCASEMENT | 23.3 | CU YD | $981.18 | $650.00 | $635.00 | |
| 36 | 50300300 | PROTECTIVE COAT | 415 | SQ YD | $3.76 | $8.00 | $5.25 | |
| 37 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $361,108.98 | $408,080.00 | $338,900.00 | |
| 38 | 50500505 | STUD SHEAR CONNECTORS | 1,440 | EACH | $4.52 | $5.50 | $4.80 | |
| 39 | 50800205 | REINF BARS, EPOXY CTD | 36,810 | POUND | $1.59 | $1.85 | $2.20 | |
| 40 | 51201800 | FUR STL PILE HP14X73 | 250 | FOOT | $51.14 | $70.00 | $51.25 | |
| 41 | 51265002 | DRILL & SET PILES (IR) | 294.6 | CU FT | $79.09 | $183.00 | $230.00 | |
| 42 | 51500100 | NAME PLATES | 1 | EACH | $892.51 | $900.00 | $900.00 | |
| 43 | 52100520 | ANCHOR BOLTS 1 | 20 | EACH | $204.01 | $245.00 | $157.00 | |
| 44 | 542D0223 | P CUL CL D 1 18 | 40 | FOOT | $64.80 | $78.00 | $90.00 | |
| 45 | 59100100 | GEOCOMPOSITE WALL DR | 105 | SQ YD | $19.33 | $20.00 | $38.00 | |
| 46 | 60146304 | P UNDR FOR STRUCT 4 | 170 | FOOT | $21.20 | $25.00 | $49.00 | |
| 47 | 63100087 | TRAF BAR TERM T6A | 1 | EACH | $4,305.81 | $6,456.00 | $4,100.00 | |
| 48 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $4,040.02 | $5,338.00 | $3,900.00 | |
| 49 | 67100100 | MOBILIZATION | 1 | L SUM | $70,200.00 | $57,500.00 | $80,000.00 | |
| 50 | 72501000 | TERMINAL MARKER - DA | 3 | EACH | $42.53 | $63.00 | $41.00 | |
| 51 | 78200005 | GRDRAIL REF TYPE A | 7 | EACH | $12.76 | $13.00 | $13.00 |